Home / Browse projects / Bengaluru Urban, Karnataka / SRI SAI ABHAYAM
SRI SAI ABHAYAM
RG-KA-14721 · RERA PRM/KA/RERA/1251/446/PR/291225/008364 · Last updated on RERA Karnataka portal: 15 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
SRI SAI ABHAYAM is a Residential/Group Housing project by SADHGURU DEVELOPERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/291225/008364 on 29 Dec 2025. Possession is promised by 31 Dec 2027. 5 of the 64 units on this registration are recorded sold or booked, and 5 of 15 construction stages are filed complete.
At a glance
Project
- NameSRI SAI ABHAYAM
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- 562129
- Pincode562129
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/446/PR/291225/008364
- ReraGenie IDRG-KA-14721
Builder
- NameSADHGURU DEVELOPERS
- Entity typePartnership Firm
- GSTIN29AEYFS6039M1ZU
- Authorized SignatoryRamesh G
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on29 Dec 2025
- Promised completion31 Dec 2027
- Revised completionNone
- Buildings1 building record
- Documents filed82 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SRI SAI ABHAYAM | - | - | - | 64 | 0 | 64 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 15 construction stages are filed complete. The stage furthest along is Masonry Construction, at 98%.
Building: 52% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | Not applicable |
| RCC or MS Framed structure | 100% |
| Masonry Construction | 98% |
| Plastering inside , outside & Ceiling | 75% |
| Joinery: Doors, Windows, Ventilators etc | 35% |
| Basic work of Water supply, Sanitary and Electrification | 30% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 30% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 15% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 25% |
| Sewage and Drainage System | Yes | 25% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 15% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | Yes | 10% |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | 50% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | No | Not applicable |
| Community Hall | Yes | 50% |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | Yes | 0% |
| Gym | Yes | 50% |
| Parks | No | Not applicable |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 25% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 50% |
| Lifts | Yes | 20% |
| Corridor/Lobbies | Yes | 50% |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 15% |
| Basement | No | Not applicable |
| Terrace | Yes | 75% |
| Outer Wall | Yes | 25% |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | Yes | 15% |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SADHGURU DEVELOPERS | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 29.53 cr | Rs 2.57 cr |
| On-site expenditure-Consultants Fees | Rs 32.85 lakh | - |
| On-site expenditure-Salaries of workers | Rs 28.98 lakh | Rs 1.18 lakh |
| Payment of taxes | Rs 1.59 lakh | Rs 55,609 |
| Principal sum and interest payable to financial institutions-Scheduled Banks | - | Rs 20.01 lakh |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | TATA VITTALA SRINIVAS |
| Engineer | MANDHADIVENKATARAMANAREDDY |
| Chartered Accountant | John Peter Narisetty |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed82
As listed on the registration, under the names the promoter filed them with; the newest 80 of 82 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/291225/008364 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 CA QU Q2 2026-2027.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect QU Q2 2026-2027.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer QU Q2 2026-2027.pdf | 15 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 CA QU Q1 2026-2027.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect QU Q1 2026-2027.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer QU Q1 2026-2027.pdf | 15 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 CA QU Q4 2025-2026.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect QU Q4 2025-2026.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer QU Q4 2025-2026.pdf | 15 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 CA QU Q3 2025-2026pdf.pdf | 7 Feb 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect QU Q3 2025-2026.pdf | 7 Feb 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer QU Q3 2025-2026.pdf | 7 Feb 2026 |
| Structural stability certificate signed by the Structural engineerFile: Strutural stability 2nd quiery .pdf | 24 Dec 2025 |
| Structural engineer licenseFile: 1Strucural eng license.pdf | 24 Dec 2025 |
| chartered accountant certificate (CA) in prescribed format form -01File: 1Form 1 CA.pdf | 20 Dec 2025 |
| bank affidavit in the prescribed format documentsFile: 1Bank Affidavit.pdf | 20 Dec 2025 |
| profit and loss account and balance sheet for 2022-23File: 1CA Letter for 2022-23.pdf | 20 Dec 2025 |
| sources of funds to complete the projectFile: 1Source of Funds.pdf | 20 Dec 2025 |
| Approved Original Single Plot layout planFile: 1Single site approval.pdf | 20 Dec 2025 |
| Approved Original Single Plot layout plan orderFile: 1Single site approval letter1.pdf | 20 Dec 2025 |
| Building License from Local Authority Original CopyFile: 1Building Licensce&fee receipt Panchayat approval.pdf | 20 Dec 2025 |
| ADLR Certified survey sketchFile: 1ADLR Sketch.pdf | 20 Dec 2025 |
| original sanctioned drawings, floor planFile: 1Plan Approval HPA Typical.pdf | 20 Dec 2025 |
| Upload all original sanctioned drawings, floor plan, sectional drawings and elevationsFile: 1Plan Approval HPA S+Ground-compressed.pdf | 20 Dec 2025 |
| commencement certificateFile: 1Commencement certificate (CC).pdf | 20 Dec 2025 |
| Village map certified by the competent authorityFile: 1Village Map.pdf | 20 Dec 2025 |
| self attseted copy of engineer licenceFile: 1Engineer licesece self attested.pdf | 20 Dec 2025 |
| structural stability certificateFile: 1Structural Stability certificate.pdf | 20 Dec 2025 |
| Structural engineer licenseFile: 1Strucural eng license.pdf | 20 Dec 2025 |
| payment planFile: 1Payment plan Abhayam.pdf | 20 Dec 2025 |
| Land cost CalculationFile: 1Land Cost Calculation Sheet (Sri Sai Abhayam ).pdf | 20 Dec 2025 |
| allotment letterFile: 1Allotment Lettetr Sri Sai Abhayam.pdf | 20 Dec 2025 |
| project estimationFile: 1Project estimation.pdf | 20 Dec 2025 |
| STP drawingFile: 1STP Drawings.pdf | 20 Dec 2025 |
| Draft AgreementFile: 1Agreement of sale Draft.pdf | 20 Dec 2025 |
| RTC, survey 29/6 | - |
| Mutation, survey 29/6 | - |
| Encumbrance Certificate, survey 29/6 | - |
| Conversion/Alienation Order, survey 29/6 | - |
| Sale/Title/Gift Deed, survey 29/6 | - |
| Khatha, survey 29/6 | - |
| Registration CertificateFile: Partnership reg certificate old & new.pdf | - |
| GST CertificateFile: GST Certificate Sadhguru.pdf | - |
| Partnership DeedFile: Partnership Reconstitution Sadhguru-New.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: 1Form 1 CA.pdf | - |
| Certificate issued by Architect Form 2File: Form 2 Architect.pdf | - |
| Certificate issued by Engineer Form 3File: Form 3 Engineer.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: 2Affidavit for Non-Litigation Details- With JDA.pdf | - |
| Balance Sheet 2024 - 2025File: Balance sheet 2024-25.pdf | - |
| Balance Sheet 2023 - 2024File: Balance sheet 23-24.pdf | - |
| Audited Profit and Loss Statement 2024 - 2025File: P&L 2024-25.pdf | - |
| Audited Profit and Loss Statement 2023 - 2024File: P&L 23-24.pdf | - |
| Income Tax Return Acknowledgement 2024 - 2025File: ITR FY 2024-25.pdf | - |
| Income Tax Return Acknowledgement 2023 - 2024File: ITR FY 2023-24.pdf | - |
| Commencement certificate (CC) | - |
| Plan Approval HPA S+Ground | - |
| Plan Approval HPA Typical | - |
| Structural statbility certificate | - |
| Specifications- Sri Sai Abhayam | - |
| Brochure letter | - |
| Relinquishment Deed | - |
| As of SRI SAI ABHAYAM Rera | - |
| Allotment letter Bendiganahalli revised | - |
| 3FORM B Affidavit | - |
| 5Notarized Affidavit for 3(1) Voliation | - |
| 4JD Affidavit cum declaration | - |
| Legal Opinion-Sri Sai Abhayam | - |
| BESCOM NOC | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep SRI SAI ABHAYAM on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 21 registered projects within 2 km.
UNITED PROJECTS DREAMCITY
UNITED PROJECTS
DISHA PURSUIT OF SUNSHINE
DISHAHABITAT PROJECTS LLP
TRIFECTA VERDE EN RESPLANDOR ROW HOUSE PHASE-2
TRIFECTA PROJECTS PVT LTD
BHARTHI VIHAR II
IKYA PROPERTIES
Gateway Meadows Phase-2 Extension
Gateway Shelters Private Limited
SWARAM PHASE-1
One Bangalore Luxury Projects LLP
See every Bengaluru Urban project, with the district possession charts
Builder: SADHGURU DEVELOPERS
SADHGURU DEVELOPERS has 1 registration on RERA Karnataka, including SRI SAI ABHAYAM. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if SRI SAI ABHAYAM is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SRI SAI ABHAYAM?
The registered promoter entity is SADHGURU DEVELOPERS, a partnership firm as per the filing. Its GSTIN 29AEYFS6039M1ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SRI SAI ABHAYAM?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SRI SAI ABHAYAM?
The professionals named in the filing: Architect: TATA VITTALA SRINIVAS; Engineer: MANDHADIVENKATARAMANAREDDY; Chartered Accountant: John Peter Narisetty. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SRI SAI ABHAYAM?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback