Home / Browse projects / Gandhinagar, Gujarat / SUPER CITY PHASE 2 HONOUR

Valid until 30 Dec 2021 Residential/Group Housing project

SUPER CITY PHASE 2 HONOUR

By SHRINIVAS ORGANISORS PRIVATE LIMITED

RG-GJ-43166 · RERA PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA00507/A1R/280921 · Last updated on GujRERA portal: 24 Dec 2021

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Dec 2021Possession promisedno revision filed
7 of 7Construction stages doneevery applicable stage filed complete
32 of 134Units unsoldnot recorded sold or booked
Jump to the 39 documents Report an error

SUPER CITY PHASE 2 HONOUR is a Residential/Group Housing project by SHRINIVAS ORGANISORS PRIVATE LIMITED in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA00507/A1R/280921 on 18 Oct 2017. Possession is promised by 30 Dec 2021. 102 of the 134 units on this registration are recorded sold or booked, and 7 of 7 construction stages are filed complete.

At a glance

Project

  • NameSUPER CITY PHASE 2 HONOUR
  • TypeResidential/Group Housing
  • Location
    • BHADAJ DENTAL COLLEGE ROAD
    • NEAR SCIENCE CITY
    • Santej
    • Kalol
    • Gandhinagar
    • 382721
  • Pincode382721
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA00507/A1R/280921
  • ReraGenie IDRG-GJ-43166

Builder

  • NameSHRINIVAS ORGANISORS PRIVATE LIMITED
  • Entity typeCOMPANY
  • Other registrations13 more →
  • Past their filed date8

Key dates

this monthRegisteredOct 2017PromisedDec 2021

Key facts

Registration and timeline

  • StatusValid until 30 Dec 2021
  • Registered on18 Oct 2017
  • Promised completion30 Dec 2021
  • Revised completionNone
  • Buildings1 building record
  • Documents filed39 files

Current status

76%102 of 134 units booked
114.2%Of the estimated cost spent so far

Figures as on 24 Dec 2021, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
HONOUR---1340134

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 24 Dec 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 7 construction stages are filed complete.

HONOUR: 100% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 24 Dec 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area27,047 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 43.72 cr
Cost incurredRs 49.92 cr
Spent of the estimate114.19%
BuildingWingEstimatedIncurred
HONOURNARs 43.72 crRs 49.92 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJHARNA NAGORI
EngineerNARESH K SHAH

Documents filed39

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA00507/A1R/280921 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)24 Dec 2021
Architect's certificate (Form 1)23 Dec 2021
Engineer's certificate (Form 2)23 Dec 2021
Engineer's certificate annexure23 Dec 2021
Site photograph, HONOUR23 Dec 2021
Site photograph, HONOUR23 Dec 2021
RERA registration certificate18 Oct 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

76%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep SUPER CITY PHASE 2 HONOUR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Santej1,600+ in Gandhinagar

2 kmSUPER CITY PHASE 2 HONOUOther 15Dot size: filed unitsN

Filed coordinates, straight-line distance. 15 registered projects within 2 km.

Builder: SHRINIVAS ORGANISORS PRIVATE LIMITED

SHRINIVAS ORGANISORS PRIVATE LIMITED has 14 registrations on GujRERA, including SUPER CITY PHASE 1 and SUPER CITY PHASE 2 DREAM. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if SUPER CITY PHASE 2 HONOUR is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SUPER CITY PHASE 2 HONOUR?

The registered promoter entity is SHRINIVAS ORGANISORS PRIVATE LIMITED, a company as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SUPER CITY PHASE 2 HONOUR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SUPER CITY PHASE 2 HONOUR?

The professionals named in the filing: Architect: JHARNA NAGORI; Engineer: NARESH K SHAH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUPER CITY PHASE 2 HONOUR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUPER CITY PHASE 2 HONOUR. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUPER CITY PHASE 2 HONOUR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.