Home / Browse projects / Bengaluru Urban, Karnataka / THE ADWAITH BY SANJEEVINI
THE ADWAITH BY SANJEEVINI
By SANJEEVINI PROPERTIES PRIVATE LIMITED
RG-KA-34503 · RERA PRM/KA/RERA/1251/446/PR/140825/007996 · Last updated on RERA Karnataka portal: 14 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
THE ADWAITH BY SANJEEVINI is a Residential/Group Housing project by SANJEEVINI PROPERTIES PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/140825/007996 on 14 Aug 2025. Possession is promised by 31 Dec 2028. 260 of the 704 units on this registration are recorded sold or booked, and 5 of 18 construction stages are filed complete.
At a glance
Project
- NameTHE ADWAITH BY SANJEEVINI
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- 560087
- Pincode560087
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/446/PR/140825/007996
- ReraGenie IDRG-KA-34503
Builder
- NameSANJEEVINI PROPERTIES PRIVATE LIMITED
- Entity typeCompany
- CINU45309KA2016PTC097494
- GSTIN29AAXCS8174K1Z5
- Authorized SignatorySuresh H A
- DirectorsSuresh H A, Suresh H A, Umesh Gowda H A, Asha Gowda, Venkatalakshmamma, Banupriya M Y
- Project HeadSURESH ASHWATHAIAH HALASAHALLI
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on14 Aug 2025
- Promised completion31 Dec 2028
- Revised completionNone
- Buildings5 building records
- Documents filed210 files
Current status
Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| AARKA | - | - | - | 124 | 0 | 124 |
| AVANI | - | - | - | 145 | 0 | 145 |
| ANILA | - | - | - | 145 | 0 | 145 |
| AQUA | - | - | - | 145 | 0 | 145 |
| ARANYA | - | - | - | 145 | 0 | 145 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 18 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 35%.
Building: 40% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | 100% |
| RCC or MS Framed structure | 35% |
| Masonry Construction | 35% |
| Plastering inside , outside & Ceiling | 20% |
| Joinery: Doors, Windows, Ventilators etc | 35% |
| Basic work of Water supply, Sanitary and Electrification | 30% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 15% |
| Railing and Grill fixing | 15% |
| Electrification, Water supply and Sanitary Finishing | 30% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | 0% |
| Weather Proof work(tile,concrete) | 0% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 30% |
| Sewage and Drainage System | Yes | 40% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 30% |
| Energy management | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Solid waste management and disposal | Yes | 0% |
| Emergency Evacuation services | Yes | 0% |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | Yes | 0% |
| Sewage Treatment Plant (STP) | Yes | 40% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | Yes | 0% |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | Yes | 0% |
| Indoor Sports facility | Yes | 0% |
| Swimming Pool | Yes | 0% |
| Gym | Yes | 0% |
| Parks | Yes | 0% |
| Power Backup | Yes | 0% |
| Piped Gas | Yes | 0% |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 15% |
| Lifts | Yes | 15% |
| Corridor/Lobbies | Yes | 15% |
| Fire escapes | Yes | 0% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 0% |
| Basement | Yes | 100% |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 15% |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | Yes | 0% |
| Water conservation and renewable energy | Yes | 0% |
| Common storage spaces | No | Not applicable |
Land and ownership19
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| R Ramakrishnappa | - | - |
| R Ramesh | - | - |
| P R Muniraju | - | - |
| Gopalappa | - | - |
| Harish L | - | - |
| Ashok L | - | - |
| R Ramesh | - | - |
| P.R.LAKSHMANA | - | - |
| K.PRAMODINI | - | - |
| P.M. VEERABHADRAPPA | - | - |
| P.M.BHADRAPPA | - | - |
| R.SARVESHA | - | - |
| R.BEERESH | - | - |
| R.NAGESH | - | - |
| R.SUNDARESH | - | - |
| Vijayalakshmi | - | - |
| D.RATHNAMMA | - | - |
| CHETHAN N | - | - |
| D.MUNIYAPPA | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 441.52 cr | Rs 180.88 cr |
| Payment of taxes | Rs 60.80 cr | Rs 11.58 cr |
| On-site expenditure-Site Overhead | Rs 11.09 cr | Rs 47.38 cr |
| Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC) | Rs 10.00 cr | Rs 9.59 cr |
| On-site expenditure-Consultants Fees | Rs 6.00 cr | Rs 1.50 cr |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | BOMMU VEERA NARENDRANATH REDDY |
| Engineer | B E Pruthviraja |
| Chartered Accountant | Nirmala Sreenivasulu |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed210
As listed on the registration, under the names the promoter filed them with; the newest 80 of 210 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/140825/007996 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Adwaith Q2_compressed.pdf | 14 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: form-5_Archi.pdf | 14 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: form-6_Engi.pdf | 14 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 14 Oct 2026 |
| Q2 2026-27 KSPCB- MOEF (Above 50 Acres) | 14 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 14 Oct 2026 |
| Q2 2026-27 Fire and Safety | 14 Oct 2026 |
| Q2 2026-27 Airport Authority of India | 14 Oct 2026 |
| Q2 2026-27 BSNL/Telecommunication Department | 14 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Adwaith_coM_compressed.pdf | 11 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: form-5.pdf | 11 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: form-6.pdf | 11 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 11 Jul 2026 |
| Q1 2026-27 KSPCB- MOEF (Above 50 Acres) | 11 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 11 Jul 2026 |
| Q1 2026-27 Fire and Safety | 11 Jul 2026 |
| Q1 2026-27 Airport Authority of India | 11 Jul 2026 |
| Q1 2026-27 BSNL/Telecommunication Department | 11 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Adwaith by Sanjeevini_compressed.pdf | 14 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: form-5_Architecture Certificate.pdf | 14 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 10 Apr 2026 Sanjeevni.pdf | 14 Apr 2026 |
| Q4 2025-26 Water supply and sewage board | 14 Apr 2026 |
| Q4 2025-26 KSPCB- MOEF (Above 50 Acres) | 14 Apr 2026 |
| Q4 2025-26 KPTCL- BESCOM | 14 Apr 2026 |
| Q4 2025-26 Fire and Safety | 14 Apr 2026 |
| Q4 2025-26 Airport Authority of India | 14 Apr 2026 |
| Q4 2025-26 BSNL/Telecommunication Department | 14 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Adwaith Form 4_11zon.pdf | 13 Jan 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: form-5_Architecture Certificate_ Q3_12JAN2026.pdf | 13 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: form-6_Engineer Certificate_Q3_12JAN2026.pdf | 13 Jan 2026 |
| Q3 2025-26 Water supply and sewage board | 13 Jan 2026 |
| Q3 2025-26 KSPCB- MOEF (Above 50 Acres) | 13 Jan 2026 |
| Q3 2025-26 KPTCL- BESCOM | 13 Jan 2026 |
| Q3 2025-26 Fire and Safety | 13 Jan 2026 |
| Q3 2025-26 Airport Authority of India | 13 Jan 2026 |
| Q3 2025-26 BSNL/Telecommunication Department | 13 Jan 2026 |
| Covering LetterFile: Covering Letter.pdf | 11 Aug 2025 |
| Upload signed copy of with UDIN of Cash flow statement, for 2021-22, 2022-23 & 2023-24File: Cash Flow Statement 2021-22.pdf | 11 Aug 2025 |
| Upload signed copy of with UDIN of Cash flow statement, for 2021-22, 2022-23 & 2023-24File: Cash Flow Statement 2022-23.pdf | 11 Aug 2025 |
| Upload signed copy of with UDIN of Cash flow statement, for 2021-22, 2022-23 & 2023-24File: Cash Flow Statement 2023-24.pdf | 11 Aug 2025 |
| Upload sanction planFile: Plan Approval 1.pdf | 11 Aug 2025 |
| Upload sanction planFile: Plan Approval 2.pdf | 11 Aug 2025 |
| Upload sanction planFile: Plan Approval 3.pdf | 11 Aug 2025 |
| Upload sanction planFile: Plan Approval 4.pdf | 11 Aug 2025 |
| Upload sanction planFile: Plan Approval 5.pdf | 11 Aug 2025 |
| Loan amount should be deposited into RERA designated account as per notification dated 19/07/2023( sFile: Final Confirmation for Transfer of Project Loan Amount.pdf | 11 Aug 2025 |
| What are all sources of fund to complete the project with supporting documentsFile: Final SOURCES OF FUNDS TO COMPLETE THE PROJECT.pdf | 11 Aug 2025 |
| Building License from Local Authority Original CopyFile: Building License.pdf | 11 Aug 2025 |
| ADLR Certified survey sketch Certifying the Boundary of the Proposed land-Original survey sketchFile: ADLR Sketch.pdf | 11 Aug 2025 |
| Approved building planFile: Plan Approval 1.pdf | 11 Aug 2025 |
| Approved building planFile: Plan Approval 2.pdf | 11 Aug 2025 |
| Approved building planFile: Plan Approval 3.pdf | 11 Aug 2025 |
| Approved building planFile: Plan Approval 4.pdf | 11 Aug 2025 |
| Approved building planFile: Plan Approval 5.pdf | 11 Aug 2025 |
| Upload all original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Plan Approval 1.pdf | 11 Aug 2025 |
| Upload all original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Plan Approval 2.pdf | 11 Aug 2025 |
| Upload all original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Plan Approval 3.pdf | 11 Aug 2025 |
| Upload all original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Plan Approval 4.pdf | 11 Aug 2025 |
| Upload all original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Plan Approval 5.pdf | 11 Aug 2025 |
| Upload commencement certificateFile: Commencement Certificate.pdf | 11 Aug 2025 |
| Demarcation of proposed land in Approved Master plan Certified by the concern authorityFile: Plan Approval 1.pdf | 11 Aug 2025 |
| Demarcation of proposed land in Approved Master plan Certified by the concern authorityFile: Plan Approval 2.pdf | 11 Aug 2025 |
| Demarcation of proposed land in Approved Master plan Certified by the concern authorityFile: Plan Approval 3.pdf | 11 Aug 2025 |
| Demarcation of proposed land in Approved Master plan Certified by the concern authorityFile: Plan Approval 4.pdf | 11 Aug 2025 |
| Demarcation of proposed land in Approved Master plan Certified by the concern authorityFile: Plan Approval 5.pdf | 11 Aug 2025 |
| Demarcation of proposed land in original Village map certified by the concern authorityFile: Village Map showing Proposed Site.pdf | 11 Aug 2025 |
| KSPCB NOCFile: KSPCB NOC.pdf | 11 Aug 2025 |
| Approval/NOC under section 14 of the KTCP ActFile: KTCP NOC.pdf | 11 Aug 2025 |
| Update Development Details (Plot Dimension wise break up,height of the tower as per the approved plaFile: Project Development Details.pdf | 11 Aug 2025 |
| Not uploaded Engineer certificate Form-3,once again informed to kindly upload the Engineer certificaFile: Form - 3, Engineer.pdf | 11 Aug 2025 |
| kindly upload structural stability certificate duly signed by the Structural engineer , clearly statFile: STABILITY CERTIFICATE.pdf | 11 Aug 2025 |
| kindly upload project specification with signatureFile: Adwaith Project Specification.pdf | 11 Aug 2025 |
| kindly upload the brief project estimation details with Engineer signatureFile: Brief Estimated COst Merged.pdf | 11 Aug 2025 |
| upload the Land cost calculation sheet as per the guidance value(Self-attested copy)File: SPPL Guidance Value_merged.pdf | 11 Aug 2025 |
| kindly upload the STP design drawing certified by the Engineer as per the guidelinesFile: Signed STP 210KLD.pdf | 11 Aug 2025 |
| kindly upload the STP design drawing certified by the Engineer as per the guidelinesFile: Signed STP 300KLD.pdf | 11 Aug 2025 |
| Phase wise Development SketchFile: Phase wise Development Sketch.pdf | 11 Aug 2025 |
| Total units DetailsFile: Final Total Units Details_Updated.xlsx | 11 Aug 2025 |
| Submission of Tower DetailsFile: Submission of Tower Details.pdf | 11 Aug 2025 |
| Upload Cash flow statement, for 2021-22, 2022-23 & 2023-24File: Cash flow 2021-22.pdf | 11 Jul 2025 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| Sanjeevini Vaibhav | Site No. 167, Pattandur Agrahara Village, K R Puram Hobli, Whitefield, Bangalore -560066 | Completed | - | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep THE ADWAITH BY SANJEEVINI on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 83 registered projects within 2 km.
Prestige Lavender Fields
Prestige Office Ventures
Brigade Sanctuary
Brigade Enterprises Ltd
MYHNA VISTARA
MYHNA PROPERTIES PRIVATE LIMITED
ABHEE AARIA
ABHEE VENTURES PRIVATE LIMITED
ABHEE CITY URBAN GLENN PHASE II
ABHEE VENTURES PRIVATE LIMITED
GODREJ PARK RETREAT
Godrej Properties Limited
See every Bengaluru Urban project, with the district possession charts
Builder: SANJEEVINI PROPERTIES PRIVATE LIMITED
SANJEEVINI PROPERTIES PRIVATE LIMITED has 1 registration on RERA Karnataka, including THE ADWAITH BY SANJEEVINI. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if THE ADWAITH BY SANJEEVINI is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of THE ADWAITH BY SANJEEVINI?
The registered promoter entity is SANJEEVINI PROPERTIES PRIVATE LIMITED, a company as per the filing. Its CIN U45309KA2016PTC097494 and GSTIN 29AAXCS8174K1Z5 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in THE ADWAITH BY SANJEEVINI?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at THE ADWAITH BY SANJEEVINI?
The professionals named in the filing: Architect: BOMMU VEERA NARENDRANATH REDDY; Engineer: B E Pruthviraja; Chartered Accountant: Nirmala Sreenivasulu. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in THE ADWAITH BY SANJEEVINI?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.