Home / Browse projects / Bengaluru Urban, Karnataka / Brigade Sanctuary

Registration approved Litigation declared Residential/Group Housing project

Brigade Sanctuary

By Brigade Enterprises Ltd

RG-KA-43917 · RERA PRM/KA/RERA/1251/446/PR/041123/006372 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • Litigation declared, 1 case
  • 3 complaints at RERA Karnataka

Clear

  • Completion date never moved
  • Separate project account declared
Dec 2028Possession promisedno revision filed
1 of 18Construction stages donefurthest along: Dadoing, 95%
1 of 1,275Units unsoldnot recorded sold or booked
3Complaints at RERA Karnatakaon this registration
Jump to the 164 documents Report an error

Brigade Sanctuary is a Residential/Group Housing project by Brigade Enterprises Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/041123/006372 on 4 Nov 2023. Possession is promised by 31 Dec 2028. 1,274 of the 1,275 units on this registration are recorded sold or booked, and 1 of 18 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameBrigade Sanctuary
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560087
  • Pincode560087
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/041123/006372
  • ReraGenie IDRG-KA-43917

Builder

  • NameBrigade Enterprises Ltd
  • Entity typeCompany
  • CINL85110KA1995PLC019126
  • GSTIN29AAACB7459F1ZI
  • Authorized SignatoryViswa Prathap Desu
  • Managing DirectorPavitra Shankar
  • DirectorsM. R. Jaishankar, Bijou Kurien, Aroon Raman, Lakshmi Venkatachalam, Pradeep Kumar Panja, Venkatesh Panchapagesan, Amar Mysore, Pavitra Shankar, Nirupa Shankar, Roshin Mathew, Velloor Venkatakrishnan Ranganathan, Pradyumna Krishnakumar
  • Project HeadAhamed Liyaqyath Ali
  • Other registrations45 more →
  • No longer live1 withdrawn or revoked
  • Declared earlier projects67 →

Key dates

this monthRegisteredNov 2023PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on4 Nov 2023
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings8 building records
  • Documents filed164 files

Current status

100%1274 of 1,275 units booked
4.8%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---1090109
B---1640164
C---1640164
D---1090109
E---1630163
F---1610161
G---2140214
H---1910191

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 18 construction stages are filed complete. The stage furthest along is Dadoing, at 95%.

Building: 76% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work90%
Upto Plinth Level90%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)90%
Retaining wall (All types)90%
RCC or MS Framed structure90%
Masonry Construction90%
Plastering inside , outside & Ceiling90%
Joinery: Doors, Windows, Ventilators etc68%
Basic work of Water supply, Sanitary and Electrification65%
Dadoing, Skirting, Flooring, Tiles work (All types)95%
Railing and Grill fixing80%
Electrification, Water supply and Sanitary Finishing53%
Painting45%
Fire prevention and fire fighting fitting and fixture with network93%
Weather Proof work(tile,concrete)30%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work76%
Internal and External work including landscapes as per sanctioned drawings40%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes40%
Sewage and Drainage SystemYes60%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes80%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes65%
Electricity supply transformer and substationYes5%
Storm water drainsYes25%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes75%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes40%
GymYes0%
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes95%
LiftsYes40%
Corridor/LobbiesYes65%
Fire escapesYes40%
Common entrance and exit for the building/common portico/foyer/verandahYes15%
BasementYes85%
TerraceYes95%
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership5

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area60,399 sq m
Named landowners5
LandownerVillageDistrict
ZARAH IQBAL--
ZARAH IQBAL--
ZARAH IQBAL--
ZARAH IQBAL--
ZARAH IQBAL--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 803.81 cr
Cost incurredRs 38.72 cr
Spent of the estimate4.82%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 618.73 crRs 38.41 cr
Payment of taxesRs 111.82 crRs 33,333
On-site expenditure-Site OverheadRs 40.80 crRs 28.75 lakh
Principal sum and interest payable to financial institutions-Scheduled BanksRs 29.93 cr-
On-site expenditure-Salaries of workersRs 1.77 crRs 1.24 lakh
On-site expenditure-Consultants FeesRs 70.85 lakhRs 49,932
Payment of PremiumsRs 3.07 lakhRs 2,160
Payment of cessRs 2.70 lakhRs 1,905

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTILAK THOMAS -THOMAS ARCHITECTS
EngineerArun Karanth N
Chartered AccountantR. Srinivasan

Litigation declared1

CaseCourtStatus
677Sr Civil Judge - Anekal-

Complaints filed with RERA Karnataka3

Case no.ComplainantRespondentFiled
01329/2024-Brigade Enterprises Ltd19/12/2024
01151/2025-Brigade Enterprises Ltd11/09/2025
01421/2025-Brigade Enterprises Ltd21/11/2025

Documents filed164

As listed on the registration, under the names the promoter filed them with; the newest 80 of 164 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/041123/006372 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Brigade Sanctuary - Form 4 - Q2.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Brigade Sanctuary - Form 5 - Q2.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Brigade Sanctuary - Form 6 - Q2.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Brigade Sanctuary - Form 4 - Q1.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Brigade Sanctuary - Form 5 - Q1.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Brigade Sanctuary - Form 6 - Q1.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Brigade Sancturary - Form 4 - Q4.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Sanctuary - Form 5 - Q4.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Brigade Sanctuary - Form 6 - Q4.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Brigade Sanctuary - Form 4 - Q3.pdf14 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Brigade Sanctuary - Form 5 - Q3.pdf14 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Brigade Sanctuary - Form 6 - Q3.pdf14 Jan 2026
Q3 2025-26 Water supply and sewage board14 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)14 Jan 2026
Q3 2025-26 KPTCL- BESCOM14 Jan 2026
Q3 2025-26 Fire and Safety14 Jan 2026
Q3 2025-26 Airport Authority of India14 Jan 2026
MR No 32/2004-05 - Sy No 27File: MR No - 32.pdf28 Oct 2023
Uploaded ECFile: EC 27.pdf28 Oct 2023
Uploaded ECFile: EC - Sy No 33-1.pdf28 Oct 2023
Uploaded ECFile: EC - Sy No 34-1.pdf28 Oct 2023
Sale deed of Sy No 33/1File: Sale Deed - Sy No 33-1 - Clear Copy_compressed (1).pdf28 Oct 2023
BDA Zonal RegularationFile: BDA Zonal Regulation 2015.pdf28 Oct 2023
Architects certificate with valid COA numberFile: Brigade Sanctuary - Form 2.pdf28 Oct 2023
Change of land useFile: BDA - Change of Land Use.pdf28 Oct 2023
ZR Showing the Lake BufferFile: BDA Zonal Regulation 2015.pdf28 Oct 2023
FAR ClarificationFile: Brigade Enterprises Limited.pdf28 Oct 2023
Carpet area calculationFile: Brigade Sanctuary - Carpet Area Details.pdf28 Oct 2023
Engineer Certificate - Self AttestedFile: Structural Engineer Certificat.pdf28 Oct 2023
Agreement for SaleFile: Brigade Sanctuary - Agreement to Sell.pdf28 Oct 2023
Proforma of the Allotment letterFile: Brigade Sanctuary - Proforma Allotment.pdf28 Oct 2023
Power supply NOC Fee Paid ReceiptFile: Fee Paid Receipt.pdf28 Oct 2023
site planFile: Brigade Sanctuary - Site Plan.pdf28 Oct 2023
Amenities Plan 1File: Amenities Block - Plan 1.pdf28 Oct 2023
Amenities Plan 2File: Amenities Block - Plan 2.pdf28 Oct 2023
20th Floor PlanFile: Brigade Sanctuary - 20th Floor Plan Refugee Level.pdf28 Oct 2023
Basement Plan 1File: Brigade Sanctuary - B1 Floor Plan.pdf28 Oct 2023
Basement Plan 2File: Brigade Sanctuary - B2 Floor Plan.pdf28 Oct 2023
First Floor PlanFile: Brigade Sanctuary - First Floor Plan.pdf28 Oct 2023
Ground Floor PlanFile: Brigade Sanctuary - Ground Floor.pdf28 Oct 2023
Section and SpecificationFile: Brigade Sanctuary - Section and Specifications.pdf28 Oct 2023
Section and ElevationFile: Brigade Sanctuary - Section Elevation.pdf28 Oct 2023
Terrace FloorFile: Brigade Sanctuary - Terrace Floor.pdf28 Oct 2023
First PlanFile: Brigade Sanctuary - Typical Floor Plan.pdf28 Oct 2023
Ground FloorFile: Brigade Sanctuary - First Floor Plan.pdf28 Oct 2023
Reply to the QueriesFile: Reply to Queries.pdf28 Oct 2023
RTC, survey 27-
Mutation, survey 27-
Encumbrance Certificate, survey 27-
Conversion/Alienation Order, survey 27-
Sale/Title/Gift Deed, survey 27-
JDA, survey 27-
Khatha, survey 27-
RTC, survey 33/1-
Mutation, survey 33/1-
Encumbrance Certificate, survey 33/1-
Conversion/Alienation Order, survey 33/1-
Sale/Title/Gift Deed, survey 33/1-
JDA, survey 33/1-
Khatha, survey 33/1-
RTC, survey 34/1-

How this compares with Bengaluru Urban

100%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Brigade Sanctuary on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmBrigade SanctuaryOther 22Dot size: filed unitsN

Filed coordinates, straight-line distance. 22 registered projects within 2 km.

Builder: Brigade Enterprises Ltd

Brigade Enterprises Ltd has 46 registrations on RERA Karnataka, including Brigade Oasis - Phase 1 and Brigade Atmosphere- Phase 1. Its filings declare 67 earlier projects, 41 of them declared completed. Litigation is declared on 10 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Brigade Sanctuary is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Brigade Sanctuary?

The registered promoter entity is Brigade Enterprises Ltd, a company as per the filing. Its CIN L85110KA1995PLC019126 and GSTIN 29AAACB7459F1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Brigade Sanctuary?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Brigade Sanctuary?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Brigade Sanctuary?

The professionals named in the filing: Architect: TILAK THOMAS -THOMAS ARCHITECTS; Engineer: Arun Karanth N; Chartered Accountant: R. Srinivasan. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Brigade Sanctuary?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Brigade Sanctuary. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Brigade Sanctuary to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.