Home / Browse projects / Bengaluru Urban, Karnataka / DISHA PURSUIT OF SUNSHINE
DISHA PURSUIT OF SUNSHINE
RG-KA-57997 · RERA PRM/KA/RERA/1251/446/PR/100323/005790 · Last updated on RERA Karnataka portal: 4 Nov 2025
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
DISHA PURSUIT OF SUNSHINE is a Residential/Group Housing project by DISHAHABITAT PROJECTS LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/100323/005790 on 10 Mar 2023. Possession is promised by 31 Dec 2026. 319 of the 322 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete.
At a glance
Project
- NameDISHA PURSUIT OF SUNSHINE
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- 562129
- Pincode562129
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/446/PR/100323/005790
- ReraGenie IDRG-KA-57997
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on10 Mar 2023
- Promised completion31 Dec 2026
- Revised completionNone
- Buildings2 building records
- Documents filed107 files
Current status
Figures as on 4 Nov 2025, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Block 1 | - | - | - | 160 | 0 | 160 |
| Block 2 | - | - | - | 162 | 0 | 162 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 4 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
18 of 18 construction stages are filed complete.
Building: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | 100% |
| RCC or MS Framed structure | 100% |
| Masonry Construction | 100% |
| Plastering inside , outside & Ceiling | 100% |
| Joinery: Doors, Windows, Ventilators etc | 100% |
| Basic work of Water supply, Sanitary and Electrification | 100% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 100% |
| Railing and Grill fixing | 100% |
| Electrification, Water supply and Sanitary Finishing | 100% |
| Painting | 100% |
| Fire prevention and fire fighting fitting and fixture with network | 100% |
| Weather Proof work(tile,concrete) | 100% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 100% |
| Internal and External work including landscapes as per sanctioned drawings | 100% |
Progress on shared amenities38
As on 4 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 100% |
| Sewage and Drainage System | Yes | 100% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 100% |
| Energy management | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Solid waste management and disposal | Yes | 100% |
| Emergency Evacuation services | Yes | 100% |
| Internal Roads & Footpaths | Yes | 100% |
| Electricity supply transformer and substation | Yes | 100% |
| Storm water drains | Yes | 100% |
| Use of renewable energy | Yes | 100% |
| Sewage Treatment Plant (STP) | Yes | 100% |
| Parks & Tree planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Electricity | Yes | 100% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 100% |
| Club House | Yes | 100% |
| Community Hall | Yes | 100% |
| Outdoor Sports facility | Yes | 100% |
| Indoor Sports facility | Yes | 100% |
| Swimming Pool | Yes | 100% |
| Gym | Yes | 100% |
| Parks | Yes | 100% |
| Power Backup | Yes | 100% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 100% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 100% |
| Lifts | Yes | 100% |
| Corridor/Lobbies | Yes | 100% |
| Fire escapes | Yes | 100% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 100% |
| Basement | Yes | 100% |
| Terrace | Yes | 100% |
| Outer Wall | Yes | 100% |
| Open parking areas | Yes | 100% |
| Provision for lodging of management staff and security staff | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| DISHAHABITAT PROJECTS LLP | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 120.87 cr | Rs 92.91 lakh |
| On-site expenditure-Cost Of Services(Water, Electricity, Sewage) | Rs 9.06 cr | Rs 6.30 lakh |
| On-site expenditure-Consultants Fees | Rs 6.04 cr | Rs 38.59 lakh |
| Principal sum and interest payable to financial institutions-Scheduled Banks | Rs 6.04 cr | - |
| Payment of taxes | Rs 2.80 cr | - |
| On-site expenditure-Salaries of workers | - | Rs 33.86 lakh |
| On-site expenditure-Site Overhead | - | Rs 14.16 lakh |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ASOKA BABU MORLA |
| Engineer | SANTOSH KUMAR N B |
| Chartered Accountant | D Manoj |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed107
As listed on the registration, under the names the promoter filed them with; the newest 80 of 107 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/100323/005790 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate_compressed (1).pdf | 4 Nov 2025 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-2_Architect__Oct_2025.pdf | 4 Nov 2025 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Enginner Certificate.pdf | 4 Nov 2025 |
| Q3 2025-26 Water supply and sewage board | 4 Nov 2025 |
| Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 4 Nov 2025 |
| Q3 2025-26 KPTCL- BESCOM | 4 Nov 2025 |
| Q3 2025-26 Fire and Safety | 4 Nov 2025 |
| Q3 2025-26 Airport Authority of India | 4 Nov 2025 |
| Q3 2025-26 BSNL/Telecommunication Department | 4 Nov 2025 |
| Q3 2025-26 Registration documentFile: Opinion Formation of Apartment Owners Associations (Disha habitat ).pdf | 4 Nov 2025 |
| Covering LetterFile: Covering Letter.pdf | 9 Mar 2023 |
| Affidavit and DeclarationFile: Affidavit and Declaration.pdf | 9 Mar 2023 |
| Profile of Promoters and companyFile: Profile of Promoters and company.pdf | 9 Mar 2023 |
| Final Sanction letter after signedFile: Final Sanction letter after signed.pdf | 9 Mar 2023 |
| ITR 2020-21File: 1 ITR 2020-21.pdf | 27 Feb 2023 |
| Financials 2020-21File: 2 Financials 2020-21.pdf | 27 Feb 2023 |
| ITR 2021-22File: 3 ITR 2021-22.pdf | 27 Feb 2023 |
| Disha Habitat Balance sheet and P&L 2021-22File: 4 Disha Habitat Balance sheet and P&L 2021-22.pdf | 27 Feb 2023 |
| Development Plan OrderFile: 5 Development Plan Order.pdf | 27 Feb 2023 |
| Typical Floor Plan 1-18thFile: 6 Typical Floor Plan 1-18th.pdf | 27 Feb 2023 |
| Section PlanFile: 7 Section Plan.pdf | 27 Feb 2023 |
| Terrace and Elevation PlanFile: 8 Terrace and Elevation Plan.pdf | 27 Feb 2023 |
| Basement and Ground Floor PlanFile: 9 Basement and Ground Floor Plan.pdf | 27 Feb 2023 |
| Development PlanFile: 10 Development Plan.pdf | 27 Feb 2023 |
| Site PlanFile: 11 Site Plan.pdf | 27 Feb 2023 |
| Engineer Certificate along with Estimated CostFile: 12 Engineer Certificate along with Estimated Cost.pdf | 27 Feb 2023 |
| Proforma Allotment LetterFile: 13 Proforma Allotment Letter.pdf | 27 Feb 2023 |
| Proforma Agreement of SaleFile: 14 Proforma Agreement of Sale.pdf | 27 Feb 2023 |
| RTC, survey 210 | - |
| Mutation, survey 210 | - |
| Encumbrance Certificate, survey 210 | - |
| Conversion/Alienation Order, survey 210 | - |
| Sale/Title/Gift Deed, survey 210 | - |
| Khatha, survey 210 | - |
| Registration CertificateFile: Certificate of LLP Incorporation.PDF | - |
| Partnership DeedFile: Dishahabitat Projects LLP_Partnership Deed.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: Form 1_CA Certificate.pdf | - |
| Certificate issued by Architect Form 2File: Form-2 Architect Certficate.pdf | - |
| Certificate issued by Engineer Form 3File: Form-3 Engineer Certificarte.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Affidavit_Declartion abt Non litigation.pdf | - |
| Certificate from Chartered AccountFile: Form 1_CA Certificate.pdf | - |
| Balance Sheet 2021 - 2022File: Disha Habitat Balance sheet and P&L 2021-22.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: Disha Habitat Balance sheet and P&L 2021-22.pdf | - |
| Director's Report 2021 - 2022File: Disha Habitat Balance sheet and P&L 2021-22.pdf | - |
| Cash Flow Statement 2021 - 2022File: Disha Habitat Balance sheet and P&L 2021-22.pdf | - |
| Auditor's Report 2021 - 2022File: Disha Habitat Balance sheet and P&L 2021-22.pdf | - |
| Income Tax Return Acknowledgement 2021 - 2022File: ITR 2021-22.pdf | - |
| Commencement Certificate | - |
| BESCOM NOC with fee paid receipt | - |
| Water NOC | - |
| Development Plan | - |
| Development Plan | - |
| Development Plan | - |
| Project Specifications with Sign and Signature | - |
| Section Plan | - |
| Project Specifications with Sign and Signature | - |
| Terrace and Elevation Plan | - |
| Structural Stability Certficate | - |
| Legal Opnion | - |
| Mother Deed | - |
| Proforma Agreement of Sale | - |
| Proforma Allotment letter | - |
| Brochure | - |
| Form B -Affidavit | - |
| Affidavit_Declartion abt Non litigation | - |
| BESCOM NOC with fee paid receipt | - |
| Water NOC | - |
| Unnamed document | - |
| Unnamed document | - |
| FIRE NOC | - |
| Airport Authorty NOC | - |
| KSPCB NOC with Fee paid receipt | - |
| Unnamed document | - |
| BSNL NOC | - |
| Unnamed document | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep DISHA PURSUIT OF SUNSHINE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 20 registered projects within 2 km.
UNITED PROJECTS DREAMCITY
UNITED PROJECTS
SRI SAI ABHAYAM
SADHGURU DEVELOPERS
TRIFECTA VERDE EN RESPLANDOR ROW HOUSE PHASE-2
TRIFECTA PROJECTS PVT LTD
BHARTHI VIHAR II
IKYA PROPERTIES
Gateway Meadows Phase-2 Extension
Gateway Shelters Private Limited
SWARAM PHASE-1
One Bangalore Luxury Projects LLP
See every Bengaluru Urban project, with the district possession charts
Builder: DISHAHABITAT PROJECTS LLP
Dishahabitat Projects LLP has 3 registrations on RERA Karnataka, including Disha Pursuit of the Elements Phase II and DISHA PURSUIT OF THE ELEMENTS PHASE 1. Its filings declare 2 earlier projects, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if DISHA PURSUIT OF SUNSHINE is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of DISHA PURSUIT OF SUNSHINE?
The registered promoter entity is DISHAHABITAT PROJECTS LLP, a partnership firm as per the filing. Its LLPIN AAU-7415 and GSTIN 29AARFD7369L1ZF can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in DISHA PURSUIT OF SUNSHINE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at DISHA PURSUIT OF SUNSHINE?
The professionals named in the filing: Architect: ASOKA BABU MORLA; Engineer: SANTOSH KUMAR N B; Chartered Accountant: D Manoj. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DISHA PURSUIT OF SUNSHINE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.