Home / Browse projects / Bengaluru Urban, Karnataka / SV POLARIS
SV POLARIS
By SV HOUSING
RG-KA-00087 · RERA PRM/KA/RERA/1251/446/PR/101224/007281 · Last updated on RERA Karnataka portal: 15 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
SV POLARIS is a Residential/Group Housing project by SV HOUSING in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/101224/007281 on 10 Dec 2024. Possession is promised by 21 Dec 2026. 143 of the 223 units on this registration are recorded sold or booked, and 11 of 18 construction stages are filed complete.
At a glance
Project
- NameSV POLARIS
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- 560087
- Pincode560087
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/446/PR/101224/007281
- ReraGenie IDRG-KA-00087
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on10 Dec 2024
- Promised completion21 Dec 2026
- Revised completionNone
- Buildings3 building records
- Documents filed133 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Shree | - | - | - | 74 | 0 | 74 |
| Veeram | - | - | - | 74 | 0 | 74 |
| Geetham | - | - | - | 75 | 0 | 75 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 18 construction stages are filed complete. The stage furthest along is Basic work of Water supply, at 96%.
Building: 97% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | 100% |
| RCC or MS Framed structure | 100% |
| Masonry Construction | 100% |
| Plastering inside , outside & Ceiling | 100% |
| Joinery: Doors, Windows, Ventilators etc | 90% |
| Basic work of Water supply, Sanitary and Electrification | 96% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 93% |
| Railing and Grill fixing | 93% |
| Electrification, Water supply and Sanitary Finishing | 93% |
| Painting | 88% |
| Fire prevention and fire fighting fitting and fixture with network | 100% |
| Weather Proof work(tile,concrete) | 100% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 100% |
| Internal and External work including landscapes as per sanctioned drawings | 96% |
Progress on shared amenities40
As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 93% |
| Sewage and Drainage System | Yes | 96% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 96% |
| Energy management | Yes | 70% |
| Fire protection and fire safety requirements | Yes | 100% |
| Solid waste management and disposal | Yes | 87% |
| Emergency Evacuation services | Yes | 90% |
| Internal Roads & Footpaths | Yes | 96% |
| Electricity supply transformer and substation | Yes | 90% |
| Storm water drains | Yes | 90% |
| Use of renewable energy | Yes | 84% |
| Sewage Treatment Plant (STP) | Yes | 100% |
| Parks & Tree planting | Yes | 96% |
| Street Lighting | Yes | 100% |
| Electricity | Yes | 75% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 45% |
| Club House | Yes | 96% |
| Community Hall | Yes | 75% |
| Outdoor Sports facility | Yes | 75% |
| Indoor Sports facility | Yes | 70% |
| Swimming Pool | Yes | 96% |
| Gym | Yes | 96% |
| Parks | Yes | 90% |
| Power Backup | Yes | 96% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 90% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 97% |
| Lifts | Yes | 84% |
| Corridor/Lobbies | Yes | 93% |
| Fire escapes | Yes | 100% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 96% |
| Basement | Yes | 93% |
| Terrace | Yes | 96% |
| Outer Wall | Yes | 100% |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SV HOUSING | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 124.09 cr | Rs 117.47 cr |
| On-site expenditure-Salaries of workers | Rs 27.60 cr | Rs 4.79 cr |
| Payment of taxes | Rs 15.00 cr | Rs 12.89 cr |
| On-site expenditure-Cost Of Services(Water, Electricity, Sewage) | Rs 7.00 cr | Rs 1.22 cr |
| On-site expenditure-Site Overhead | Rs 5.50 cr | Rs 95.06 lakh |
| On-site expenditure-Consultants Fees | Rs 5.10 cr | Rs 88.37 lakh |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | KUSHAL NB |
| Engineer | Manohar N |
| Chartered Accountant | IVS Raju |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed133
As listed on the registration, under the names the promoter filed them with; the newest 80 of 133 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/101224/007281 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA certificate (QU).pdf | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect (QU).pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer (QU).pdf | 15 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA certificate (QU)_compressed.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architect (QU).pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer (QU).pdf | 15 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Jul 2026 |
| Q1 2026-27 Fire and Safety | 15 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA certificate (QU).pdf | 15 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect (QU).pdf | 15 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer (QU).pdf | 15 Apr 2026 |
| Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 15 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA certificate_compressed.pdf | 15 Jan 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect (QU).pdf | 15 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer (QU).pdf | 15 Jan 2026 |
| Extract of Master PlanFile: 04 Master Plan Demarkation Panathur 12 LU-1.pdf | 10 Dec 2024 |
| Village MapFile: 05 Village Map Demarkation Panathur 12 RC.pdf | 10 Dec 2024 |
| Single Plot Plan ClarificationFile: 01 Single Plot Plan Clarification.pdf | 10 Dec 2024 |
| Single Plot Order ClarificationFile: 02 Single Plot Order Clarification.pdf | 10 Dec 2024 |
| KSPCB Area and Unit ClarificationFile: 03 KSPCB NOC Area & No of Units Clarifiaction.pdf | 10 Dec 2024 |
| Sources of funds to complete the project with supportive documentsFile: Source of Funds with Supporting Documents.pdf | 27 Nov 2024 |
| Balance sheet, profit and loss & ITR of 2021-22, and 2022-2023 and 2023-24File: 01 ITR 2021-22, 22-23, 23-24.pdf | 23 Oct 2024 |
| Sources of fundsFile: 02 Source of Funds.pdf | 23 Oct 2024 |
| CA KYC and membership registration certificateFile: 03 CA KYC documents.pdf | 23 Oct 2024 |
| Single Plot planFile: 04 Single Plot Plan Clarification.pdf | 23 Oct 2024 |
| Single Plot work orderFile: 05 Single Plot Order Clarification.pdf | 23 Oct 2024 |
| Commencement certificateFile: 06 CC Clarifiaction.pdf | 23 Oct 2024 |
| KSPCB noc Area / no of Units ClarificationsFile: 07 KSPCB NOC Area & No of Units Clarifiaction.pdf | 23 Oct 2024 |
| Master plan DemarcationFile: 08 Master Plan Demarkation Panathur 12 LU-1.pdf | 23 Oct 2024 |
| Village map demarcationFile: 09 Village Map Demarkation Panathur 12 RC.pdf | 23 Oct 2024 |
| Tower details clarificationFile: 10 Tower details clarification.pdf | 23 Oct 2024 |
| Proforma of Agreement for SaleFile: 11 Agreement of Sale Proforma.pdf | 23 Oct 2024 |
| STP design drawingFile: 12 STP RERA.pdf | 23 Oct 2024 |
| HAL NOCFile: 13 HAL NOC.pdf | 23 Oct 2024 |
| Bank statements of 100%, 70%, and 30% accountFile: 01 Bank Statement.pdf | 1 Oct 2024 |
| Bank affidavitFile: 02 Bank Affidavit.pdf | 1 Oct 2024 |
| Balance sheet, profit and loss account & ITR of 2020-21, 2021-22, and 2022-2023 with scheduleFile: 03 Financial Statement SVH.pdf | 1 Oct 2024 |
| CA KYC self-attestedFile: 04 CA KYC documents.pdf | 1 Oct 2024 |
| Sources of fundsFile: 05 Souce of Funds.pdf | 1 Oct 2024 |
| Form 1 CA certificateFile: 06 Form 1 CA Certificate.pdf | 1 Oct 2024 |
| Partners financial statementsFile: 07 Partners Financial Statement.pdf | 1 Oct 2024 |
| B-karab land ClarificationFile: 08 B Karab ADLR.pdf | 1 Oct 2024 |
| ADLR sketchFile: 09 ADLR Sketch for boundaries.pdf | 1 Oct 2024 |
| Single Plot layout planFile: 10&11 single plot.pdf | 1 Oct 2024 |
| Single Plot layout plan work orderFile: 10&11 single plot.pdf | 1 Oct 2024 |
| Building LicenseFile: 12 Building License.pdf | 1 Oct 2024 |
| Approved building planFile: 13&15 Approval Plan.pdf | 1 Oct 2024 |
| Phase wise demarcation drawingsFile: 14 NA Phasewise.pdf | 1 Oct 2024 |
| Sanctioned drawings, floor plan, sectional drawings and elevationsFile: 13&15 Approval Plan.pdf | 1 Oct 2024 |
| Architects certificateFile: 16 Form 2 Architect Certificate.pdf | 1 Oct 2024 |
| Commencement certificateFile: 17 Commencement Certificate.pdf | 1 Oct 2024 |
| Area of KSPCB ClarificationFile: 18 Clarification of KSPCB NOC.pdf | 1 Oct 2024 |
| Master plan ExtractFile: 19 Master plan.pdf | 1 Oct 2024 |
| Village mapFile: 20 Village Map.pdf | 1 Oct 2024 |
| Change of land useFile: 21 Change of Land use NA.pdf | 1 Oct 2024 |
| Area detailsFile: 22 Area Statement.pdf | 1 Oct 2024 |
| Amenities and Common area detailsFile: 23 Common Area & Amenties Details.pdf | 1 Oct 2024 |
| Estimated cost of constructionFile: 24 Estimated Cost of Construction.pdf | 1 Oct 2024 |
| Project specificationFile: 25&33 Project Specification.pdf | 1 Oct 2024 |
| 3(1) notarized affidavitFile: 26 Violation Affidavit.pdf | 1 Oct 2024 |
| Proforma of the Allotment letterFile: 27 Allotment Letter.pdf | 1 Oct 2024 |
| Proforma of Agreement for saleFile: 27 Sale Agreement Draft.pdf | 1 Oct 2024 |
| Self-attested BESCOM NOC and BWSSB NOCFile: 28 BESCOM & BWSSB NOC Self Attested.pdf | 1 Oct 2024 |
| STP designFile: 29 STP Design.pdf | 1 Oct 2024 |
| Structural safety certificateFile: 30 Structural Stability Certificate.pdf | 1 Oct 2024 |
| Land cost calculationFile: 31 Guideline Value Calculation.pdf | 1 Oct 2024 |
| Source of water supplyFile: 32 Source of Water.pdf | 1 Oct 2024 |
| Project specificationFile: 25&33 Project Specification.pdf | 1 Oct 2024 |
| RTC, survey 12/1 | - |
| Mutation, survey 12/1 | - |
| Encumbrance Certificate, survey 12/1 | - |
| Conversion/Alienation Order, survey 12/1 | - |
| Sale/Title/Gift Deed, survey 12/1 | - |
| Khatha, survey 12/1 | - |
| Registration CertificateFile: 01 FIRM REG CERTIFICATE.jpg | - |
| GST CertificateFile: 01 FIRM REG CERTIFICATE.jpg | - |
| Partnership DeedFile: 07 SV Housing Partnership deed.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| SV GRANDUR | Sy no 101/2 & 101/3, Kammasandra, Attibele, Anekal | Completed | - | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep SV POLARIS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 71 registered projects within 2 km.
Prestige Lavender Fields
Prestige Office Ventures
Brigade Sanctuary
Brigade Enterprises Ltd
MYHNA VISTARA
MYHNA PROPERTIES PRIVATE LIMITED
ABHEE AARIA
ABHEE VENTURES PRIVATE LIMITED
ABHEE CITY URBAN GLENN PHASE II
ABHEE VENTURES PRIVATE LIMITED
GODREJ PARK RETREAT
Godrej Properties Limited
See every Bengaluru Urban project, with the district possession charts
Builder: SV HOUSING
SV HOUSING has 2 registrations on RERA Karnataka, including SV GRANDUR and SV POLARIS. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if SV POLARIS is delayed beyond 21 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SV POLARIS?
The registered promoter entity is SV HOUSING, a partnership firm as per the filing. Its GSTIN 29ACMFS5438G1ZM can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SV POLARIS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SV POLARIS?
The professionals named in the filing: Architect: KUSHAL NB; Engineer: Manohar N; Chartered Accountant: IVS Raju. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SV POLARIS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.