SUMUK SQUARE-2

By sumuk projects

RG-KA-74336 · RERA PRM/KA/RERA/1251/472/PR/150525/007747 · Last updated on RERA Karnataka portal: 13 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Apr 2029Possession promisedno revision filed
2 of 17Construction stages donefurthest along: Sub-structure flooring (Parking Floor, 90%
28 of 79Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 112 documents Report an error

SUMUK SQUARE-2 is a Residential/Group Housing project by sumuk projects in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/472/PR/150525/007747 on 15 May 2025. Possession is promised by 30 Apr 2029. 51 of the 79 units on this registration are recorded sold or booked, and 2 of 17 construction stages are filed complete.

At a glance

Project

  • NameSUMUK SQUARE-2
  • TypeResidential/Group Housing
  • Location
    • Yelahanka
    • Bengaluru Urban
    • 560098
  • Pincode560098
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/472/PR/150525/007747
  • ReraGenie IDRG-KA-74336

Builder

  • Namesumuk projects
  • Entity typePartnership Firm
  • GSTIN29AERFS0908Q1Z3
  • Authorized SignatoryYASHWANTH KUMAR H
  • Other registrations1 more →

Key dates

this monthRegisteredMay 2025PromisedApr 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on15 May 2025
  • Promised completion30 Apr 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed112 files

Current status

65%51 of 79 units booked
70.4%Of the estimated cost spent so far

Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
sumuk square-2---79079

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 17 construction stages are filed complete. The stage furthest along is Sub-structure flooring (Parking Floor, at 90%.

Building: 35% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level70%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)90%
Retaining wall (All types)80%
RCC or MS Framed structure50%
Masonry Construction50%
Plastering inside , outside & Ceiling50%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes0%
Storm water drainsNoNot applicable
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingNoNot applicable
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityYes0%
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes90%
LiftsYes0%
Corridor/LobbiesYes90%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes50%
TerraceYes45%
Outer WallYes0%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,059 sq m
Named landowners1
LandownerVillageDistrict
SUBRAMANYAM RPM--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 25.75 cr
Cost incurredRs 18.12 cr
Spent of the estimate70.39%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 25.00 crRs 16.76 cr
Payment of taxesRs 15.00 lakh-
Payment of PremiumsRs 15.00 lakh-
On-site expenditure-Salaries of workersRs 10.00 lakhRs 55.07 lakh
On-site expenditure-Consultants FeesRs 10.00 lakh-
On-site expenditure-Site OverheadRs 10.00 lakhRs 22.79 lakh
Payment of cessRs 10.00 lakh-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 5.00 lakhRs 12.45 lakh
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)-Rs 46.11 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Architectmayur g kulkarni
Engineerramesh s
Chartered AccountantKVN PHANIENDRA REDDY

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed112

As listed on the registration, under the names the promoter filed them with; the newest 80 of 112 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/472/PR/150525/007747 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA CERTIFICATE SUMUK 02.pdf13 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Architect Cerficate Sumuk 02.pdf13 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate Sumuk 02.pdf13 Oct 2026
Q2 2026-27 Water supply and sewage board13 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Oct 2026
Q2 2026-27 KPTCL- BESCOM13 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Sumuk Square 02 CA Certificate_compressed.pdf11 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Sumuk Square-2 Archiect's Certificates.pdf11 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Sumuk Square-2 Engineer's Certificates.pdf11 Jul 2026
Q1 2026-27 Water supply and sewage board11 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)11 Jul 2026
Q1 2026-27 KPTCL- BESCOM11 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA CERTIFICATE-SUMUK SQUARE - 2_compressed.pdf25 Jun 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Sumuk Projects-2- Architect's Certification.pdf25 Jun 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Sumuk Projects-2 Engineer's Certification.pdf25 Jun 2026
Q4 2025-26 Water supply and sewage board25 Jun 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)25 Jun 2026
Q4 2025-26 KPTCL- BESCOM25 Jun 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Project Name-SUMUK SQUARE - 2-PHASE-2 (1)_compressed.pdf20 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Sumuk Phase 02 Architect certificate.pdf20 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Sumuk Phase 02 Engineer Certicate.pdf20 Feb 2026
Q3 2025-26 Water supply and sewage board20 Feb 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)20 Feb 2026
Q3 2025-26 KPTCL- BESCOM20 Feb 2026
PROFIT AND LOSS AND BALANCE SHEETFile: Profit and Losss Financials.pdf8 May 2025
SOURCES OF FUNDFile: SUMUK SOURCE OF FUNDS DETAILS4.pdf8 May 2025
NON LITIGATION AFFIDAVITFile: NON LITIGATION AFFIDAVIT,.pdf8 May 2025
Single Plot layout plan ClarificationFile: SINGLE LAYOUT PLAN Clarification.pdf8 May 2025
Building LicenseFile: BUILDING LICENCE8.pdf8 May 2025
ADLR Certified survey sketchFile: ADLR9.pdf8 May 2025
BUILDING PLAN, SANCTIONED DRAWING,FLOOR PLAN,SECTIONAL DRAWINGSFile: BUILDING PLAN10 and 11.PDF8 May 2025
Commencement certificate ClarificationFile: Commencement Clarification.pdf8 May 2025
Approved Master planFile: RMP13.pdf8 May 2025
Village mapFile: VILLAGE MAP14.pdf8 May 2025
Brief estimated cost of constructionFile: COST 15.pdf8 May 2025
Proforma of the Allotment letterFile: allotment letter16.pdf8 May 2025
BWSSB NOCFile: BWSSB WATER NOC.pdf8 May 2025
STP design drawingFile: STP.pdf8 May 2025
Guidance VlaueFile: GUIDELINES VALUE SUB REG OFF19.pdf8 May 2025
Partnership registration certificateFile: Partnership Registration Cert.pdf8 May 2025
CA FORM1 CertificateFile: CA FORM1 SUMUK SQUARE.pdf8 May 2025
PARTNERSHIP DEEDFile: PARTNERSHIP DEED-1.pdf7 May 2025
PROFIT AND LOSS AND BALANCE SHEETFile: Profit and Losss Financials.pdf7 May 2025
SOURCES OF FUNDFile: SUMUK SOURCE OF FUNDS DETAILS-4.pdf7 May 2025
BUILDING LICENCEFile: BUILDING LICENCE-8.pdf7 May 2025
ADLR SKETCHFile: ADLR-9.pdf7 May 2025
BUILDING PLANFile: BUILDING PLAN-10 and 11.PDF7 May 2025
SANCTIONED DRAWING,FLOOR PLAN,SECTIONAL DRAWINGSFile: BUILDING PLAN-10 and 11.PDF7 May 2025
DEMARCATION IN MASTER PLANFile: RMP-13.pdf7 May 2025
VILLAGE MAPFile: VILLAGE MAP-14.pdf7 May 2025
COST OF CONSTRUCTION BY ENGINEERFile: COST -15.pdf7 May 2025
ALLOTMENT LETTERFile: allotment letter-16.pdf7 May 2025
BWSSB NOCFile: BWSSB WATER NOC.pdf7 May 2025
STP DRAWINGSFile: STP.pdf7 May 2025
GUIDANCE VALUEFile: GUIDELINES VALUE SUB REG OFF-19.pdf7 May 2025
WATER SUPPLYFile: borewel-1-(20)_merged.pdf7 May 2025
RTC, survey SY NO-55/5 AND 55/23 , KHATHA NO-384/1163/1159/55/5,23-
Mutation, survey SY NO-55/5 AND 55/23 , KHATHA NO-384/1163/1159/55/5,23-
Encumbrance Certificate, survey SY NO-55/5 AND 55/23 , KHATHA NO-384/1163/1159/55/5,23-
Conversion/Alienation Order, survey SY NO-55/5 AND 55/23 , KHATHA NO-384/1163/1159/55/5,23-
Sale/Title/Gift Deed, survey SY NO-55/5 AND 55/23 , KHATHA NO-384/1163/1159/55/5,23-
JDA, survey SY NO-55/5 AND 55/23 , KHATHA NO-384/1163/1159/55/5,23-
Khatha, survey SY NO-55/5 AND 55/23 , KHATHA NO-384/1163/1159/55/5,23-
Registration CertificateFile: Partnership Registration Cert.pdf-
GST CertificateFile: GST CERTIFICATE.pdf-
Partnership DeedFile: PARTNERSHIP DEED.pdf-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: CA FORM1 SUMUK SQUARE.pdf-
Certificate issued by Architect Form 2File: ARCHITECT CERTIFICATE (2).pdf-
Certificate issued by Engineer Form 3File: ENGINEER CERTIFICATE.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: NON LITIGATION AFFIDAVIT,.pdf-
Balance Sheet 2023 - 2024File: YASHWANTH KUMAR H - ITR- 2024-25.pdf-
Balance Sheet 2022 - 2023File: YASHWANTH KUMAR H - ITR-2023-24.pdf-
Balance Sheet 2021 - 2022File: YASHWANTH KUMAR H - ITR 2022-23.pdf-
Audited Profit and Loss Statement 2023 - 2024File: YASHWANTH KUMAR H - ITR- 2024-25.pdf-

How this compares with Bengaluru Urban

65%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SUMUK SQUARE-2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSUMUK SQUARE-2Other 16Dot size: filed unitsN

Filed coordinates, straight-line distance. 16 registered projects within 2 km.

Builder: sumuk projects

SUMUK PROJECTS has 2 registrations on RERA Karnataka, including SUMUK SQUARE and SUMUK SQUARE-2. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SUMUK SQUARE-2 is delayed beyond 30 Apr 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SUMUK SQUARE-2?

The registered promoter entity is sumuk projects, a partnership firm as per the filing. Its GSTIN 29AERFS0908Q1Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SUMUK SQUARE-2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SUMUK SQUARE-2?

The professionals named in the filing: Architect: mayur g kulkarni; Engineer: ramesh s; Chartered Accountant: KVN PHANIENDRA REDDY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUMUK SQUARE-2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUMUK SQUARE-2. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUMUK SQUARE-2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.