SSVD SERENITY

By SRI SAI VENKATESHWARA DEVELOPERS

RG-KA-17095 · RERA PRM/KA/RERA/1251/446/PR/130625/007829 · Last updated on RERA Karnataka portal: 15 Apr 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2029Possession promisedno revision filed
0 of 17Construction stages donefurthest along: Earth work and other leveling..., 75%
56 of 56Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 87 documents Report an error

SSVD SERENITY is a Residential/Group Housing project by SRI SAI VENKATESHWARA DEVELOPERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/130625/007829 on 13 Jun 2025. Possession is promised by 30 Jun 2029. 0 of the 56 units on this registration are recorded sold or booked, and 0 of 17 construction stages are filed complete.

At a glance

Project

  • NameSSVD SERENITY
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560049
  • Pincode560049
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/130625/007829
  • ReraGenie IDRG-KA-17095

Builder

  • NameSRI SAI VENKATESHWARA DEVELOPERS
  • Entity typePartnership Firm
  • GSTIN29ACFFS1149B2ZA
  • Authorized SignatoryDoddala Chandrasekhar Naidu

Key dates

this monthRegisteredJun 2025PromisedJun 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on13 Jun 2025
  • Promised completion30 Jun 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed87 files

Current status

0%0 of 56 units booked
1.1%Of the estimated cost spent so far

Figures as on 15 Apr 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SSVD SERENITY---56056

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 17 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 75%.

Building: 11% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work75%
Foundation footing work62%
Upto Plinth Level42%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)5%
Retaining wall (All types)5%
RCC or MS Framed structure0%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 15 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingNoNot applicable
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes0%
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,803 sq m
Named landowners1
LandownerVillageDistrict
Sri Sai Venkateshwara Developers--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 30.61 cr
Cost incurredRs 32.22 lakh
Spent of the estimate1.05%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 30.01 crRs 32.22 lakh
Principal sum and interest payable to financial institutions-Scheduled BanksRs 50.00 lakh-
On-site expenditure-Salaries of workersRs 10.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBhanumathy G.
EngineerArun Kumar S R
Chartered AccountantK Hemadri

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed87

As listed on the registration, under the names the promoter filed them with; the newest 80 of 87 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/130625/007829 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Q3.pdf20 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Arc Q3.pdf20 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Eng Q3.pdf20 Feb 2026
Q3 2025-26 Water supply and sewage board20 Feb 2026
Q3 2025-26 KPTCL- BESCOM20 Feb 2026
ADLR Survey SketchFile: ADLR Survey Sketch.pdf31 May 2025
Affdavit for Non LitigationFile: Affidavit for Non Litigation.pdf31 May 2025
Affidavit for Violation Sec 3(1)File: Affidavit for Violation.pdf31 May 2025
Affdiavit FORM BFile: Form B.pdf31 May 2025
Affidavit RERA Bank AccountFile: RERA Bank Account.pdf31 May 2025
Form 3 - Eng CertificateFile: FORM-3 Eng.pdf31 May 2025
KSPCB NOCFile: KSPCB NOC.pdf31 May 2025
Original Sanction Plan All SheetsFile: Sanction Plan 2 out of 2 Sheets.pdf31 May 2025
Plan Sanction Confirmation LetterFile: Plan Letter.pdf31 May 2025
Advocate Search ReportFile: Advocate Search Report.pdf31 May 2025
EC from from 25/7/2023File: ECC 3.pdf31 May 2025
STP DrawingFile: STP Drawing - Certified by Eng.pdf31 May 2025
VIllage MAPFile: Village MAP.pdf31 May 2025
ITR FY 2021-22File: AY 22-23.pdf31 May 2025
ITR FY 2022-23File: AY 23-24.pdf31 May 2025
ITR FY 2023-24File: AY 24-25.pdf31 May 2025
E KhataFile: E Khata.pdf31 May 2025
Building Plan Sanction LetterFile: Plan Letter.pdf31 May 2025
Architects certificate with valid COA numberFile: COA Copy.pdf31 May 2025
Project SpecsFile: Project Specs.pdf31 May 2025
Proforma of Allotment LetterFile: Proforma of Allotment Letter.pdf31 May 2025
Proforma of Sale AgreementFile: Proform of Sale Agreement.pdf31 May 2025
Water NOCFile: Water NOC.pdf31 May 2025
BESCOM NOCFile: BESCOM NOC.jpg31 May 2025
STP DrawingFile: STP Drawing - Certified by Eng.pdf31 May 2025
Land Cost Calc SheetFile: Land Calc.pdf31 May 2025
RTC, survey 100-
Mutation, survey 100-
Encumbrance Certificate, survey 100-
Conversion/Alienation Order, survey 100-
Sale/Title/Gift Deed, survey 100-
Khatha, survey 100-
Registration CertificateFile: Form C.pdf-
GST CertificateFile: GST Certificate.pdf-
Partnership DeedFile: Partnership Deed.pdf-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: CA Reg 1.pdf-
Certificate issued by Architect Form 2File: FORM-2 - Arc.pdf-
Certificate issued by Engineer Form 3File: FORM-3 Eng.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit for Non Litigation.pdf-
Balance Sheet 2023 - 2024File: ITR 23-24.pdf-
Balance Sheet 2022 - 2023File: ITR 22-23.pdf-
Balance Sheet 2021 - 2022File: ITR 21-22.pdf-
Audited Profit and Loss Statement 2023 - 2024File: ITR 23-24.pdf-
Audited Profit and Loss Statement 2022 - 2023File: ITR 22-23.pdf-
Audited Profit and Loss Statement 2021 - 2022File: ITR 21-22.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: ITR ACK.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ITR ACK.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITR ACK.pdf-
Structural Stability-
KSPCB NOC-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-

How this compares with Bengaluru Urban

0%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SSVD SERENITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSSVD SERENITYOther 35Dot size: filed unitsN

Filed coordinates, straight-line distance. 35 registered projects within 2 km.

Builder: SRI SAI VENKATESHWARA DEVELOPERS

SRI SAI VENKATESHWARA DEVELOPERS has 1 registration on RERA Karnataka, including SSVD SERENITY. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SSVD SERENITY is delayed beyond 30 Jun 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SSVD SERENITY?

The registered promoter entity is SRI SAI VENKATESHWARA DEVELOPERS, a partnership firm as per the filing. Its GSTIN 29ACFFS1149B2ZA can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SSVD SERENITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SSVD SERENITY?

The professionals named in the filing: Architect: Bhanumathy G.; Engineer: Arun Kumar S R; Chartered Accountant: K Hemadri. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SSVD SERENITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SSVD SERENITY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SSVD SERENITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.