Home / Browse projects / Bengaluru Urban, Karnataka / SHRIRAM 107SOUTHEAST - PHASE 3

Registration approved No litigation declared Residential/Group Housing project

SHRIRAM 107SOUTHEAST - PHASE 3

By Shriprop Living Space Private Limited

RG-KA-82712 · RERA PRM/KA/RERA/1251/308/PR/140222/004708 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 3 complaints at RERA Karnataka

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
Jan 2027Possession promisedno revision filed
6 of 17Construction stages donefurthest along: Plastering inside, 80%
0 of 1,055Units unsoldnot recorded sold or booked
3Complaints at RERA Karnatakaon this registration
Jump to the 162 documents Report an error

SHRIRAM 107SOUTHEAST - PHASE 3 is a Residential/Group Housing project by Shriprop Living Space Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/140222/004708 on 14 Feb 2022. Possession is promised by 7 Jan 2027. 1,055 of the 1,055 units on this registration are recorded sold or booked, and 6 of 17 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameSHRIRAM 107SOUTHEAST - PHASE 3
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
    • 562107
  • Pincode562107
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/140222/004708
  • ReraGenie IDRG-KA-82712

Builder

  • NameShriprop Living Space Private Limited
  • Entity typeCompany
  • CINU70109KA2014PTC076190
  • GSTIN29AAUCS9989D1Z6
  • Authorized SignatoryKrishna veeraraghavan
  • Director & Chief Operating Officer (Bangalore)Krishna veeraraghavan
  • DirectorRajesh Yashwant Shirwatkar
  • Project HeadS Senthil Kumar
  • Other registrations2 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredFeb 2022PromisedJan 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on14 Feb 2022
  • Promised completion7 Jan 2027
  • Revised completionNone
  • Buildings9 building records
  • Documents filed162 files

Current status

100%1055 of 1,055 units booked
7.0%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1A---1170117
1---1170117
2---1170117
3---1170117
4---1170117
5---1170117
6---1170117
13---1180118
14---1180118

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 17 construction stages are filed complete. The stage furthest along is Plastering inside, at 80%.

Building: 68% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction70%
Plastering inside , outside & Ceiling80%
Joinery: Doors, Windows, Ventilators etc30%
Basic work of Water supply, Sanitary and Electrification50%
Dadoing, Skirting, Flooring, Tiles work (All types)50%
Railing and Grill fixing30%
Electrification, Water supply and Sanitary Finishing80%
Painting40%
Fire prevention and fire fighting fitting and fixture with network40%
Weather Proof work(tile,concrete)40%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawings40%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes50%
Sewage and Drainage SystemYes80%
Water conservation/rain water harvesting/recharge of ground waterYes35%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes30%
Solid waste management and disposalYes30%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes30%
Electricity supply transformer and substationYes30%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes30%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes60%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes100%
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationYes40%
Air ConditioningNoNot applicable
StaircasesYes40%
LiftsNoNot applicable
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area23,181 sq m
Named landowners2
LandownerVillageDistrict
ICONICA PROJECTS--
ICONICA PROJECTS--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 313.68 cr
Cost incurredRs 22.04 cr
Spent of the estimate7.03%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 199.46 crRs 16.48 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 67.73 crRs 2.41 cr
Payment of taxesRs 24.40 crRs 2.99 cr
On-site expenditure-Consultants FeesRs 18.00 crRs 15.50 lakh
On-site expenditure-Site OverheadRs 2.16 cr-
Payment of cessRs 1.93 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBiswarup Sarangi
EngineerArun Nadig
Chartered AccountantVivek Gupta

Complaints filed with RERA Karnataka3

Case no.ComplainantRespondentFiled
CMP/220401/0009305-Shriprop Living Space Private Limited01/04/2022
00497/2023-Shriprop Living Space Private Limited17/04/2023
01439/2023-Shriprop Living Space Private Limited16/09/2023

Documents filed162

As listed on the registration, under the names the promoter filed them with; the newest 80 of 162 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/140222/004708 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4_107 Southeast Q2 Sep-2026.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) 107SE - P3 Q2 2026-27.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer (QU) 107SE P3 Q2 2026-27.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4_107 Southeast June-2026.pdf13 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) 107SE - P3 Q1 2026-27.pdf13 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer (QU) 107SE P3 Q4 2026-27.pdf13 Jul 2026
Q1 2026-27 Water supply and sewage board13 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)13 Jul 2026
Q1 2026-27 KPTCL- BESCOM13 Jul 2026
Q1 2026-27 Fire and Safety13 Jul 2026
Q1 2026-27 Airport Authority of India13 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department13 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4_107 Southeast March-2026.pdf13 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) 107SE - P3 Q4 2025-26.pdf13 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer (QU) 107SE P3 Q4 2024-25.pdf13 Apr 2026
Q4 2025-26 Water supply and sewage board13 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)13 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)13 Apr 2026
Q4 2025-26 KPTCL- BESCOM13 Apr 2026
Q4 2025-26 Fire and Safety13 Apr 2026
Q4 2025-26 Airport Authority of India13 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department13 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4_107 Southeast Dec-2025.pdf6 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) 107SE - P3 Q3 2025-26.pdf6 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer (QU) 107SE P3 Q3 2024-25.pdf6 Feb 2026
Q3 2025-26 Water supply and sewage board6 Feb 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)6 Feb 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)6 Feb 2026
Q3 2025-26 KPTCL- BESCOM6 Feb 2026
Q3 2025-26 Fire and Safety6 Feb 2026
Q3 2025-26 Airport Authority of India6 Feb 2026
Q3 2025-26 BSNL/Telecommunication Department6 Feb 2026
Updated Agreement of Sell - AOSFile: Updated Agreement of Sell - AOS.pdf8 Feb 2022
Clarifications for ExtentFile: ANEKAL- SITE PLAN-PHASE-3.pdf25 Jan 2022
sale deed for sy no. 5/1 ext 2-07File: 5-1 sale deed -2 A - 7 Guntas.pdf25 Jan 2022
EC - 5-1File: 5-1 -1-4-2004 to 22-4-16.pdf25 Jan 2022
EC- 5-1File: 5-1- 16-9-2016 - 26-3-2019.pdf25 Jan 2022
EC - 5-2File: 5-2-16-9-2016 to 26-3-2019.pdf25 Jan 2022
EC- 7-2File: 7-2- 1-4-2004 to 16-9-2016-.pdf25 Jan 2022
EC- 7-2File: 7-2-16-9-2016 to 26-3-2019.pdf25 Jan 2022
EC - 7-3File: 7-3 from 1-4-2004 to 17-11-2021.pdf25 Jan 2022
EC - 10-2File: 10-2 (1 acre) - 1-4-2004 to 16-09-16.pdf25 Jan 2022
EC - 10-2File: 10-2 (2A 5G) - 1-4-2004 to 22-4-2016.pdf25 Jan 2022
EC - 10-2File: 10-2-16-9-2016 to 26-3-2019.pdf25 Jan 2022
EC - 44-2File: 44-2 - 1-4- 2004 to 3-10-2016.pdf25 Jan 2022
EC - 44-2File: 44-2-16-9-2016 to 26-3-2019.pdf25 Jan 2022
EC - 44-5File: 44-5 -1-4-2004 to 20-10-2016-.pdf25 Jan 2022
EC - 44-5File: 44-5-16-9-2016 to 26-3-2019.pdf25 Jan 2022
EC - 45-2CFile: 45-2C- 16-9-2016 to 26-3-2019.pdf25 Jan 2022
EC - 45-2CFile: 45-2C-1-4-2004 to 24-8-2016.pdf25 Jan 2022
EC - 46File: 46- 1-4-2004 to 20-2-2017-.pdf25 Jan 2022
EC - 46File: 46-16-9-2016 to 26-3-2019.pdf25 Jan 2022
EC - 47File: 47-1-4-2004 to 16-9-2016-.pdf25 Jan 2022
EC - 47File: 47-16-9-2016 to 26-3-2019.pdf25 Jan 2022
EC for all survey numbersFile: Ec for all Sy No from 1-1-2020 to 5-2-2020.pdf25 Jan 2022
EC for all survey numbersFile: Ec for all Sy No from 1-2-2020 to 16-6-2020.pdf25 Jan 2022
EC for all survey numbersFile: Ec for all Sy No from 1-7-2021 to 30-09-2021.pdf25 Jan 2022
EC for all survey numbersFile: Ec for all Sy No from 1-10-2021 to 20-1-2022.pdf25 Jan 2022
EC for all survey numbersFile: Ec for all Sy No from 1-11-2019 to 30-11-2019.pdf25 Jan 2022
EC for all survey numbersFile: Ec for all Sy No from 1-12-19 to 31-12-2019.pdf25 Jan 2022
EC for all survey numbersFile: Ec for all Sy No from 3-1-2021 to 30-06-2021.pdf25 Jan 2022
EC for all survey numbersFile: Ec for all Sy No from 3-11-2020 to 3-1-2021.pdf25 Jan 2022
EC for all survey numbersFile: Ec for all Sy No from 17-6-2020 to 17-08-2020.pdf25 Jan 2022
EC for all survey numbersFile: Ec for all Sy No from 25-6-2019 to 5-7-2019.pdf25 Jan 2022
EC for all survey numbersFile: EC for all Sy No from 26-3-2019 to 02-05-2019.pdf25 Jan 2022
notarized form-BFile: Form B.pdf25 Jan 2022
NOC for fireFile: Fire NOC-compressed.pdf25 Jan 2022
NOC for KSPCBFile: KSPCB.pdf25 Jan 2022
updated plinth areaFile: Plinth and Common area.pdf25 Jan 2022
Updated common areasFile: Plinth and Common area.pdf25 Jan 2022
Architect certificateFile: Architect Certificate.pdf25 Jan 2022
Engineer certificateFile: Engineer Certificate - 107SE-PH-3.pdf25 Jan 2022

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
SHRIRAM 107SOUTHEAST - PHASE 2Sy.No. 5/1, 5/2, 7/2,10/2, 44/2, 44/5, 45/2C, 46 and 47 of Manchenahalli Village,Attibele hobli, Anekal Taluk, BangaloreOngoingMar 2025Not delivered
SHRIRAM 107SOUTHEASTSy.No. 5/1, 5/2, 7/2,10/2, 44/2, 44/5, 45/2C, 46 and 47 of Manchenahalli Village,Attibele hobli, Anekal Taluk, BangaloreOngoingJul 2024Not delivered

How this compares with Bengaluru Urban

100%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SHRIRAM 107SOUTHEAST - PHASE 3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSHRIRAM 107SOUTHEAST - POther 9Dot size: filed unitsN

Filed coordinates, straight-line distance. 9 registered projects within 2 km.

Builder: Shriprop Living Space Private Limited

Shriprop Living Space Private Limited has 3 registrations on RERA Karnataka, including SHRIRAM 107SOUTHEAST - PHASE 3 and SHRIRAM 107 SOUTHEAST. Its filings declare 2 earlier projects, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SHRIRAM 107SOUTHEAST - PHASE 3 is delayed beyond 7 Jan 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SHRIRAM 107SOUTHEAST - PHASE 3?

The registered promoter entity is Shriprop Living Space Private Limited, a company as per the filing. Its CIN U70109KA2014PTC076190 and GSTIN 29AAUCS9989D1Z6 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SHRIRAM 107SOUTHEAST - PHASE 3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SHRIRAM 107SOUTHEAST - PHASE 3?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at SHRIRAM 107SOUTHEAST - PHASE 3?

The professionals named in the filing: Architect: Biswarup Sarangi; Engineer: Arun Nadig; Chartered Accountant: Vivek Gupta. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHRIRAM 107SOUTHEAST - PHASE 3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHRIRAM 107SOUTHEAST - PHASE 3. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHRIRAM 107SOUTHEAST - PHASE 3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.