Home / Browse projects / Bengaluru Urban, Karnataka / SV POLARIS

Registration approved No litigation declared Residential/Group Housing project

SV POLARIS

By SV HOUSING

RG-KA-00087 · RERA PRM/KA/RERA/1251/446/PR/101224/007281 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2026Possession promisedno revision filed
11 of 18Construction stages donefurthest along: Basic work of Water supply, 96%
80 of 223Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 133 documents Report an error

SV POLARIS is a Residential/Group Housing project by SV HOUSING in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/101224/007281 on 10 Dec 2024. Possession is promised by 21 Dec 2026. 143 of the 223 units on this registration are recorded sold or booked, and 11 of 18 construction stages are filed complete.

At a glance

Project

  • NameSV POLARIS
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560087
  • Pincode560087
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/101224/007281
  • ReraGenie IDRG-KA-00087

Builder

  • NameSV HOUSING
  • Entity typePartnership Firm
  • GSTIN29ACMFS5438G1ZM
  • Authorized SignatoryS Venkatesh
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredDec 2024PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on10 Dec 2024
  • Promised completion21 Dec 2026
  • Revised completionNone
  • Buildings3 building records
  • Documents filed133 files

Current status

64%143 of 223 units booked
77.0%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Shree---74074
Veeram---74074
Geetham---75075

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 18 construction stages are filed complete. The stage furthest along is Basic work of Water supply, at 96%.

Building: 97% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc90%
Basic work of Water supply, Sanitary and Electrification96%
Dadoing, Skirting, Flooring, Tiles work (All types)93%
Railing and Grill fixing93%
Electrification, Water supply and Sanitary Finishing93%
Painting88%
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings96%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes93%
Sewage and Drainage SystemYes96%
Water conservation/rain water harvesting/recharge of ground waterYes96%
Energy managementYes70%
Fire protection and fire safety requirementsYes100%
Solid waste management and disposalYes87%
Emergency Evacuation servicesYes90%
Internal Roads & FootpathsYes96%
Electricity supply transformer and substationYes90%
Storm water drainsYes90%
Use of renewable energyYes84%
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingYes96%
Street LightingYes100%
ElectricityYes75%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes45%
Club HouseYes96%
Community HallYes75%
Outdoor Sports facilityYes75%
Indoor Sports facilityYes70%
Swimming PoolYes96%
GymYes96%
ParksYes90%
Power BackupYes96%
Piped GasNoNot applicable
Water and SanitationYes90%
Air ConditioningNoNot applicable
StaircasesYes97%
LiftsYes84%
Corridor/LobbiesYes93%
Fire escapesYes100%
Common entrance and exit for the building/common portico/foyer/verandahYes96%
BasementYes93%
TerraceYes96%
Outer WallYes100%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,172 sq m
Named landowners1
LandownerVillageDistrict
SV HOUSING--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 184.29 cr
Cost incurredRs 141.93 cr
Spent of the estimate77.01%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 124.09 crRs 117.47 cr
On-site expenditure-Salaries of workersRs 27.60 crRs 4.79 cr
Payment of taxesRs 15.00 crRs 12.89 cr
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 7.00 crRs 1.22 cr
On-site expenditure-Site OverheadRs 5.50 crRs 95.06 lakh
On-site expenditure-Consultants FeesRs 5.10 crRs 88.37 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKUSHAL NB
EngineerManohar N
Chartered AccountantIVS Raju

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed133

As listed on the registration, under the names the promoter filed them with; the newest 80 of 133 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/101224/007281 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA certificate (QU).pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect (QU).pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer (QU).pdf15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA certificate (QU)_compressed.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect (QU).pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer (QU).pdf15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA certificate (QU).pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect (QU).pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer (QU).pdf15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA certificate_compressed.pdf15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect (QU).pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer (QU).pdf15 Jan 2026
Extract of Master PlanFile: 04 Master Plan Demarkation Panathur 12 LU-1.pdf10 Dec 2024
Village MapFile: 05 Village Map Demarkation Panathur 12 RC.pdf10 Dec 2024
Single Plot Plan ClarificationFile: 01 Single Plot Plan Clarification.pdf10 Dec 2024
Single Plot Order ClarificationFile: 02 Single Plot Order Clarification.pdf10 Dec 2024
KSPCB Area and Unit ClarificationFile: 03 KSPCB NOC Area & No of Units Clarifiaction.pdf10 Dec 2024
Sources of funds to complete the project with supportive documentsFile: Source of Funds with Supporting Documents.pdf27 Nov 2024
Balance sheet, profit and loss & ITR of 2021-22, and 2022-2023 and 2023-24File: 01 ITR 2021-22, 22-23, 23-24.pdf23 Oct 2024
Sources of fundsFile: 02 Source of Funds.pdf23 Oct 2024
CA KYC and membership registration certificateFile: 03 CA KYC documents.pdf23 Oct 2024
Single Plot planFile: 04 Single Plot Plan Clarification.pdf23 Oct 2024
Single Plot work orderFile: 05 Single Plot Order Clarification.pdf23 Oct 2024
Commencement certificateFile: 06 CC Clarifiaction.pdf23 Oct 2024
KSPCB noc Area / no of Units ClarificationsFile: 07 KSPCB NOC Area & No of Units Clarifiaction.pdf23 Oct 2024
Master plan DemarcationFile: 08 Master Plan Demarkation Panathur 12 LU-1.pdf23 Oct 2024
Village map demarcationFile: 09 Village Map Demarkation Panathur 12 RC.pdf23 Oct 2024
Tower details clarificationFile: 10 Tower details clarification.pdf23 Oct 2024
Proforma of Agreement for SaleFile: 11 Agreement of Sale Proforma.pdf23 Oct 2024
STP design drawingFile: 12 STP RERA.pdf23 Oct 2024
HAL NOCFile: 13 HAL NOC.pdf23 Oct 2024
Bank statements of 100%, 70%, and 30% accountFile: 01 Bank Statement.pdf1 Oct 2024
Bank affidavitFile: 02 Bank Affidavit.pdf1 Oct 2024
Balance sheet, profit and loss account & ITR of 2020-21, 2021-22, and 2022-2023 with scheduleFile: 03 Financial Statement SVH.pdf1 Oct 2024
CA KYC self-attestedFile: 04 CA KYC documents.pdf1 Oct 2024
Sources of fundsFile: 05 Souce of Funds.pdf1 Oct 2024
Form 1 CA certificateFile: 06 Form 1 CA Certificate.pdf1 Oct 2024
Partners financial statementsFile: 07 Partners Financial Statement.pdf1 Oct 2024
B-karab land ClarificationFile: 08 B Karab ADLR.pdf1 Oct 2024
ADLR sketchFile: 09 ADLR Sketch for boundaries.pdf1 Oct 2024
Single Plot layout planFile: 10&11 single plot.pdf1 Oct 2024
Single Plot layout plan work orderFile: 10&11 single plot.pdf1 Oct 2024
Building LicenseFile: 12 Building License.pdf1 Oct 2024
Approved building planFile: 13&15 Approval Plan.pdf1 Oct 2024
Phase wise demarcation drawingsFile: 14 NA Phasewise.pdf1 Oct 2024
Sanctioned drawings, floor plan, sectional drawings and elevationsFile: 13&15 Approval Plan.pdf1 Oct 2024
Architects certificateFile: 16 Form 2 Architect Certificate.pdf1 Oct 2024
Commencement certificateFile: 17 Commencement Certificate.pdf1 Oct 2024
Area of KSPCB ClarificationFile: 18 Clarification of KSPCB NOC.pdf1 Oct 2024
Master plan ExtractFile: 19 Master plan.pdf1 Oct 2024
Village mapFile: 20 Village Map.pdf1 Oct 2024
Change of land useFile: 21 Change of Land use NA.pdf1 Oct 2024
Area detailsFile: 22 Area Statement.pdf1 Oct 2024
Amenities and Common area detailsFile: 23 Common Area & Amenties Details.pdf1 Oct 2024
Estimated cost of constructionFile: 24 Estimated Cost of Construction.pdf1 Oct 2024
Project specificationFile: 25&33 Project Specification.pdf1 Oct 2024
3(1) notarized affidavitFile: 26 Violation Affidavit.pdf1 Oct 2024
Proforma of the Allotment letterFile: 27 Allotment Letter.pdf1 Oct 2024
Proforma of Agreement for saleFile: 27 Sale Agreement Draft.pdf1 Oct 2024
Self-attested BESCOM NOC and BWSSB NOCFile: 28 BESCOM & BWSSB NOC Self Attested.pdf1 Oct 2024
STP designFile: 29 STP Design.pdf1 Oct 2024
Structural safety certificateFile: 30 Structural Stability Certificate.pdf1 Oct 2024
Land cost calculationFile: 31 Guideline Value Calculation.pdf1 Oct 2024
Source of water supplyFile: 32 Source of Water.pdf1 Oct 2024
Project specificationFile: 25&33 Project Specification.pdf1 Oct 2024
RTC, survey 12/1-
Mutation, survey 12/1-
Encumbrance Certificate, survey 12/1-
Conversion/Alienation Order, survey 12/1-
Sale/Title/Gift Deed, survey 12/1-
Khatha, survey 12/1-
Registration CertificateFile: 01 FIRM REG CERTIFICATE.jpg-
GST CertificateFile: 01 FIRM REG CERTIFICATE.jpg-
Partnership DeedFile: 07 SV Housing Partnership deed.pdf-
Partner Details-
Partner Details-
Partner Details-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
SV GRANDURSy no 101/2 & 101/3, Kammasandra, Attibele, AnekalCompleted-No date filed

How this compares with Bengaluru Urban

64%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SV POLARIS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSV POLARISOther 71Dot size: filed unitsN

Filed coordinates, straight-line distance. 71 registered projects within 2 km.

Builder: SV HOUSING

SV HOUSING has 2 registrations on RERA Karnataka, including SV GRANDUR and SV POLARIS. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SV POLARIS is delayed beyond 21 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SV POLARIS?

The registered promoter entity is SV HOUSING, a partnership firm as per the filing. Its GSTIN 29ACMFS5438G1ZM can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SV POLARIS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SV POLARIS?

The professionals named in the filing: Architect: KUSHAL NB; Engineer: Manohar N; Chartered Accountant: IVS Raju. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SV POLARIS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SV POLARIS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SV POLARIS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.