ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / SUMADHURA SOLACE PHASE-II

Registration approved No litigation declared Residential/Group Housing project

SUMADHURA SOLACE PHASE-II

By SUMADHURA INFRACON PRIVATE LIMITED

RG-KA-81158 · RERA PRM/KA/RERA/1251/446/PR/111225/008333 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2029Possession promisedno revision filed
0 of 18Construction stages donefurthest along: Earth work and other leveling..., 2%
329 of 329Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 139 documents Report an error

SUMADHURA SOLACE PHASE-II is a Residential/Group Housing project by SUMADHURA INFRACON PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/111225/008333 on 11 Dec 2025. Possession is promised by 31 Dec 2029. 0 of the 329 units on this registration are recorded sold or booked, and 0 of 18 construction stages are filed complete.

At a glance

Project

  • NameSUMADHURA SOLACE PHASE-II
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560066
  • Pincode560066
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/111225/008333
  • ReraGenie IDRG-KA-81158

Builder

  • NameSUMADHURA INFRACON PRIVATE LIMITED
  • Entity typeCompany
  • CINU45200KA2012PTC062071
  • GSTIN29AAQCS9641A1ZZ
  • Authorized SignatoryG NAVEEN KUMAR
  • Chairman and Managing DirectorGUNDA MADHUSUDHAN
  • DirectorsBHARAT KUMAR KANDUKURI, KALAKUNTLA VENKATA RAMA RAO, G NAVEEN KUMAR, G SWAPNA, G MADHUSUDHAN, RAHUL KANDUKURI, Srinivas Moramchetty
  • Project HeadPraveen Kumar G
  • Other registrations20 more →
  • Declared earlier projects16 →

Key dates

this monthRegisteredDec 2025PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on11 Dec 2025
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings4 building records
  • Documents filed139 files

Current status

0%0 of 329 units booked
3.8%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower - 1 (LUMA)---29029
Tower - 6 (MIRA)---1500150
Tower - 7 (OLEA)---1500150
VILLA---202

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 18 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 2%.

Building: 0% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work2%
Foundation footing work0%
Upto Plinth Level0%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)0%
RCC or MS Framed structure0%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area23,784 sq m
Named landowners1
LandownerVillageDistrict
NARASA REDDY.N--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 445.54 cr
Cost incurredRs 16.80 cr
Spent of the estimate3.77%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 364.56 crRs 15.25 cr
On-site expenditure-Site OverheadRs 45.63 crRs 1.44 cr
Payment of taxesRs 31.05 cr-
On-site expenditure-Consultants FeesRs 4.30 crRs 11.17 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNarasimha Ragavan
EngineerN.N. Nagendra Kumar
Chartered AccountantCH PRANAY KUMAR

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed139

As listed on the registration, under the names the promoter filed them with; the newest 80 of 139 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/111225/008333 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate-300926 Solace-II.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect Certificate Solace-II 300926.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer Certificate 300926-Solace-II.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 CA Certificate 300626-Solace-II_0001.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect Certificate Solace-II_300626.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer Certificate 300626-Solace-II.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate 310326 Solace-II_0001.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate Solace-II 310326.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate 310326 Solace-II - converted.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate 31122025 Solace-II.pdf16 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate-31122025 Solace-II.pdf16 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate-Solace-II -31122025.pdf16 Jan 2026
Q3 2025-26 Water supply and sewage board16 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)16 Jan 2026
Q3 2025-26 KPTCL- BESCOM16 Jan 2026
Q3 2025-26 Fire and Safety16 Jan 2026
Q3 2025-26 Airport Authority of India16 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department16 Jan 2026
of 1 Areas Bifurcation Details SOLACE-I&IIFile: 1 of 1 Areas Bifurcation Details SOLACE-II.pdf5 Dec 2025
of 2 Inventory Dev Area Bifurcation Details SOLACE-IIFile: 1 of 2 Inventory Dev Area Bifurcation Details SOLACE-II.pdf5 Dec 2025
of 4 Agreement Of Sale Solace-Phase - IIFile: 1 of 4 Agreement Of Sale Solace-Phase - II.pdf5 Dec 2025
of 5 Allotment Letter Solace- Phase - IIFile: 1 of 5 Allotment Letter Solace- Phase - II.pdf5 Dec 2025
of 6 Estimated cost of construction certified by the Engineer-Solace-IIFile: 1 of 6 Estimated cost of construction certified by the Engineer-Solace-II.pdf5 Dec 2025
of 7 STP Drawing As Per Kspcb Norms Certified by Engineer SOLACE Phase-IIFile: 1 of 7 STP Drawing As Per Kspcb Norms Certified by Engineer SOLACE Phase-II.pdf5 Dec 2025
DP Approved Plan SolaceFile: 1 DP Approved Plan Solace.pdf28 Nov 2025
NOC Work Order DP SolaceFile: 2 NOC Work Order DP Solace.pdf28 Nov 2025
Building License-SolaceFile: 3 Building License-Solace.pdf28 Nov 2025
ADLR Sketch-SolaceFile: 4 ADLR Sketch-Solace.pdf28 Nov 2025
Commencement cirtificateFile: 6 Commencement Certificate.pdf28 Nov 2025
Demarcation of Land area in approved plan-SaolaceFile: 7 Demarcation of Land area in approved plan-Saolace.pdf28 Nov 2025
Demarked Site Location in Village MapFile: 8 Demarked Site Location in Village Map.pdf28 Nov 2025
NOC KSPCB - SolaceFile: 9 NOC KSPCB - Solace.pdf28 Nov 2025
Apprioval from KTCP Under sec 14File: 10 Apprioval from KTCP Under sec 14.pdf28 Nov 2025
I 7 Form 3 Engineer Certificate-Solace-IFile: I 7 CE License.pdf28 Nov 2025
I 8 Structural safety for bulding Solace-IIFile: I 8 Structural safety for bulding Solace-II.pdf28 Nov 2025
I 9 Project Specification Solace Phase-IIFile: I 9 Project Specification Solace Phase-II (2).pdf28 Nov 2025
I 10 Proforma of agreement (AFS) Solace-IIFile: I 10 Proforma of agreement (AFS) for sale.pdf28 Nov 2025
I 11 Proforma of Allotment Solace-IIFile: I 11 Allotment Letter - Solace- Phaas - II.pdf28 Nov 2025
I 12 NOC BESCOM with Receipt SolaceFile: I 12 NOC BESCOM with Receipt Solace.pdf28 Nov 2025
I 13 NOC HAL SolaceFile: I 13 NOC HAL Solace.pdf28 Nov 2025
I 14 Estimated Project Budget-SOLACE-IIFile: I 14 Estimated Project Budget-SOLACE_0001.pdf28 Nov 2025
I 15 Land Cost Calculation sheet as per guidance value_0001File: I 15 Land Cost Calculation sheet as per guidance value_0001.pdf28 Nov 2025
I 16 STP drawing as per kspcb certified by EngineerFile: I 16 STP drawing as per kspcb certified by Engineer.pdf28 Nov 2025
II 1 Affidavit Bank with NotryFile: II 1 Affidavit Bank with Notry.pdf28 Nov 2025
II 2 profit and loss account and balance sheetFile: II 2 profit and loss account and balance sheet.pdf28 Nov 2025
II 3 Notarized Affidavit for 3(1) Voliation with NotaryFile: II 3 Notarized Affidavit for 3(1) Voliation with Notary_0001.pdf28 Nov 2025
II 5 RTC ALL SY NO SFile: II 5 RTC ALL SY NO S.pdf28 Nov 2025
II 6 MR No all SY NOFile: II 6 MR No all SY NO.pdf28 Nov 2025
II 8 Conversion All Sy noFile: II 8 Conversion All Sy no.pdf28 Nov 2025
II 9 EC 1-4-2004 to 28-3-2025 All SY NO'SFile: II 9 EC 1-4-2004 to 28-3-2025 All SY NO'S.pdf28 Nov 2025
II 10 JDA 9482-2023-24(Chamundi)File: II 10 JDA 9482-2023-24(Chamundi).pdf28 Nov 2025
II 11 Affidivat_Non-Litigation with NotaryFile: II 11 Affidivat_Non-Litigation with Notry_0001.pdf28 Nov 2025
II 12 Affidavit cum Declaration Form-B with NotaryFile: II 12 Affidavit cum Declaration Form-B with Notry_0001.pdf28 Nov 2025
II 13 advocate search reportFile: II 13 advocate search report.pdf28 Nov 2025
II 4b Sale Deed 2167-1997-98(1A-25G) Sy 32-3File: II 4b Sale Deed 2167-1997-98(1A-25G) Sy 32-3.pdf28 Nov 2025
II 4c Sale deed 29181994-95(15G) Sy 48-2File: II 4c Sale deed 29181994-95(15G) Sy 48-2.pdf28 Nov 2025
II 4a Sale Deed-48-1 (2Gunta)File: II 4a Sale Deed-4182-96-97(Sy No 48-1).pdf28 Nov 2025
II 4 Sale Deed No 5120-2011-12 (Sy No old 31-2 new 31-3)File: II 4 Sale Deed No 5120-2011-12 (Sy No old 31-2 new 31-3).pdf28 Nov 2025
II d Sale Deed-48-1 (2Gunta)File: II d Sale Deed-48-1 (2Gunta).pdf28 Nov 2025

How this compares with Bengaluru Urban

0%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SUMADHURA SOLACE PHASE-II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSUMADHURA SOLACE PHASE-IOther 42Dot size: filed unitsN

Filed coordinates, straight-line distance. 42 registered projects within 2 km.

Builder: SUMADHURA INFRACON PRIVATE LIMITED

SUMADHURA INFRACON PRIVATE LIMITED has 21 registrations on RERA Karnataka, including Sumadhura Belfort and SUMADHURA SUSHANTHAM PHASE I. Its filings declare 16 earlier projects, 11 of them declared completed. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SUMADHURA SOLACE PHASE-II is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SUMADHURA SOLACE PHASE-II?

The registered promoter entity is SUMADHURA INFRACON PRIVATE LIMITED, a company as per the filing. Its CIN U45200KA2012PTC062071 and GSTIN 29AAQCS9641A1ZZ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SUMADHURA SOLACE PHASE-II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SUMADHURA SOLACE PHASE-II?

The professionals named in the filing: Architect: Narasimha Ragavan; Engineer: N.N. Nagendra Kumar; Chartered Accountant: CH PRANAY KUMAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUMADHURA SOLACE PHASE-II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUMADHURA SOLACE PHASE-II. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUMADHURA SOLACE PHASE-II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.