SOWPARNIKA INDRADHANUSH PHASE II

By SOWPARNIKA HOMES PRIVATE LIMITED

RG-KA-20669 · RERA PRM/KA/RERA/1250/304/PR/200123/005641 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Nov 2027Possession promisedno revision filed
18 of 18Construction stages doneevery applicable stage filed complete
3 of 360Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 133 documents Report an error

SOWPARNIKA INDRADHANUSH PHASE II is a Residential/Group Housing project by SOWPARNIKA HOMES PRIVATE LIMITED in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/304/PR/200123/005641 on 20 Jan 2023. Possession is promised by 30 Nov 2027. 357 of the 360 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete.

At a glance

Project

  • NameSOWPARNIKA INDRADHANUSH PHASE II
  • TypeResidential/Group Housing
  • Location
    • Hosakote
    • Bengaluru Rural
    • 562114
  • Pincode562114
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1250/304/PR/200123/005641
  • ReraGenie IDRG-KA-20669

Builder

  • NameSOWPARNIKA HOMES PRIVATE LIMITED
  • Entity typeCompany
  • CINU45400KA2014PTC074654
  • GSTIN29AAUCS5844F1ZO
  • Authorized SignatoryMEENAKSHI RAMJI
  • DirectorMEENAKSHI RAMJ
  • DirectorsMEENAKSHI RAMJI, S SREENIVASAN
  • Project HeadMEENAKSHI RAMJI
  • Other registrations4 more →
  • Declared earlier projects5 →

Key dates

this monthRegisteredJan 2023PromisedNov 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on20 Jan 2023
  • Promised completion30 Nov 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed133 files

Current status

99%357 of 360 units booked
151.7%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SOWPARNIKA INDRADHANUSH PHASE II---3600360

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 18 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Solid waste management and disposalYes100%
Emergency Evacuation servicesYes100%
Internal Roads & FootpathsYes100%
Electricity supply transformer and substationYes100%
Storm water drainsYes100%
Use of renewable energyYes100%
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingYes100%
Street LightingYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksYes100%
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationYes100%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesYes100%
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areasYes100%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes100%
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area21,625 sq m
Named landowners1
LandownerVillageDistrict
SOWPARNIKA HOMES PRIVATE LIMITED--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 109.37 cr
Cost incurredRs 165.95 cr
Spent of the estimate151.74%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 56.31 crRs 91.95 cr
Administrative CostRs 43.24 crRs 56.85 cr
Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for constructionRs 8.55 crRs 11.95 cr
Payment of taxesRs 1.27 crRs 5.20 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMANIRAJ D
EngineerVAIBHAV KUMAR J G
Chartered AccountantMANAS RANJAN KAR

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed133

As listed on the registration, under the names the promoter filed them with; the newest 80 of 133 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/304/PR/200123/005641 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4, CA (QU) Indradhanush II -FY 26-27 Q2_signed_.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form - 5 - Architect Certificate ID Phase II Q2 2627.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form - 6 -INDRADHANUSH PH II Eng Certificate Q2 -2627.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Indradhanush II Q1 26-27.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form - 5 - Architect Certificate ID Phase II Q1 2627.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form - 6 -INDRADHANUSH PH II Eng Certificate Q1 -2627.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4A CA Indradansuh II Merged.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form - 5 - Architect Certificate (QU) INDRADHANUSH PH II Q4.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form - 6 -ID II ENg Certificate.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: IND II.pdf13 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate QU INDRADHANUSH PH II Q3 compressed.pdf13 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 INDRADHANUSH PH II Eng Certificate QU Q3.pdf13 Jan 2026
Q3 2025-26 Water supply and sewage board13 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)13 Jan 2026
Q3 2025-26 KPTCL- BESCOM13 Jan 2026
Q3 2025-26 Fire and Safety13 Jan 2026
Q3 2025-26 Airport Authority of India13 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department13 Jan 2026
Form 1File: Form 1.pdf15 Jan 2023
SHPL - Directors Report - FY 21-22File: SHPL - Directors Report - FY 21-22.pdf15 Jan 2023
SHPL - BS - FY 21-22File: SHPL - BS - FY 21-22.pdf15 Jan 2023
SHPL - Audit Report - FY 21-22File: SHPL - Audit Report - FY 21-22.pdf15 Jan 2023
SHPL - PL - FY 21-22File: SHPL - PL - FY 21-22.pdf15 Jan 2023
SHPL - ITR - FY 21-22File: SHPL - ITR - FY 21-22.pdf15 Jan 2023
SHPL - Cash Flow - FY 21-22File: SHPL - Cash Flow - FY 21-22.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - 1 Sale Deed -Sy No 9-1-SPIPL - 11 GuntasFile: Sowparnika Indradhanush Phase II - 1 Sale Deed -Sy No 9-1-SPIPL - 11 Guntas.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - 2 Sale deed -Sy No 9-1 - SPIPL - 2 Acres 5 GuntasFile: Sowparnika Indradhanush Phase II - 2 Sale deed -Sy No 9-1 - SPIPL - 2 Acres 5 Guntas.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - 3 Sale deed -Sy No 9-2- SPIPL - 1 Acre 30 GuntasFile: Sowparnika Indradhanush Phase II - 3 Sale deed -Sy No 9-2- SPIPL - 1 Acre 30 Guntas.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - 4 Sale Deed -Sy No 129-3-SPIPL - 10Acres 08 GuntasFile: Sowparnika Indradhanush Phase II - 4 Sale Deed -Sy No 129-3-SPIPL - 10Acres 08 Guntas.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - e-Khatha - Full ExtentFile: Sowparnika Indradhanush Phase II - e-Khatha - Full Extent.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - Order of District Registrar - Value of the PropertyFile: Sowparnika Indradhanush Phase II - Order of District Registrar - Value of the Property.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - Title Deed to Conversion Land OwnerFile: Sowparnika Indradhanush Phase II - Title Deed to Conversion Land Owner.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - Affidavit for No LitigationFile: Sowparnika Indradhanush Phase II - Affidavit for No Litigation.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - Plan Sanctions - 1 of 6 - Approved Layout PlanFile: Sowparnika Indradhanush Phase II - Plan Sanctions - 1 of 6 - Approved Layout Plan.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - Plan Sanctions - 2 of 6 - Basement FloorFile: Sowparnika Indradhanush Phase II - Plan Sanctions - 2 of 6 - Basement Floor.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - Plan Sanctions - 3 of 6 - Stilt Floor PlanFile: Sowparnika Indradhanush Phase II - Plan Sanctions - 3 of 6 - Stilt Floor Plan.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - Plan Sanctions - 4 of 6 - Typical Floor PlanFile: Sowparnika Indradhanush Phase II - Plan Sanctions - 4 of 6 - Typical Floor Plan.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - Plan Sanctions - 5 of 6 - Terrace Floor PlanFile: Sowparnika Indradhanush Phase II - Plan Sanctions - 5 of 6 - Terrace Floor Plan.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - Carpet Area Statement - Certified by ArchitectFile: Sowparnika Indradhanush Phase II - Carpet Area Statement - Certified by Architect.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - Clarification on Area Details for Phase I & IIFile: Sowparnika Indradhanush Phase II - Clarification on Area Details for Phase I & II.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - Clarification on Project Area and Khata AreaFile: Sowparnika Indradhanush Phase II - Clarification on Project Area and Khata Area.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - Constrction Cost Break-up - Certified by EngineerFile: Sowparnika Indradhanush Phase II - Constrction Cost Break-up - Certified by Engineer.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - Developmenent Plan (Extract of Master Plan)File: Sowparnika Indradhanush Phase II - Developmenent Plan (Extract of Master Plan).pdf15 Jan 2023
Sowparnika Indradhanush Phase II - Developmenent Plan Approval LetterFile: Sowparnika Indradhanush Phase II - Developmenent Plan Approval Letter.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - Form 3 - Engineer CertificateFile: Sowparnika Indradhanush Phase II - Form 3 - Engineer Certificate.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - Location and Demarcation DrawingFile: Sowparnika Indradhanush Phase II - Location and Demarcation Drawing.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - MAP - CDP Map with Sy No MarkedFile: Sowparnika Indradhanush Phase II - MAP - CDP Map with Sy No Marked.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - MAP - Village MAP - YelachanayakanapuraFile: Sowparnika Indradhanush Phase II - MAP - Village MAP - Yelachanayakanapura.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - STP Demarcation Plan along with STP Design DrawingsFile: Sowparnika Indradhanush Phase II - STP Demarcation Plan along with STP Design Drawings.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - Affidavit for BESCOM NOCFile: Sowparnika Indradhanush Phase II - Affidavit for BESCOM NOC.pdf15 Jan 2023
Sowparnika Indradhanush Phase II - Affidavit Under Sec 3(1)File: Sowparnika Indradhanush Phase II - Affidavit Under Sec 3(1).pdf15 Jan 2023
Sowparnika Indradhanush Phase II - Plan Sanctions - 6 of 6 - Elevation and Section DrawingsFile: Sowparnika Indradhanush Phase II - Plan Sanctions - 6 of 6 - Elevation and Section Drawing15 Jan 2023
Sowparnika Indradhanush Phase II - Plan Sanctions - 1 of 6 - Approved Layout Plan - Version IFile: Sowparnika Indradhanush Phase II - Plan Sanctions - 1 of 6 - Approved Layout Plan - Versio15 Jan 2023
Sowparnika Indradhanush Phase II - Plan Sanctions - 1 of 6 - Approved Layout Plan - Version IIFile: Sowparnika Indradhanush Phase II - Plan Sanctions - 1 of 6 - Approved Layout Plan - Versio15 Jan 2023
Registration CertificateFile: SHPL - Registration Certificate.pdf-
Organization StructureFile: SHPL - Org Structure.pdf-
Certificate issued by CA Form 1File: Form 1.pdf-
Certificate issued by Architect Form 2File: Sowparnika Indradhanush Phase II - Form 2 - Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Sowparnika Indradhanush Phase II - Form 3 - Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-

How this compares with Bengaluru Rural

99%of this project is bookeddistrict median 45%
20%of Bengaluru Rural projects moved their completion datethis one has not
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep SOWPARNIKA INDRADHANUSH PHASE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

2 kmSOWPARNIKA INDRADHANUSH Other 9Dot size: filed unitsN

Filed coordinates, straight-line distance. 9 registered projects within 2 km.

Builder: SOWPARNIKA HOMES PRIVATE LIMITED

SOWPARNIKA HOMES PRIVATE LIMITED has 5 registrations on RERA Karnataka, including Sowparnika The Native and SOWPARNIKA EUPHORIA IN THE EAST. Its filings declare 5 earlier projects, none of them declared completed. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if SOWPARNIKA INDRADHANUSH PHASE II is delayed beyond 30 Nov 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SOWPARNIKA INDRADHANUSH PHASE II?

The registered promoter entity is SOWPARNIKA HOMES PRIVATE LIMITED, a company as per the filing. Its CIN U45400KA2014PTC074654 and GSTIN 29AAUCS5844F1ZO can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SOWPARNIKA INDRADHANUSH PHASE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SOWPARNIKA INDRADHANUSH PHASE II?

The professionals named in the filing: Architect: MANIRAJ D; Engineer: VAIBHAV KUMAR J G; Chartered Accountant: MANAS RANJAN KAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SOWPARNIKA INDRADHANUSH PHASE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SOWPARNIKA INDRADHANUSH PHASE II. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SOWPARNIKA INDRADHANUSH PHASE II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.