Home / Browse projects / Bengaluru Urban, Karnataka / SSVD DIVINE

Registration approved No litigation declared Residential/Group Housing project

SSVD DIVINE

By SSVD NISARGA

RG-KA-24774 · RERA PRM/KA/RERA/1251/310/PR/190822/005169 · Last updated on RERA Karnataka portal: 29 Jul 2022

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Aug 2024Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 92 documents Report an error

SSVD DIVINE is a Residential/Group Housing project by SSVD NISARGA in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/190822/005169 on 19 Aug 2022. Possession is promised by 31 Aug 2024.

At a glance

Project

  • NameSSVD DIVINE
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560061
  • Pincode560061
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/190822/005169
  • ReraGenie IDRG-KA-24774

Builder

  • NameSSVD NISARGA
  • Entity typePartnership Firm
  • GSTIN29AEMFS7131H1ZH
  • Authorized SignatoryD Chandra Sekhar Naidu

Key dates

this monthRegisteredAug 2022PromisedAug 2024

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on19 Aug 2022
  • Promised completion31 Aug 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed92 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SSVD DIVINE---60060

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 29 Jul 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja work-
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 29 Jul 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingYes-
Street LightingYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallYes-
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areasYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,601 sq m
Named landowners1
LandownerVillageDistrict
SSVD NISARGA Rep. Its Partner D Chandra Sekhar & Others--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 15.75 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 12.33 cr-
On-site expenditure-Site OverheadRs 90.00 lakh-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 70.00 lakh-
Payment of taxesRs 70.00 lakh-
Principal sum and interest payable to financial institutions-Scheduled BanksRs 37.80 lakh-
On-site expenditure-Salaries of workersRs 27.30 lakh-
On-site expenditure-Consultants FeesRs 20.00 lakh-
Payment of cessRs 12.00 lakh-
Payment of feesRs 10.00 lakh-
Payment of chargesRs 5.00 lakh-
Payment of PremiumsRs 70,000-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectV SIVA KUMAR
EngineerSRINIVAS RAO BOLIMUNTA
Chartered AccountantB MALLAIAH

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed92

As listed on the registration, under the names the promoter filed them with; the newest 80 of 92 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/190822/005169 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Conversion order as per land revenue act section 95File: Affidavit_.pdf29 Jul 2022
Advocate Search ReportFile: Advocate Search Report_.pdf29 Jul 2022
Conversion Order & ASRFile: Commencement Order & Endorsement.pdf14 Jul 2022
Court Judgment regarding land ceilingFile: Urban Land Ceiling Order.pdf14 Jul 2022
Layout Plan with demarcation of SiteFile: Layout Plan_.pdf14 Jul 2022
Layout Order Copy by BDAFile: Layout Order by BDA.pdf14 Jul 2022
Amalgamation Map and OrdersFile: Amalgamation Site MAP & Order Copy.pdf14 Jul 2022
Others Supporting DocumentsFile: Writ Petition - High Court - BDA, City Planning Authority.pdf14 Jul 2022
Sale Deed for full extent of project since site no 987 and othersFile: SSVD Nisarga Sale Deed.pdf15 Jun 2022
Title Deed - Mother Deed Sy. No. 27File: 27#1.pdf15 Jun 2022
Title Deed - Mother Deed Sy. No. 117File: sy-117.pdf15 Jun 2022
Title Deed - Mother Deed Sy. No. 118File: sy-118.pdf15 Jun 2022
Layout PlanFile: Site Plan.pdf15 Jun 2022
Master PlanFile: Master Plan.pdf15 Jun 2022
Location and Demarcation Drawing - Village BasedFile: Village Map - Copy with Mark Final.pdf15 Jun 2022
Layout Order CopyFile: Commence Certificate Permission to use the Land - BDA.pdf15 Jun 2022
Amalgamation MAP and Order of the SitesFile: Site Amalgamation Plan.pdf15 Jun 2022
Advocate Search ReportFile: Advocate Search Report.pdf15 Jun 2022
BESCOM NOC along with copy of fee paid receiptFile: BESCOM NOC with Receipt.pdf15 Jun 2022
Provision of STP in the project along with the supporting demarcated STP design drawingsFile: STP Plan.pdf15 Jun 2022
Site PlanFile: Site Amalgamation Plan.pdf15 Jun 2022
BANK ACCOUNT STATEMENTFile: Bank Statement.jpeg27 May 2022
Sale Deed 30-09-2021 from ismail shariff to ssvd nisargaFile: Ismail Shariff Sale Deed.pdf27 May 2022
EC 1File: ssvd nisarga EC 1.pdf27 May 2022
EC 2File: ssvd nisarga EC 2.pdf27 May 2022
PARTNERSHIP DEEDFile: Partnership Deed.pdf27 May 2022
AFFIDAVIT FOR NON LITIGATIONFile: Affidavit for Non Litigation.pdf27 May 2022
SUB REGISTRAR CERTIFIED OF GUIDANCE VALUEFile: Sub Registrar Copy.pdf27 May 2022
LAYOUT PLAN AND MASTER PLAN OF THE APARTMENTFile: Working Plan.pdf27 May 2022
Amalgamation Map and order of Site no 982,983,984,985,986,987,988File: Amalgamation Order & Drawing.pdf27 May 2022
Signed copy of project specificationFile: Project Specification of SSVD DIVINE.pdf27 May 2022
Sale Agreement of ProformaFile: Sale Agreement (RERA).pdf27 May 2022
Engineer indicating the structural safetyFile: Stability Certificate.pdf27 May 2022
Copy of fee receipt paid towards BWSSB NOCFile: BWSSB NOC with Receipt.pdf27 May 2022
Title deed to conversion land ownerFile: Commencement Certificate to.jpeg27 May 2022
Notarised Form BFile: Form B.pdf27 May 2022
Registration CertificateFile: Partnership Deed (Certificate).pdf-
Partnership DeedFile: Partnership Deed ().pdf-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: CA Registration Certificate.pdf-
Certificate issued by Architect Form 2File: Arc PR.pdf-
Certificate issued by Engineer Form 3File: Eng PR.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit for Non Litigation.pdf-
Certificate from Chartered AccountFile: CA Registration Certificate.pdf-
Balance Sheet 2020 - 2021File: Yet to be filed.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Yet to be filed.pdf-
Director's Report 2020 - 2021File: Yet to be filed.pdf-
Cash Flow Statement 2020 - 2021File: Yet to be filed.pdf-
Auditor's Report 2020 - 2021File: Yet to be filed.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: Yet to be filed.pdf-
Commencement Certificate-
BWSSB NOC-
BBMP Sanction Plan-
BBMP Sanction Plan-
BBMP Sanction Plan-
Specifications-
BBMP Sanction Plan-
Working Plan-
Conversion Document-
Sale Deeds-
Sale Agreement-
Allotment Letter-
Form B-
Notarized Affidavit for 3(1) Voliation-
BWSSB NOC-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
KSPCB CFE-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SSVD DIVINE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSSVD DIVINEOther 16Dot size: filed unitsN

Filed coordinates, straight-line distance. 16 registered projects within 2 km.

Builder: SSVD NISARGA

SSVD NISARGA has 1 registration on RERA Karnataka, including SSVD DIVINE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SSVD DIVINE is delayed beyond 31 Aug 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SSVD DIVINE?

The registered promoter entity is SSVD NISARGA, a partnership firm as per the filing. Its GSTIN 29AEMFS7131H1ZH can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SSVD DIVINE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SSVD DIVINE?

The professionals named in the filing: Architect: V SIVA KUMAR; Engineer: SRINIVAS RAO BOLIMUNTA; Chartered Accountant: B MALLAIAH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SSVD DIVINE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SSVD DIVINE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SSVD DIVINE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.