SUMADHURA EDITION PHASE-I

By SUMADHURA INFRACON PRIVATE LIMITED

RG-KA-51698 · RERA PRM/KA/RERA/1251/446/PR/111225/008328 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • Litigation declared
  • 1 complaint at RERA Karnataka

Clear

  • Completion date never moved
  • Separate project account declared
Dec 2029Possession promisedno revision filed
0 of 16Construction stages donefurthest along: Earth work and other leveling..., 75%
335 of 450Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 136 documents Report an error

SUMADHURA EDITION PHASE-I is a Residential/Group Housing project by SUMADHURA INFRACON PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/111225/008328 on 11 Dec 2025. Possession is promised by 31 Dec 2029. 115 of the 450 units on this registration are recorded sold or booked, and 0 of 16 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSUMADHURA EDITION PHASE-I
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560066
  • Pincode560066
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/111225/008328
  • ReraGenie IDRG-KA-51698

Builder

  • NameSUMADHURA INFRACON PRIVATE LIMITED
  • Entity typeCompany
  • CINU45200KA2012PTC062071
  • GSTIN29AAQCS9641A1ZZ
  • Authorized SignatoryG NAVEEN KUMAR
  • Chairman and Managing DirectorGUNDA MADHUSUDHAN
  • DirectorsBHARAT KUMAR KANDUKURI, KALAKUNTLA VENKATA RAMA RAO, G NAVEEN KUMAR, G SWAPNA, G MADHUSUDHAN, RAHUL KANDUKURI
  • Project HeadPraveen Kumar G
  • Other registrations20 more →
  • Declared earlier projects16 →

Key dates

this monthRegisteredDec 2025PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on11 Dec 2025
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings3 building records
  • Documents filed136 files

Current status

26%115 of 450 units booked
5.2%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
(WING - A) ARA---1500150
(WING - B) AQUILA---1500150
(WING - C) CARINA---1500150

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 16 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 75%.

Building: 8% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work75%
Foundation footing work50%
Upto Plinth Level0%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)Not applicable
RCC or MS Framed structure0%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningYes0%
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area35,623 sq m
Named landowners1
LandownerVillageDistrict
MUNIYAPPA AND OTHERS--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 519.72 cr
Cost incurredRs 27.00 cr
Spent of the estimate5.2%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 400.65 crRs 18.51 cr
On-site expenditure-Site OverheadRs 59.18 crRs 3.60 cr
Payment of taxesRs 43.15 crRs 3.17 cr
Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for constructionRs 12.00 crRs 1.40 cr
On-site expenditure-Consultants FeesRs 4.73 crRs 32.85 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectIndrajith S Kembhavi
EngineerB E Pruthviraj
Chartered AccountantCH PRANAY KUMAR

Litigation declaredYes

The promoter declares litigation on this registration. The case records are in the filed documents.

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
00822/2026-SUMADHURA INFRACON PRIVATE LIMITED15/07/2026

Documents filed136

As listed on the registration, under the names the promoter filed them with; the newest 80 of 136 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/111225/008328 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: form 4 CA Certificate-300926 Edition-I_0001.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect Certificate-300926_Edition-I.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer Certificate 300926-Edition-I.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 CA Certificate 300626 Edition-I_0001.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect Certificate-300626_Edition-I.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer Certificate 300626-Edition-I.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate 310326 Edition-I.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate-310326 Edition-I.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate 310326 Edition-I - converted.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate 31122025 Edition-I.pdf14 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate 31122025-Edition-I.pdf14 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate-31122025 Edition-I - converted.pdf14 Jan 2026
Q3 2025-26 Water supply and sewage board14 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)14 Jan 2026
Q3 2025-26 KPTCL- BESCOM14 Jan 2026
Q3 2025-26 Fire and Safety14 Jan 2026
Q3 2025-26 Airport Authority of India14 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department14 Jan 2026
of 1 Areas Bifurcation Details Sumadhura Edition Phases wiseFile: 1 of 1 Areas Bifurcation Details Sumadhura Edition Phases wise.pdf5 Dec 2025
of 2 Agreement Of Sale Edition-IFile: 1 of 2 Agreement Of Sale Edition-I.pdf5 Dec 2025
of 3 Allotment Letter - Edition-IFile: 1 of 3 Allotment Letter - Edition-I.pdf5 Dec 2025
1of 4 Estimated cost of construction certified by the Engineer-Edition-I &IIFile: 1of 4 Estimated cost of construction certified by the Engineer-Edition-I &II.pdf5 Dec 2025
DP Approved Plan (Single Plot) EditionFile: 1 DP Approved Plan (Single Plot) Edition.pdf29 Nov 2025
NOC DP Work Order (Single plot) EditionFile: 2 NOC DP Work Order (Single plot) Edition.pdf29 Nov 2025
Building License-EditionFile: 3 Building License-Edition.pdf29 Nov 2025
ADLR Sketch Edition for 20AcresFile: 4 ADLR Sketch Edition for 20Acres.pdf29 Nov 2025
Site & GF PlanFile: 06 Site & GF Plan.pdf29 Nov 2025
06a 1st & 2nd BF PlanFile: 06a 1st & 2nd BF Plan.pdf29 Nov 2025
06c 1st to 18th Plan Wing-AFile: 06c 1st to 18th Plan Wing-A.pdf29 Nov 2025
06d 1st to 18th Plan Wing-BFile: 06d 1st to 18th Plan Wing-B.pdf29 Nov 2025
06e 1st to 18th Plan Wing-CFile: 06e 1st to 18th Plan Wing-C.pdf29 Nov 2025
06f Terrace Plan Wing-ABCFile: 06f Terrace Plan Wing-ABC.pdf29 Nov 2025
06g Elevation & Section PlanFile: 06g Elevation & Section Plan.pdf29 Nov 2025
Commencement CertificateFile: 7 Commencement Certificate Edition.pdf29 Nov 2025
Demarcation of Land area in approved plan-EditionFile: 8 Demarcation of Land area in approved plan-Edition.pdf29 Nov 2025
Demarked Site Location in Village MapFile: 9 Demarked Site Location in Village Map.pdf29 Nov 2025
NOC KSPCB - EDITIONFile: 10 NOC KSPCB - EDITION.pdf29 Nov 2025
Apprioval from KTCP Under sec 14File: 11 NOC Approva KPTC under sec 14 Edition.pdf29 Nov 2025
Area DetailsFile: 8 Demarcation of Land area in approved plan-Edition.pdf29 Nov 2025
I 2 Structural Eng LicenseFile: I 2 Structural Lice and adhar.pdf29 Nov 2025
I 3 C Engineer License (Form-3)File: I 3 C Engineer License (Form-3).pdf29 Nov 2025
I 4 Certificate Of Structural Safety For Building with Structural License Edition-1File: I 4 Certificate Of Structural Safety For Building with Structural License Edition-1.pdf29 Nov 2025
I 5 Project Specification Certified by Promoter Edition-IFile: I 5 Project Specification Certified by Promoter Edition-I.pdf29 Nov 2025
I 6 Proforma Of Agreement to SellFile: I 6 Proforma Of Agreement to Sell.pdf29 Nov 2025
I 7 Proforma of Allotment LetterFile: I 7 Proforma of Allotment Letter.pdf29 Nov 2025
I 8 Notarized Affidavit for 3(1) Voliation With Notari_0001File: I 8 Notarized Affidavit for 3(1) Voliation With Notari_0001.pdf29 Nov 2025
I 9 Estimated Cost Of Construction Project-EditionFile: I 9 Estimated Cost Of Construction Project-Edition.pdf29 Nov 2025
I 10 Land Cost Calculation sheet as per guidance value_0001File: I 10 Land Cost Calculation sheet as per guidance value_0001.pdf29 Nov 2025
I 11 STP Drawing certified by Engineer Edition-IFile: I 11 STP Drawing certified by Engineer Edition-I.pdf29 Nov 2025
II 1 RTC 2025-26 all SY NOFile: II 1 RTC 2025-26 all SY NO.pdf29 Nov 2025
II 2 MR Land Owners Before ConversionFile: II 2 MR Land Owners Before Conversion.pdf29 Nov 2025
II 4 Conversion Order for all Sy NoFile: II 4 Conversion Order for all Sy No.pdf29 Nov 2025
II 5 EC 01042004 to 28072025 All Sy NoFile: II 5 EC 01042004 to 28072025 All Sy No.pdf29 Nov 2025
II 6 JDA Sy No 83,84,85, EditionFile: II 6 JDA Sy No 83,84,85, Edition.pdf29 Nov 2025
II 6 JDA Sy No.82-2 (SIPL)File: II 6 JDA Sy No 82-2.pdf29 Nov 2025
II 7 Advoacte Search ReportFile: II 7 Advocate Search Report - converted (1).pdf29 Nov 2025
Sale Deed Sy No 83 (3A-36G)File: Sale Deed Sy No 83 (3A-36G).pdf29 Nov 2025
Sale Deed Sy No 84 & 85File: Sale Deed Sy No 84 & 85 (2).pdf29 Nov 2025

How this compares with Bengaluru Urban

26%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SUMADHURA EDITION PHASE-I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSUMADHURA EDITION PHASE-Other 42Dot size: filed unitsN

Filed coordinates, straight-line distance. 42 registered projects within 2 km.

Builder: SUMADHURA INFRACON PRIVATE LIMITED

SUMADHURA INFRACON PRIVATE LIMITED has 21 registrations on RERA Karnataka, including Sumadhura Belfort and SUMADHURA SUSHANTHAM PHASE I. Its filings declare 16 earlier projects, 11 of them declared completed. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SUMADHURA EDITION PHASE-I is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SUMADHURA EDITION PHASE-I?

The registered promoter entity is SUMADHURA INFRACON PRIVATE LIMITED, a company as per the filing. Its CIN U45200KA2012PTC062071 and GSTIN 29AAQCS9641A1ZZ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SUMADHURA EDITION PHASE-I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SUMADHURA EDITION PHASE-I?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at SUMADHURA EDITION PHASE-I?

The professionals named in the filing: Architect: Indrajith S Kembhavi; Engineer: B E Pruthviraj; Chartered Accountant: CH PRANAY KUMAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUMADHURA EDITION PHASE-I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUMADHURA EDITION PHASE-I. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUMADHURA EDITION PHASE-I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.