Registration approved No litigation declared Residential/Group Housing project

Sobha Hamptons -Townpark Phase 2 W1 to 3

By SOBHA LIMITED

RG-KA-72568 · RERA PRM/KA/RERA/1251/308/PR/230125/007418 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2033Possession promisedno revision filed
0 of 17Construction stages donefurthest along: Earth work and other leveling..., 89%
242 of 492Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 391 documents Report an error

Sobha Hamptons -Townpark Phase 2 W1 to 3 is a Residential/Group Housing project by SOBHA LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/230125/007418 on 23 Jan 2025. Possession is promised by 30 Jun 2033. 250 of the 492 units on this registration are recorded sold or booked, and 0 of 17 construction stages are filed complete.

At a glance

Project

  • NameSobha Hamptons -Townpark Phase 2 W1 to 3
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
    • 562107
  • Pincode562107
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/230125/007418
  • ReraGenie IDRG-KA-72568

Builder

  • NameSOBHA LIMITED
  • Entity typeCompany
  • CINL45201KA1995PLC018475
  • GSTIN29AABCS7723E1ZB
  • Authorized SignatoryPavithra G Kalmath
  • Managing DirectorMr Jagadish Nangineni
  • DirectorMr Jagadish Nangineni
  • Project HeadMr. Yatheesha
  • Other registrations119 more →
  • No longer live8 withdrawn or revoked
  • Declared earlier projects196 →

Key dates

this monthRegisteredJan 2025PromisedJun 2033

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on23 Jan 2025
  • Promised completion30 Jun 2033
  • Revised completionNone
  • Buildings3 building records
  • Documents filed391 files

Current status

51%250 of 492 units booked
4.0%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING - 1---1640164
WING - 2---1640164
WING - 3---1640164

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 17 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 89%.

Building: 9% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work89%
Foundation footing work67%
Upto Plinth Level3%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)Not applicable
RCC or MS Framed structure0%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes0%
Swimming PoolNoNot applicable
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership33

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area20,489 sq m
Named landowners33
LandownerVillageDistrict
A G Hemanth Kumar--
Urban Spaces Projects P. Ltd--
Urban Spaces Projects P. Ltd--
Urban Spaces Projects P. Ltd--
Urban Spaces Projects P. Ltd--
Urban Spaces Projects P. Ltd--
Sheela kulakarni--
Nambiar Builders Pvt ltd--
Urban Spaces Projects P. Ltd--
B Ramaiah--
Urban Spaces Projects P. Ltd--
Urban Spaces Projects P. Ltd--
Urban Spaces Projects P. Ltd--
Urban Spaces Projects P. Ltd--
Urban Spaces Projects P. Ltd--
Urban Spaces Projects P. Ltd--
Urban Spaces Projects P. Ltd--
Urban Spaces Projects P. Ltd--
Abhinandan T S--
A G Hemanth Kumar--
A G Hemanth Kumar--
Abhinandan T S--
Abhinandan T S--
A G Hemanth Kumar--
Urban Spaces Projects P. Ltd--
Urban Spaces Projects P. Ltd--
Urban Spaces Projects P. Ltd--
Urban Spaces Projects P. Ltd--
Amit Ompraksh Poojari--
Urban Spaces Projects P. Ltd--
Urban Spaces Projects P. Ltd--
Abhinandan T S--
Urban Spaces Projects P. Ltd--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 661.53 cr
Cost incurredRs 26.74 cr
Spent of the estimate4.04%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 496.32 crRs 18.48 cr
Payment of taxesRs 66.13 crRs 5.55 cr
On-site expenditure-Consultants FeesRs 62.25 cr-
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 36.83 cr-
On-site expenditure-Site Overhead-Rs 1.37 cr
Principal sum and interest payable to financial institutions-Scheduled Banks-Rs 1.33 cr

Certifying professionals and partners4

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectArun Kumar
EngineerOUSEPPACHAN.C.AMBOOKEN
EngineerBalakrishnan G
Chartered AccountantBalaji D

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed391

As listed on the registration, under the names the promoter filed them with; the newest 80 of 391 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/230125/007418 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Hamptions PH2 C.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Hampton Ph2.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Hampton Ph2.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q2 2026-27 Fire and Safety14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Hamptions PH2.pdf13 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Hamptons PH2.pdf13 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Hampton Phase 2.pdf13 Jul 2026
Q1 2026-27 Water supply and sewage board13 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Jul 2026
Q1 2026-27 KPTCL- BESCOM13 Jul 2026
Q1 2026-27 Fire and Safety13 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Hamptions PH2.pdf13 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Hampton Phase 2.pdf13 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Hamptons Phase 2.pdf13 Apr 2026
Q4 2025-26 Water supply and sewage board13 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)13 Apr 2026
Q4 2025-26 KPTCL- BESCOM13 Apr 2026
Q4 2025-26 Fire and Safety13 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Hamptions PH2.pdf12 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Hampton PH2.pdf12 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Hampton PH 2.pdf12 Jan 2026
Q3 2025-26 Water supply and sewage board12 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)12 Jan 2026
Q3 2025-26 KPTCL- BESCOM12 Jan 2026
Q3 2025-26 Fire and Safety12 Jan 2026
Form-1 Sobha Hamptons -Townpark Phase 2 W1 to 3File: Form-1 Sobha Hamptons -Townpark Phase 2 W1 to 3.pdf22 Jan 2025
Amalgamated Khata-Form9File: 1 Amalgamated Khata-Form9.pdf22 Jan 2025
Discharge Deed sy no 74-6 Doc 5632-2015-16File: 2 Discharge Deed sy no 74-6 Doc 5632-2015-16.pdf22 Jan 2025
Discharge Deed Sy No 54-1 Doc 1783-2015-16File: 3 Discharge Deed Sy No 54-1 Doc 1783-2015-16.pdf22 Jan 2025
Conversion Order 56-6 2-24 GFile: 4 Conversion Order 56-6 2-24 G.pdf22 Jan 2025
Conversion Order 56-6 01-7 GFile: 5 Conversion Order 56-6 01-7 G.pdf22 Jan 2025
SY NO 54-3 & 54-5 NOC FROM CANARA BANK001File: 6 SY NO 54-3 & 54-5 NOC FROM CANARA BANK001.pdf22 Jan 2025
Deed of Discharge - piramal doc no 1541-2021-22File: 7 Deed of Discharge - piramal doc no 1541-2021-22.pdf22 Jan 2025
Discharge Deed dt 15-10-2020, Doc 3283-20-21File: 8 Discharge Deed dt 15-10-2020, Doc 3283-20-21.pdf22 Jan 2025
Yadavanahalli ADLR SketchFile: 1 Yadavanahalli ADLR Sketch.pdf22 Jan 2025
Engineers License 160125File: 2 Engineers License 160125.pdf22 Jan 2025
Sobha Hamptons -Townpark Phase 2 W1 to 3 DemarcationFile: 3 Sobha Hamptons -Townpark Phase 2 W1 to 3 Demarcation.pdf22 Jan 2025
Sobha Hamptons -Townpark Phase 2 W1 to 3 Land CostFile: 4 Sobha Hamptons -Townpark Phase 2 W1 to 3 Land Cost.pdf22 Jan 2025
Fire NOC fee paid receipt with declarationFile: 5 Fire NOC fee paid receipt with declaration.pdf22 Jan 2025
Sobha Hamptons -Townpark Phase 2 W1 to 3 AffidavitFile: 6 Sobha Hamptons -Townpark Phase 2 W1 to 3 Affidavit.pdf22 Jan 2025
Syno 56-3-CLU dt 19112019File: 1 Syno 56-3-CLU dt 19112019.pdf22 Jan 2025
SyNo 74-7 148-2 74-6 74-11-CLU dt 19112019File: 2 SyNo 74-7 148-2 74-6 74-11-CLU dt 19112019.pdf22 Jan 2025
SyNo 148-1 74-6 CLU dt 19112019 2File: 3 SyNo 148-1 74-6 CLU dt 19112019 2.pdf22 Jan 2025
Syno 52-2-CLU dt 19112019File: 4 Syno 52-2-CLU dt 19112019.pdf22 Jan 2025
Syno 54-1-CLU dt 19112019File: 5 Syno 54-1-CLU dt 19112019.pdf22 Jan 2025
Syno 54-3-CLU dt 19112019File: 6 Syno 54-3-CLU dt 19112019.pdf22 Jan 2025
Syno 54-4-CLU dt 19112019File: 7 Syno 54-4-CLU dt 19112019.pdf22 Jan 2025
Syno 54-5-CLU dt 19112019File: 8 Syno 54-5-CLU dt 19112019.pdf22 Jan 2025
Syno 56-4 CLU dt 19112019File: 9 Syno 56-4 CLU dt 19112019.pdf22 Jan 2025
KSPCB NOC fee paid receipt with declaration Hamptons P2 W1-3File: 8 KSPCB NOC fee paid receipt with declaration Hamptons P2 W1-3.pdf22 Jan 2025
Hamptons and Madison Commencement LetterFile: Hamptons and Madison Commencement Letter.pdf22 Jan 2025
Clarification on Building LicenseFile: Clarification on Building License.pdf22 Jan 2025
Development Plan Sanction LetterFile: Development Plan Sanction Letter.pdf22 Jan 2025
Development Plan ApprovedFile: Development Plan Approved.pdf22 Jan 2025
SITE PLANFile: 1 SITE PLAN.pdf22 Jan 2025
BASEMENT 2 FLOOR PLAN BUILDING 1File: 2 BASEMENT 2 FLOOR PLAN BUILDING 1.pdf22 Jan 2025
BASEMENT 1 FLOOR PLAN BUILDING 1File: 3 BASEMENT 1 FLOOR PLAN BUILDING 1.pdf22 Jan 2025
GROUND FLOOR PLAN BUILDING 1File: 4 GROUND FLOOR PLAN BUILDING 1.pdf22 Jan 2025
4A GROUND FLOOR PLAN 2 BUILDING 1File: 4A GROUND FLOOR PLAN 2 BUILDING 1.pdf22 Jan 2025
FIRST FLOOR PLAN BUILDING 1File: 5 FIRST FLOOR PLAN BUILDING 1.pdf22 Jan 2025
TYPICAL FLOOR PLAN BUILDING 1File: 6 TYPICAL FLOOR PLAN BUILDING 1.pdf22 Jan 2025
20TH,30TH & 40TH FLOOR PLAN BUILDING 1File: 7 20TH,30TH & 40TH FLOOR PLAN BUILDING 1.pdf22 Jan 2025
TERRACE FLOOR PLAN BUILDING 1File: 8 TERRACE FLOOR PLAN BUILDING 1.pdf22 Jan 2025
ELEVATION BUIDLING 1File: 9 ELEVATION BUIDLING 1.pdf22 Jan 2025
SECTIONAL ELEVATION BUILDING 1File: 10 SECTIONAL ELEVATION BUILDING 1.pdf22 Jan 2025
10A SECTIONAL ELEVATION 2 BUILDING 1File: 10A SECTIONAL ELEVATION 2 BUILDING 1.pdf22 Jan 2025
BASEMENT 2 FLOOR PLAN BUILDING 2File: 11 BASEMENT 2 FLOOR PLAN BUILDING 2.pdf22 Jan 2025
BASEMENT 1 FLOOR PLAN BUILDING 2File: 12 BASEMENT 1 FLOOR PLAN BUILDING 2.pdf22 Jan 2025
GROUND FLOOR PLAN BUILDING 2File: 13 GROUND FLOOR PLAN BUILDING 2.pdf22 Jan 2025
FIRST FLOOR PLAN BUILDING 2File: 14 FIRST FLOOR PLAN BUILDING 2.pdf22 Jan 2025
SECOND FLOOR PLAN BUILDING 2File: 15 SECOND FLOOR PLAN BUILDING 2.pdf22 Jan 2025
THIRD FLOOR PLAN BUILDING 2File: 16 THIRD FLOOR PLAN BUILDING 2.pdf22 Jan 2025
FOURTH FLOOR PLAN BUILDING 2File: 17 FOURTH FLOOR PLAN BUILDING 2.pdf22 Jan 2025
FIFTH FLOOR PLAN BUILDING 2File: 18 FIFTH FLOOR PLAN BUILDING 2.pdf22 Jan 2025
SIXTH FLOOR PLAN BUILDING 2File: 19 SIXTH FLOOR PLAN BUILDING 2.pdf22 Jan 2025
TYPICAL FLOOR PLAN BUILDING 2File: 20 TYPICAL FLOOR PLAN BUILDING 2.pdf22 Jan 2025
20TH,30TH & 40TH FLOOR PLAN BUILDING 2File: 21 20TH,30TH & 40TH FLOOR PLAN BUILDING 2.pdf22 Jan 2025

Promoter's earlier projects40

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

17 not delivered by the promised date40 under way, not due yet8 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
SOBHA Crystal Meadows Phase 5 Wing 16 to 22SURVEY NOS 64/1, 64/2, 64/3, 64/4, 65/2(P), 74, 75/1, 75/2, 75/3, 76/1(P), 76/2, 76/3, 78, 79, 80/1, 80/2, 80/3, 80/4, 82/2, 83/1, 83/2, 83/3, 83/4, 84, 85/1(P), 85/2(P), 85/3(P), 86/1A(P) SITUATED AT MULLUR VILLAGE, BENGALURU EAST, BENGALURU URBAN, KARNATAKA - 571442OngoingDec 2035Not due yet
SOBHA Crystal Meadows Phase 4 Wing 23 to 28SURVEY NOS 64/1, 64/2, 64/3, 64/4, 65/2(P), 74, 75/1, 75/2, 75/3, 76/1(P), 76/2, 76/3, 78, 79, 80/1, 80/2, 80/3, 80/4, 82/2, 83/1, 83/2, 83/3, 83/4, 84, 85/1(P), 85/2(P), 85/3(P), 86/1A(P) SITUATED AT MULLUR VILLAGE, BENGALURU EAST, BENGALURU URBAN, KARNATAKA - 571442OngoingDec 2033Not due yet
SOBHA Crystal Meadows Phase 3 Wing 9 to 15SURVEY NOS 64/1, 64/2, 64/3, 64/4, 65/2(P), 74, 75/1, 75/2, 75/3, 76/1(P), 76/2, 76/3, 78, 79, 80/1, 80/2, 80/3, 80/4, 82/2, 83/1, 83/2, 83/3, 83/4, 84, 85/1(P), 85/2(P), 85/3(P), 86/1A(P) SITUATED AT MULLUR VILLAGE, BENGALURU EAST, BENGALURU URBAN, KARNATAKA - 571442OngoingDec 2032Not due yet
Sobha Neopolis Phase 5 - W 5, 6 & 7"Sobha Neopolis, Survey no 46/4, 46/7 (old no. 46/6), 46/8 (old no. 46/5), 47/3, (old no. 47/1), 47/5 ( old no. 47/1,) 47/6, 47/7, 49/1, 49/3, 49/6 & 50 , Panathur Village Varthur Hobli, Bengaluru, 560103"OngoingDec 2031Not due yet
Sobha Neopolis Phase 4 - 3, 4, 8 & 9"Sobha Neopolis, Survey no 46/4, 46/7 (old no. 46/6), 46/8 (old no. 46/5), 47/3, (old no. 47/1), 47/5 ( old no. 47/1,) 47/6, 47/7, 49/1, 49/3, 49/6 & 50 , Panathur Village Varthur Hobli, Bengaluru, 560103"OngoingDec 2031Not due yet
SOBHA Ayana at Dream Acres Wing 60 to 71Sy No 50/2, 50/4, 50/5, 50/6, 51/1,51/2B1, 51/2B2, 51/3,51/4, 51/2C1,51/2C2, 53/1 and 53/2 of BalagereVillage , Ward No 149 , Varthur Hobli ,Bengaluru East , Bengaluru Urban,Karnataka - 560087OngoingDec 2031Not due yet
SOBHA Crystal Meadows Phase 2 Wing 7 and 8SURVEY NOS 64/1, 64/2, 64/3, 64/4, 65/2(P), 74, 75/1, 75/2, 75/3, 76/1(P), 76/2, 76/3, 78, 79, 80/1, 80/2, 80/3, 80/4, 82/2, 83/1, 83/2, 83/3, 83/4, 84, 85/1(P), 85/2(P), 85/3(P), 86/1A(P) SITUATED AT MULLUR VILLAGE, BENGALURU EAST, BENGALURU URBAN, KARNATAKA - 571442OngoingJun 2031Not due yet
Sobha Neopolis Phase 2 - W 12 & 13"Sobha Neopolis, Survey no 46/4, 46/7 (old no. 46/6), 46/8 (old no. 46/5), 47/3, (old no. 47/1), 47/5 ( old no. 47/1,) 47/6, 47/7, 49/1, 49/3, 49/6 & 50 , Panathur Village Varthur Hobli, Bengaluru, 560103"OngoingDec 2030Not due yet
Sobha Infinia Phase 2B Block 4 W1 and Block 3 W2Survey nos 10,55, 7/2, 8/2, 9/10, 9/11,9/12, 9/13, 9/14, 9/15, 9/16 , NEARAYAPPASWAMY TEMPLE, AGARAVILLAGE , BENGALURU , Bengaluru East, Bengaluru Urban, Karnataka - 560034OngoingDec 2030Not due yet
Sobha Infinia Phase 2A Block 5 Wing 5Survey nos 10,55, 7/2, 8/2, 9/10, 9/11,9/12, 9/13, 9/14, 9/15, 9/16 , NEARAYAPPASWAMY TEMPLE, AGARAVILLAGE , BENGALURU , Bengaluru East, Bengaluru Urban, Karnataka - 560034OngoingJun 2030Not due yet
Sobha Neopolis Phase 3 - W 1, 2, 10 & 11"Sobha Neopolis, Survey no 46/4, 46/7 (old no. 46/6), 46/8 (old no. 46/5), 47/3, (old no. 47/1), 47/5 ( old no. 47/1,) 47/6, 47/7, 49/1, 49/3, 49/6 & 50 , Panathur Village Varthur Hobli, Bengaluru, 560103"OngoingDec 2029Not due yet
SOBHA Crystal Meadows Phase 1 Wing 1 to 6SURVEY NOS 64/1, 64/2, 64/3, 64/4, 65/2(P), 74, 75/1, 75/2, 75/3, 76/1(P), 76/2, 76/3, 78, 79, 80/1, 80/2, 80/3, 80/4, 82/2, 83/1, 83/2, 83/3, 83/4, 84, 85/1(P), 85/2(P), 85/3(P), 86/1A(P) SITUATED AT MULLUR VILLAGE, BENGALURU EAST, BENGALURU URBAN, KARNATAKA - 571442OngoingDec 2029Not due yet
Sobha Brooklyn Towers - Town Park Phase 4, W4Sy nos - 51/1(P), 51/2(P), 52/1(P), 52/2(P)&53 at Yadavanahalli village, Attibele hobli, Anekal taluk, Bangalore, KarnatakaOngoingJun 2029Not due yet
Sobha Brooklyn Towers - Town Park Phase 3, W5Sy nos - 51/1(P), 51/2(P), 52/1(P), 52/2(P)&53 at Yadavanahalli village, Attibele hobli, Anekal taluk, Bangalore, KarnatakaOngoingJun 2029Not due yet
Sobha Royal crest"PROPOSED RESIENTIAL APARMENT @ BBMP Katha no. 989/38/2, 38/4, 80/3, 37/1, 38/3, 80/2, 38/1, 35/3, 35/4, 37/2 , 38/5, 79, 80/1 @ HOSAKARAHALLI VILLAGE, UTTARAHALLI HOBLI, NEAR P.E.S COLLEGE,BANGALORE SOUTH TALUK., WARD NO 160, RAJARAJESHWARINAGAR ZONE"OngoingDec 2028Not due yet
Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18&19"Sobha Neopolis, Survey no 46/4, 46/7 (old no. 46/6), 46/8 (old no. 46/5), 47/3, (old no. 47/1), 47/5 ( old no. 47/1,) 47/6, 47/7, 49/1, 49/3, 49/6 & 50 , Panathur Village Varthur Hobli, Bengaluru, 560103"OngoingDec 2028Not due yet
Sobha Neopolis Phase 1 - W 14, 15, 16, 17, 18&19"Sobha Neopolis, Survey no 46/4, 46/7 (old no. 46/6), 46/8 (old no. 46/5), 47/3, (old no. 47/1), 47/5 ( old no. 47/1,) 47/6, 47/7, 49/1, 49/3, 49/6 & 50 , Panathur Village Varthur Hobli, Bengaluru, 560103"OngoingDec 2028Not due yet
Sobha Dream Gardens Phase 5 - Wing 10Survey No. 50, 51 & 54, Belahalli Village, Yelahanka HobliOngoingDec 2028Not due yet
Sobha Dream Gardens Phase 4 - Wing 1 and 2Survey No. 50, 51 & 54, Belahalli Village, Yelahanka HobliOngoingDec 2028Not due yet
Sobha Manhattan Towers-Town Park Phase 2 W 1 & 2Phase 1 at Sy.No.48/1A and 48/2, in the composite project Sobha Manhattan Towers - Town Park situated at Sy.Nos.48/1A, 48/2, 50/2 and 50/3, presently bearing Khata No.1877/48/1A-1881/50/2-1886/48/2-1913/50/3, situated at Yadavanahalli Village, Attibele Hobli, Anekal TalukOngoingSep 2028Not due yet
Sobha Brooklyn Towers - Town Park Phase 5, W3Sy nos - 51/1(P), 51/2(P), 52/1(P), 52/2(P)&53 at Yadavanahalli village, Attibele hobli, Anekal taluk, Bangalore, KarnatakaOngoingJun 2028Not due yet
Sobha Brooklyn Towers - Town Park Phase 5, W3Sy nos - 51/1(P), 51/2(P), 52/1(P), 52/2(P)&53 at Yadavanahalli village, Attibele hobli, Anekal taluk, Bangalore, KarnatakaOngoingJun 2028Not due yet
Sobha Windsor Phase 4 Wing 9, 10 and 11Sy No. 107(P), 115/2, 115/3, 115/4, 115/5, 116/3 situated at Nagondanahalli village and Sy No. 30/1, 30/6, Situated at Hagadur Village, K.R.Puram HobliOngoingMar 2028Not due yet
Sobha Victoria park phase 2"PROPOSED RESIDENTIAL DEVELOPMENT PROJECT AT SY.NO.47/1B,47/2B, KYALASANAHALLI VILLAGE , WARD NO.25, MAHADEVAPURA ZONE, K.R. PURAM HOBLI, BANGALORE "OngoingDec 2027Not due yet
Sobha Victoria park phase 1"PROPOSED RESIDENTIAL DEVELOPMENT PROJECT AT SY.NO.47/1B,47/2B, KYALASANAHALLI VILLAGE , WARD NO.25, MAHADEVAPURA ZONE, K.R. PURAM HOBLI, BANGALORE "OngoingDec 2027Not due yet
Sobha Sentosa Phase 4 Wing 1 and 2"PROPOSED RESIDENTIAL DEVELOPMENT PLAN AT SY NOS. 49/4 , 49/7, 50/2 (P) , 50/3 (P) , 50/4 (P) , 51/1 (P) , 51/2 B1(P) & 51/2B2 (P) AT BALAGERE, VARTHUR HOBLI, BANGALORE EAST, KARNATAKA "OngoingDec 2027Not due yet
Sobha Sentosa Phase 4 Wing 1 and 2"PROPOSED RESIDENTIAL DEVELOPMENT PLAN AT SY NOS. 49/4 , 49/7, 50/2 (P) , 50/3 (P) , 50/4 (P) , 51/1 (P) , 51/2 B1(P) & 51/2B2 (P) AT BALAGERE, VARTHUR HOBLI, BANGALORE EAST, KARNATAKA "OngoingDec 2027Not due yet
Sobha Oakshire Phase 3 Wing 5,6,11 and 12Proposed residential building plan, Katha no. 80/73/3/74/2/75 (PID NO 150300200400520002), Sy nos 73/3, 74/2, 75 of Thimmegowdana Hosahalli village, Kasaba hobli,Devanahalli Taluk,Bangalore rural,562110OngoingDec 2027Not due yet
Sobha Dream Gardens Phase 3 - Wing 3 and 4Survey No. 50, 51 & 54, Belahalli Village, Yelahanka HobliOngoingDec 2027Not due yet
Sobha Brooklyn Towers - Town Park Phase 2, W2Sy nos - 51/1(P), 51/2(P), 52/1(P), 52/2(P)&53 at Yadavanahalli village, Attibele hobli, Anekal taluk, Bangalore, KarnatakaOngoingDec 2027Not due yet
Sobha Brooklyn Towers - Town Park Phase 1, W1Sy nos - 51/1(P), 51/2(P), 52/1(P), 52/2(P)&53 at Yadavanahalli village, Attibele hobli, Anekal taluk, Bangalore, KarnatakaOngoingDec 2027Not due yet
Sobha Windsor Phase 3 Wing 6, 7 and 8Sy No. 107(P), 115/2, 115/3, 115/4, 115/5, 116/3 situated at Nagondanahalli village and Sy No. 30/1, 30/6, Situated at Hagadur Village, K.R.Puram HobliOngoingSep 2027Not due yet
Sobha City AthenaProperty No 2091/40/7/1, 9/1, 9/2, 62/2, 62/3/1, Chokkanahalli Village, Ward No. 5, Jakkuru, Yelahanka Zone, BengaluruOngoingSep 2027Not due yet
Sobha Sentosa Phase 3 Wing 3 and 4"PROPOSED RESIDENTIAL DEVELOPMENT PLAN AT SY NOS. 49/4 , 49/7, 50/2 (P) , 50/3 (P) , 50/4 (P) , 51/1 (P) , 51/2 B1(P) & 51/2B2 (P) AT BALAGERE, VARTHUR HOBLI, BANGALORE EAST, KARNATAKA "OngoingJun 2027Not due yet
Sobha Oakshire Phase 2 Wing 3,4,9 and 10Proposed residential building plan, Katha no. 80/73/3/74/2/75 (PID NO 150300200400520002), Sy nos 73/3, 74/2, 75 of Thimmegowdana Hosahalli village, Kasaba hobli,Devanahalli Taluk,Bangalore rural,562110OngoingJun 2027Not due yet
Sobha Sentosa Phase 2 Wing 5 and 6"PROPOSED RESIDENTIAL DEVELOPMENT PLAN AT SY NOS. 49/4 , 49/7, 50/2 (P) , 50/3 (P) , 50/4 (P) , 51/1 (P) , 51/2 B1(P) & 51/2B2 (P) AT BALAGERE, VARTHUR HOBLI, BANGALORE EAST, KARNATAKA "OngoingDec 2026Not due yet
Sobha Oakshire Phase 1 Wing 1,2,7 and 8Proposed residential building plan, Katha no. 80/73/3/74/2/75 (PID NO 150300200400520002), Sy nos 73/3, 74/2, 75 of Thimmegowdana Hosahalli village, Kasaba hobli,Devanahalli Taluk,Bangalore rural,562110OngoingDec 2026Not due yet
Sobha Manhattan Towers-Town Park Phase 1 W 4 & 5Phase 1 at Sy.No.48/1A and 48/2, in the composite project Sobha Manhattan Towers - Town Park situated at Sy.Nos.48/1A, 48/2, 50/2 and 50/3, presently bearing Khata No.1877/48/1A-1881/50/2-1886/48/2-1913/50/3, situated at Yadavanahalli Village, Attibele Hobli, Anekal TalukOngoingDec 2026Not due yet
Sobha Galera"SOBHA GALERA, SURVEY NO 45/4 OF HUSKUR VILLAGE, BIDARAHALLI HOBLI, BANGLAORE EAST TALUK SURVEY NO.116 OF AMANIDODDAKERE VILLAGE, KASABA HOBLI, HOSAKOTE TALUK, BANGALORE , BENGALURU EAST, BENGALURU URBAN, KARNATAKA - 560049"OngoingDec 2026Not due yet
Sobha Galera"SOBHA GALERA, SURVEY NO 45/4 OF HUSKUR VILLAGE, BIDARAHALLI HOBLI, BANGLAORE EAST TALUK SURVEY NO.116 OF AMANIDODDAKERE VILLAGE, KASABA HOBLI, HOSAKOTE TALUK, BANGALORE , BENGALURU EAST, BENGALURU URBAN, KARNATAKA - 560049"OngoingDec 2026Not due yet

How this compares with Bengaluru Urban

51%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Sobha Hamptons -Townpark Phase 2 W1 to 3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSobha Hamptons -TownparkOther 19Dot size: filed unitsN

Filed coordinates, straight-line distance. 19 registered projects within 2 km.

Builder: SOBHA LIMITED

SOBHA LIMITED has 120 registrations on RERA Karnataka, including Sobha Oakshire Phase 1 Wing 1,2,7 and 8 and Sobha Oakshire Phase 2 Wing 3,4,9 and 10. Its filings declare 196 earlier projects, 85 of them declared completed. Litigation is declared on 33 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Sobha Hamptons -Townpark Phase 2 W1 to 3 is delayed beyond 30 Jun 2033?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Sobha Hamptons -Townpark Phase 2 W1 to 3?

The registered promoter entity is SOBHA LIMITED, a company as per the filing. Its CIN L45201KA1995PLC018475 and GSTIN 29AABCS7723E1ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Sobha Hamptons -Townpark Phase 2 W1 to 3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Sobha Hamptons -Townpark Phase 2 W1 to 3?

The professionals named in the filing: Architect: Arun Kumar; Engineer: OUSEPPACHAN.C.AMBOOKEN; Engineer: Balakrishnan G; Chartered Accountant: Balaji D. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sobha Hamptons -Townpark Phase 2 W1 to 3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sobha Hamptons -Townpark Phase 2 W1 to 3. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sobha Hamptons -Townpark Phase 2 W1 to 3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.