Home / Browse projects / Bengaluru Urban, Karnataka / Spectra Parijatha

Registration approved No litigation declared Residential/Group Housing project

Spectra Parijatha

By Spectra Constructions Private Limited

RG-KA-76927 · RERA PRM/KA/RERA/1251/446/PR/251023/006346 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Aug 2028Possession promisedno revision filed
6 of 18Construction stages donefurthest along: Weather Proof work(tile, 95%
59 of 140Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 176 documents Report an error

Spectra Parijatha is a Residential/Group Housing project by Spectra Constructions Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/251023/006346 on 25 Oct 2023. Possession is promised by 31 Aug 2028. 81 of the 140 units on this registration are recorded sold or booked, and 6 of 18 construction stages are filed complete.

At a glance

Project

  • NameSpectra Parijatha
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560066
  • Pincode560066
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/251023/006346
  • ReraGenie IDRG-KA-76927

Builder

  • NameSpectra Constructions Private Limited
  • Entity typeCompany
  • CINU45209KA1999PTC025826
  • GSTIN29AAFCS8564H1ZS
  • Authorized SignatoryC Chandrashekar
  • Managing DirectorC Chandrashekar
  • DirectorsC Chandrashekar, Manjula C Raju
  • Project HeadVishal C Raju
  • Other registrations4 more →
  • Declared earlier projects4 →

Key dates

this monthRegisteredOct 2023PromisedAug 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on25 Oct 2023
  • Promised completion31 Aug 2028
  • Revised completionNone
  • Buildings3 building records
  • Documents filed176 files

Current status

58%81 of 140 units booked
5.1%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower A---36036
Tower B---52052
Tower C---52052

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 18 construction stages are filed complete. The stage furthest along is Weather Proof work(tile, at 95%.

Building: 61% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level0%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc25%
Basic work of Water supply, Sanitary and Electrification85%
Dadoing, Skirting, Flooring, Tiles work (All types)75%
Railing and Grill fixing90%
Electrification, Water supply and Sanitary Finishing20%
Painting45%
Fire prevention and fire fighting fitting and fixture with network5%
Weather Proof work(tile,concrete)95%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work45%
Internal and External work including landscapes as per sanctioned drawings20%

Progress on shared amenities40

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes80%
Sewage and Drainage SystemYes70%
Water conservation/rain water harvesting/recharge of ground waterYes10%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes5%
Solid waste management and disposalYes5%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes5%
Electricity supply transformer and substationYes5%
Storm water drainsYes5%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes15%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes5%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes55%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes60%
GymYes0%
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes60%
LiftsYes25%
Corridor/LobbiesYes60%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementYes60%
TerraceYes75%
Outer WallNoNot applicable
Open parking areasYes10%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership13

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,545 sq m
Named landowners13
LandownerVillageDistrict
P. K. Raghothama Rao--
R. Ramesh Rao--
R. Rekha Rao--
Ramya. S.--
Biju Thoppil John--
R. Mahalakshmi Rao--
Pavan Shiralagi--
Shilpa Shiralagi--
Jyothi Rao--
T. S. Amarnath--
Gagan Shiralagi--
Sneha Shiralagi--
Gita R Rao--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 83.14 cr
Cost incurredRs 4.26 cr
Spent of the estimate5.12%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 73.14 crRs 4.26 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 10.00 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnup Naik
EngineerDhruvaraj Iyengar
Chartered AccountantSaurabh Srivastava

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed176

As listed on the registration, under the names the promoter filed them with; the newest 80 of 176 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/251023/006346 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Q2 26-27 Parijatha.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 A Q2 26-27 Parijatha.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 E Q2 26-27 Parijatha.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q2 2026-27 Fire and Safety14 Oct 2026
Q2 2026-27 Airport Authority of India14 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: From 4 CA Q1 26 - 27 Parijatha.pdf13 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 A Q1 26-27 Parijatha.pdf13 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 E Q1 26-27 Parijatha.pdf13 Jul 2026
Q1 2026-27 Water supply and sewage board13 Jul 2026
Q1 2026-27 KPTCL- BESCOM13 Jul 2026
Q1 2026-27 Fire and Safety13 Jul 2026
Q1 2026-27 Airport Authority of India13 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department13 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Q4 25-26 Parijatha Comp.pdf11 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 A Q4 25-26 Parijatha.pdf11 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 E Q4 25-26 Parijatha.pdf11 Apr 2026
Q4 2025-26 Water supply and sewage board11 Apr 2026
Q4 2025-26 KPTCL- BESCOM11 Apr 2026
Q4 2025-26 Fire and Safety11 Apr 2026
Q4 2025-26 Airport Authority of India11 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department11 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Q3 25-26 Parijatha.pdf13 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 A Q3 25-26 Parijatha.pdf13 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 E Q3 25-26 Parijatha.pdf13 Jan 2026
Q3 2025-26 Water supply and sewage board13 Jan 2026
Q3 2025-26 KPTCL- BESCOM13 Jan 2026
Q3 2025-26 Fire and Safety13 Jan 2026
Q3 2025-26 Airport Authority of India13 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department13 Jan 2026
P&L - FY 2019-20File: E - PL - FY 2019-20.pdf17 Oct 2023
P&L - FY 2020-21File: E - PL - FY 2020-21.pdf17 Oct 2023
P&L - FY 2021-22File: E - PL - FY 2021-22.pdf17 Oct 2023
Balance Sheet - FY 2019-20File: E - BS - FY 2019-20.pdf17 Oct 2023
Balance Sheet - FY 2020-21File: E - BS - FY 2020-21.pdf17 Oct 2023
Balance Sheet - FY 2021-22File: E - BS - FY 2021-22.pdf17 Oct 2023
Source of FundsFile: E - Source of Funds.pdf17 Oct 2023
Project DetailsFile: E - Project Details.pdf17 Oct 2023
BBMP Plan Sanction - Site PlanFile: E - BBMP Plan Sanction - Site Plan.pdf17 Oct 2023
BBMP Plan Sanction - Basement Floor PlanFile: E - BBMP Plan Sanction - Basement Floor Plan.pdf17 Oct 2023
BBMP Plan Sanction - Ground Floor PlanFile: E - BBMP Plan Sanction - Ground Floor Plan.pdf17 Oct 2023
BBMP Plan Sanction - First & Second Floor PlanFile: E - BBMP Plan Sanction - First & Second Floor Plan.pdf17 Oct 2023
BBMP Plan Sanction - Typical & Terrace Floor PlanFile: E - BBMP Plan Sanction - Typical & Terrace Floor Plan.pdf17 Oct 2023
BBMP Plan Sanction - Section & ElevationFile: E - BBMP Plan Sanction - Section & Elevation.pdf17 Oct 2023
BBMP Plan Sanction - CompleteFile: E - BBMP Plan Sanction - Complete.pdf17 Oct 2023
Carpet Area DetailsFile: E - Carpet Area Details.pdf17 Oct 2023
Commencement CertificateFile: E - Commencement Certificate.pdf17 Oct 2023
Engineer's CertificateFile: E - Certificate Engineer.pdf17 Oct 2023
BWSSB NOC Cum Fee PaymentFile: E - BWSSB NOC Fee Payment.pdf17 Oct 2023
BESCOM NOC Cum Fee PaymentFile: E - BESCOM NOC Fee Payment.pdf17 Oct 2023
Stability CertificateFile: E - Structural Safety.pdf17 Oct 2023
Proforma Agreement to SellFile: E - Proforma Agreement to Sell.pdf17 Oct 2023
BorewellFile: E - Borewell Details.JPG17 Oct 2023
FY 19-20 ConsolidatedFile: 1 E - FY 19-20 Consolidated.pdf12 Oct 2023
FY 20-21 ConsolidatedFile: 2 E - FY 20-21 Consolidated.pdf12 Oct 2023
FY 21-22 ConsolidatedFile: 3 E - FY 21-22 Consolidated.pdf12 Oct 2023
RERA Bank Account DetailsFile: 4 E - RERA Bank Account Details.pdf12 Oct 2023
BBMP Plan SanctionFile: 5 E - BBMP Plan Sanction.pdf12 Oct 2023
Source of FundsFile: 6 E - Source of Funds.pdf12 Oct 2023
CA CertificateFile: 7 E - CA Certificate.pdf12 Oct 2023
Non-Litigation AffidavitFile: 8 E - Non-Litigation Affidavit.pdf12 Oct 2023
Landowner DetailsFile: 9 E - Landowner Details.pdf12 Oct 2023
Development AgreementFile: 10 E - Development Agreement.pdf12 Oct 2023
Sy No 80-2 DeedsFile: 11 E - Sy No 80-2 Deeds.pdf12 Oct 2023
Sy No 80-3 DeedsFile: 12 E - Sy No 80-3 Deeds.pdf12 Oct 2023
Sy No 80-4 DeedsFile: 13 E - Sy No 80-4 Deeds.pdf12 Oct 2023
Sy No 80-2 RTCFile: 14 E - Sy No 80-2 RTC.pdf12 Oct 2023
Sy No 80-3 RTCFile: 15 E - Sy No 80-3 RTC.pdf12 Oct 2023
Sy No 80-4 RTCFile: 16 E - Sy No 80-4 RTC.pdf12 Oct 2023
Sy No 80-2 KhataFile: 17 E - Sy No 80-2 Khata.pdf12 Oct 2023
Sy No 80-3 KhataFile: 18 E - Sy No 80-3 Khata.pdf12 Oct 2023
Sy No 80-4 KhataFile: 19 E - Sy No 80-4 Khata.pdf12 Oct 2023
Combined Property KhataFile: 20 E - Combined Property Khata.pdf12 Oct 2023
Encumberance CertificateFile: 21 E - Encumberance Certificate.pdf12 Oct 2023
Joint Affidavit Cum DeclarationFile: 22 E - Joint Affidavit Cum Declaration.pdf12 Oct 2023
Guideline Value CertificateFile: 23 E - Guideline Value Certificate.pdf12 Oct 2023
Project Details & BBMP Plan SanctionFile: 24 E - Project Details & BBMP Plan Sanction.pdf12 Oct 2023
Carpet Area DetailsFile: 25 E - Carpet Area Details.pdf12 Oct 2023

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Spectra RaywoodsNo. 60 & 61, Millers Road,Completed-No date filed
Spectra RaayaNo. 577/443, Siddapura, Varthur Hobli,Completed-No date filed

How this compares with Bengaluru Urban

58%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Spectra Parijatha on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSpectra ParijathaOther 44Dot size: filed unitsN

Filed coordinates, straight-line distance. 44 registered projects within 2 km.

Builder: Spectra Constructions Private Limited

Spectra Constructions Private Limited has 5 registrations on RERA Karnataka, including Spectra Mira and Spectra Reserve. Its filings declare 4 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Spectra Parijatha is delayed beyond 31 Aug 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Spectra Parijatha?

The registered promoter entity is Spectra Constructions Private Limited, a company as per the filing. Its CIN U45209KA1999PTC025826 and GSTIN 29AAFCS8564H1ZS can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Spectra Parijatha?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Spectra Parijatha?

The professionals named in the filing: Architect: Anup Naik; Engineer: Dhruvaraj Iyengar; Chartered Accountant: Saurabh Srivastava. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Spectra Parijatha?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Spectra Parijatha. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Spectra Parijatha to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.