ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / Sobha Galera

Registration approved No litigation declared Residential/Group Housing project

Sobha Galera

By SOBHA LIMITED

RG-KA-50350 · RERA PRM/KA/RERA/1251/446/PR/050123/005601 · Last updated on RERA Karnataka portal: 13 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
Dec 2026Possession promisedno revision filed
18 of 18Construction stages doneevery applicable stage filed complete
0 of 40Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 120 documents Report an error

Sobha Galera is a Residential/Group Housing project by SOBHA LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/050123/005601 on 5 Jan 2023. Possession is promised by 31 Dec 2026. 40 of the 40 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSobha Galera
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560049
  • Pincode560049
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/050123/005601
  • ReraGenie IDRG-KA-50350

Builder

  • NameSOBHA LIMITED
  • Entity typeCompany
  • CINL45201KA1995PLC018475
  • GSTIN29AABCS7723E1ZB
  • Authorized SignatoryMr. Suresh Ganiga
  • Managing DirectorMr Jagadish Nangineni
  • DirectorsRavi P N C Menon, Mr Jagadish Nangineni
  • Project HeadMr. Nandeesh raju
  • Other registrations119 more →
  • No longer live8 withdrawn or revoked
  • Declared earlier projects196 →

Key dates

this monthRegisteredJan 2023PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on5 Jan 2023
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed120 files

Current status

100%40 of 40 units booked
130.0%Of the estimated cost spent so far

Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing 1---19019
Wing 2---21021

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 18 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes100%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes100%
Electricity supply transformer and substationYes100%
Storm water drainsYes100%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingYes100%
Street LightingYes100%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes47%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsNoNot applicable
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areasYes100%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area16,525 sq m
Named landowners2
LandownerVillageDistrict
M/s. Sobha Limited--
M/s. Sobha Limited--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 83.62 cr
Cost incurredRs 108.67 cr
Spent of the estimate129.96%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 59.13 crRs 85.28 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 11.50 crRs 11.50 cr
Payment of taxesRs 8.85 crRs 7.55 cr
On-site expenditure-Site OverheadRs 4.14 crRs 4.34 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGeetha K Nair
EngineerMr. Durga Prasad KVR
Chartered AccountantBalaji D

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
00882/2024-SOBHA LIMITED12/09/2024

Documents filed120

As listed on the registration, under the names the promoter filed them with; the newest 80 of 120 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/050123/005601 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Galera C.pdf13 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Galera.pdf13 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Galera.pdf13 Oct 2026
Q2 2026-27 Water supply and sewage board13 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Oct 2026
Q2 2026-27 KPTCL- BESCOM13 Oct 2026
Q2 2026-27 Registration documentFile: Galera DOD Compressed.pdf13 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Galera.pdf13 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Galera.pdf13 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Galera.pdf13 Jul 2026
Q1 2026-27 Water supply and sewage board13 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Jul 2026
Q1 2026-27 KPTCL- BESCOM13 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Galera.pdf10 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Galera.pdf10 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Galera.pdf10 Apr 2026
Q4 2025-26 Water supply and sewage board10 Apr 2026
Q4 2025-26 KPTCL- BESCOM10 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Galera C.pdf12 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Galera.pdf12 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Galera.pdf12 Jan 2026
Q3 2025-26 Water supply and sewage board12 Jan 2026
Q3 2025-26 KPTCL- BESCOM12 Jan 2026
Bank account passbook attachedFile: 777705230998 RERA acct.pdf28 Dec 2022
BESCOM NOC and payment receiptFile: BESCOM NOC and payment receipt.pdf28 Dec 2022
Bank account detailsFile: 1 Bank account details.pdf3 Dec 2022
Upload previous project annual audit form-07File: 2 Annual audit form 07.pdf3 Dec 2022
need khata for syno 116File: 3 Survey no 116 note.pdf3 Dec 2022
need layout plan showing syno 116File: 4 CLUBHOUSE SITE SUPERIMPOSED ON SURVEY SKETCH.pdf3 Dec 2022
need title deed to conversion land owner for all synoFile: Title deed to conversion land owner for all syno.pdf3 Dec 2022
Common Area Allotted To AssociationFile: 7 Common area.pdf3 Dec 2022
BESCOM NOCFile: BESCOM NOC NA.pdf3 Dec 2022
upload the brief estimated cost of constructionFile: Form 3 Engineer certificate.pdf3 Dec 2022
Revised Proforma of Agreement for SaleFile: Proforma of ATS Sobha Galera final.pdf3 Dec 2022
Revised brochureFile: 12 Galera RERA brochure final.pdf3 Dec 2022
Galera Amanidoddakere site merged VillagemapFile: Galera Amanidoddakere site merged Villagemap.jpg3 Dec 2022
Galera CLUBHOUSE site merged CDP MapFile: GALERA phase wise siteplan 291122.pdf3 Dec 2022
GALERA phase wise site planFile: Galera phasewise siteplan for club house 291122.pdf3 Dec 2022
RTC, survey 45/4-
Mutation, survey 45/4-
Encumbrance Certificate, survey 45/4-
Conversion/Alienation Order, survey 45/4-
Sale/Title/Gift Deed, survey 45/4-
Khatha, survey 45/4-
RTC, survey 116-
Mutation, survey 116-
Encumbrance Certificate, survey 116-
Conversion/Alienation Order, survey 116-
Sale/Title/Gift Deed, survey 116-
Khatha, survey 116-
Registration CertificateFile: Registration Certificate of SL.pdf-
Organization StructureFile: Organisation Structure.pdf-
Certificate issued by CA Form 1File: Form 1 CA c.pdf-
Certificate issued by Architect Form 2File: Form 2 Arc Cert.pdf-
Certificate issued by Engineer Form 3File: Form 3 EC.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit cum Declaration.pdf-
Certificate from Chartered AccountFile: Form 1 CA c.pdf-
Balance Sheet 2021 - 2022File: Balance sheet Mar 2022.pdf-
Balance Sheet 2020 - 2021File: Balance sheet Mar 2021.pdf-
Balance Sheet 2019 - 2020File: Balance Sheet Mar 2020.pdf-
Audited Profit and Loss Statement 2021 - 2022File: Profit Loss Statement Mar 2022.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Profit Loss Statement Mar 2021.pdf-
Audited Profit and Loss Statement 2019 - 2020File: Profit Loss Statement Mar 2020.pdf-
Director's Report 2021 - 2022File: DR 2021 22.pdf-
Director's Report 2020 - 2021File: DR 2020 21.pdf-
Director's Report 2019 - 2020File: DR 2019 20.pdf-
Cash Flow Statement 2021 - 2022File: Cash Flow Mar 2022.pdf-
Cash Flow Statement 2020 - 2021File: Cash Flow Mar 2021.pdf-
Auditor's Report 2021 - 2022File: Auditors Report Mar 2022.pdf-
Auditor's Report 2020 - 2021File: Auditors Report Mar 2021.pdf-
Auditor's Report 2019 - 2020File: Auditors Report Mar 2020.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITR AY 2021 22.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR AY 2020 21.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: ITR AY 2019 20.pdf-
Commencement certificate-
Application for issuance of bescom-
Water Noc Mandur Gram Panchayat Huskur-

Promoter's earlier projects40

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

31 not delivered by the promised date16 under way, not due yet39 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Sobha Brooklyn Towers - Town Park Phase 4, W4 LitigationSy nos - 51/1(P), 51/2(P), 52/1(P), 52/2(P)&53 at Yadavanahalli village, Attibele hobli, Anekal taluk, Bangalore, KarnatakaOngoingJun 2029Not due yet
Sobha Brooklyn Towers - Town Park Phase 3, W5 LitigationSy nos - 51/1(P), 51/2(P), 52/1(P), 52/2(P)&53 at Yadavanahalli village, Attibele hobli, Anekal taluk, Bangalore, KarnatakaOngoingJun 2029Not due yet
Sobha Royal crest Litigation"PROPOSED RESIENTIAL APARMENT @ BBMP Katha no. 989/38/2, 38/4, 80/3, 37/1, 38/3, 80/2, 38/1, 35/3, 35/4, 37/2 , 38/5, 79, 80/1 @ HOSAKARAHALLI VILLAGE, UTTARAHALLI HOBLI, NEAR P.E.S COLLEGE,BANGALORE SOUTH TALUK., WARD NO 160, RAJARAJESHWARINAGAR ZONE"OngoingDec 2028Not due yet
Sobha Manhattan Towers-Town Park Phase 2 W 1 & 2 LitigationPhase 1 at Sy.No.48/1A and 48/2, in the composite project Sobha Manhattan Towers - Town Park situated at Sy.Nos.48/1A, 48/2, 50/2 and 50/3, presently bearing Khata No.1877/48/1A-1881/50/2-1886/48/2-1913/50/3, situated at Yadavanahalli Village, Attibele Hobli, Anekal TalukOngoingSep 2028Not due yet
Sobha Brooklyn Towers - Town Park Phase 5, W3 LitigationSy nos - 51/1(P), 51/2(P), 52/1(P), 52/2(P)&53 at Yadavanahalli village, Attibele hobli, Anekal taluk, Bangalore, KarnatakaOngoingJun 2028Not due yet
Sobha Windsor Phase 4 Wing 9, 10 and 11 LitigationSy No. 107(P), 115/2, 115/3, 115/4, 115/5, 116/3 situated at Nagondanahalli village and Sy No. 30/1, 30/6, Situated at Hagadur Village, K.R.Puram HobliOngoingMar 2028Not due yet
Sobha Victoria park phase 2 Litigation"PROPOSED RESIDENTIAL DEVELOPMENT PROJECT AT SY.NO.47/1B,47/2B, KYALASANAHALLI VILLAGE , WARD NO.25, MAHADEVAPURA ZONE, K.R. PURAM HOBLI, BANGALORE "OngoingDec 2027Not due yet
Sobha Victoria park phase 1 Litigation"PROPOSED RESIDENTIAL DEVELOPMENT PROJECT AT SY.NO.47/1B,47/2B, KYALASANAHALLI VILLAGE , WARD NO.25, MAHADEVAPURA ZONE, K.R. PURAM HOBLI, BANGALORE "OngoingDec 2027Not due yet
Sobha Sentosa Phase 4 Wing 1 and 2 Litigation"PROPOSED RESIDENTIAL DEVELOPMENT PLAN AT SY NOS. 49/4 , 49/7, 50/2 (P) , 50/3 (P) , 50/4 (P) , 51/1 (P) , 51/2 B1(P) & 51/2B2 (P) AT BALAGERE, VARTHUR HOBLI, BANGALORE EAST, KARNATAKA "OngoingDec 2027Not due yet
Sobha Brooklyn Towers - Town Park Phase 2, W2 LitigationSy nos - 51/1(P), 51/2(P), 52/1(P), 52/2(P)&53 at Yadavanahalli village, Attibele hobli, Anekal taluk, Bangalore, KarnatakaOngoingDec 2027Not due yet
Sobha Brooklyn Towers - Town Park Phase 1, W1 LitigationSy nos - 51/1(P), 51/2(P), 52/1(P), 52/2(P)&53 at Yadavanahalli village, Attibele hobli, Anekal taluk, Bangalore, KarnatakaOngoingDec 2027Not due yet
Sobha Windsor Phase 3 Wing 6, 7 and 8 LitigationSy No. 107(P), 115/2, 115/3, 115/4, 115/5, 116/3 situated at Nagondanahalli village and Sy No. 30/1, 30/6, Situated at Hagadur Village, K.R.Puram HobliOngoingSep 2027Not due yet
Sobha City AthenaProperty No 2091/40/7/1, 9/1, 9/2, 62/2, 62/3/1, Chokkanahalli Village, Ward No. 5, Jakkuru, Yelahanka Zone, BengaluruOngoingSep 2027Not due yet
Sobha Sentosa Phase 3 Wing 3 and 4 Litigation"PROPOSED RESIDENTIAL DEVELOPMENT PLAN AT SY NOS. 49/4 , 49/7, 50/2 (P) , 50/3 (P) , 50/4 (P) , 51/1 (P) , 51/2 B1(P) & 51/2B2 (P) AT BALAGERE, VARTHUR HOBLI, BANGALORE EAST, KARNATAKA "OngoingJun 2027Not due yet
Sobha Sentosa Phase 2 Wing 5 and 6 Litigation"PROPOSED RESIDENTIAL DEVELOPMENT PLAN AT SY NOS. 49/4 , 49/7, 50/2 (P) , 50/3 (P) , 50/4 (P) , 51/1 (P) , 51/2 B1(P) & 51/2B2 (P) AT BALAGERE, VARTHUR HOBLI, BANGALORE EAST, KARNATAKA "OngoingDec 2026Not due yet
Sobha Manhattan Towers-Town Park Phase 1 W 4 & 5 LitigationPhase 1 at Sy.No.48/1A and 48/2, in the composite project Sobha Manhattan Towers - Town Park situated at Sy.Nos.48/1A, 48/2, 50/2 and 50/3, presently bearing Khata No.1877/48/1A-1881/50/2-1886/48/2-1913/50/3, situated at Yadavanahalli Village, Attibele Hobli, Anekal TalukOngoingDec 2026Not due yet
Sobha Dream Acres - Oasis Phase 27 Wing 55, 56, 57 and 58 LitigationBalagere, BangaloreOngoingSep 2026Not delivered
Sobha Sentosa Phase 1 Wing 7 Litigation"PROPOSED RESIDENTIAL DEVELOPMENT PLAN AT SY NOS. 49/4 , 49/7, 50/2 (P) , 50/3 (P) , 50/4 (P) , 51/1 (P) , 51/2 B1(P) & 51/2B2 (P) AT BALAGERE, VARTHUR HOBLI, BANGALORE EAST, KARNATAKA "OngoingJun 2026Not delivered
Sobha Royal Pavilion Phase 8 - Wing 15 LitigationSy No. 54/3, 55/1, 55/2, 58/1, 58/2, 58/3, 59/2, 59/3, 59/4, 59/5, 60/2, 61, 63/1 Hadosiddapura Village, and Sy. No 31/1 Chikkannelli VillageOngoingJun 2026Not delivered
Sobha Royal Pavilion Phase 7 - Wing 12, 13 and 14 LitigationSy No. 54/3, 55/1, 55/2, 58/1, 58/2, 58/3, 59/2, 59/3, 59/4, 59/5, 60/2, 61, 63/1 Hadosiddapura Village, and Sy. No 31/1 Chikkannelli VillageOngoingJun 2026Not delivered
Sobha Royal Pavilion Phase 6 - Wing 10 and 11 LitigationSy No. 54/3, 55/1, 55/2, 58/1, 58/2, 58/3, 59/2, 59/3, 59/4, 59/5, 60/2, 61, 63/1 Hadosiddapura Village, and Sy. No 31/1 Chikkannelli VillageOngoingJun 2026Not delivered
Sobha Royal Pavilion Phase 5 - Wing 8 and 9 LitigationSy No. 54/3, 55/1, 55/2, 58/1, 58/2, 58/3, 59/2, 59/3, 59/4, 59/5, 60/2, 61, 63/1 Hadosiddapura Village, and Sy. No 31/1 Chikkannelli VillageOngoingJun 2026Not delivered
Sobha Insignia LitigationKHATHA NO.1232/128/7, SY NO.128/7, BHOGANAHALLI VILLAGE VARTHUR HOBLI, BENGALURU EAST, BENGALURU URBANOngoingMar 2026Not delivered
Sobha Dream Acres - Tropical Greens Phase 22 Wing 23 and 24 LitigationBalagere, BangaloreOngoingMar 2026Not delivered
Sobha Dream Acres - Tropical Greens Phase 21 Wing 21 and 22 LitigationBalagere, BangaloreOngoingMar 2026Not delivered
Sobha Windsor Phase 1 Wing 1 and 2 LitigationSy No. 107(P), 115/2, 115/3, 115/4, 115/5, 116/3 situated at Nagondanahalli village and Sy No. 30/1, 30/6, Situated at Hagadur Village, K.R.Puram HobliOngoingNov 2025Not delivered
Sobha Windsor Phase 2 Wing 3, 4 and 5 LitigationSy No. 107(P), 115/2, 115/3, 115/4, 115/5, 116/3 situated at Nagondanahalli village and Sy No. 30/1, 30/6, Situated at Hagadur Village, K.R.Puram HobliOngoingApr 2025Not delivered
Sobha Rajvilas LitigationSy. No 19/3, Minerva Mill Quarters, Gopalapura, Mysore Deviation roadOngoingMar 2025Not delivered
Sobha Dream Acres - Tropical Greens Phase 25 Wing 32, 33 and 34 LitigationBalagere, BangaloreOngoingMar 2025Not delivered
Sobha Dream Acres - Tropical Greens Phase 24 Wing 29 and 30 LitigationBalagere, BangaloreOngoingMar 2025Not delivered
Sobha Lake Gardens Phase 2Bharathi Nagar, Krishnarajapura, Seegehalli Village, K.R. Puram HobliOngoingDec 2024Not delivered
Sobha Dream Gardens Phase 2 - Wing 5, 6 and 7 LitigationSurvey No. 50, 51 & 54, Belahalli Village, Yelahanka HobliOngoingNov 2024Not delivered
Sobha Dream Gardens Phase 1 - Wing 8 and 9 LitigationSurvey No. 50, 51 & 54, Belahalli Village, Yelahanka HobliOngoingNov 2024Not delivered
Sobha Dream Acres - Tropical Greens Phase 26 Wing 35, 36, 37 and 38 LitigationBalagere, BangaloreOngoingSep 2024Not delivered
Sobha Dream Acres - Tropical Greens Phase 23 Wing 25, 26, 27 and 28 LitigationBalagere, BangaloreOngoingSep 2024Not delivered
Sobha Royal Pavilion Phase 4 - Wing 1, 2 and 3 LitigationSy No. 54/3, 55/1, 55/2, 58/1, 58/2, 58/3, 59/2, 59/3, 59/4, 59/5, 60/2, 61, 63/1 Hadosiddapura Village, and Sy. No 31/1 Chikkannelli VillageOngoingJun 2024Not delivered
Sobha Royal Pavilion Phase 3 - Wing 16 LitigationSy No. 54/3, 55/1, 55/2, 58/1, 58/2, 58/3, 59/2, 59/3, 59/4, 59/5, 60/2, 61, 63/1 Hadosiddapura Village, and Sy. No 31/1 Chikkannelli VillageOngoingJun 2024Not delivered
Sobha Royal Pavilion Phase 2 - Wing 4 and 5 LitigationSy No. 54/3, 55/1, 55/2, 58/1, 58/2, 58/3, 59/2, 59/3, 59/4, 59/5, 60/2, 61, 63/1 Hadosiddapura Village, and Sy. No 31/1 Chikkannelli VillageOngoingJun 2024Not delivered
Sobha Royal Pavilion Phase 1 - Wing 6 and 7 LitigationSy No. 54/3, 55/1, 55/2, 58/1, 58/2, 58/3, 59/2, 59/3, 59/4, 59/5, 60/2, 61, 63/1 Hadosiddapura Village, and Sy. No 31/1 Chikkannelli VillageOngoingJun 2024Not delivered
Sobha Lake Gardens Phase 1Bharathi Nagar, Krishnarajapura, Seegehalli Village, K.R. Puram HobliOngoingFeb 2024Not delivered

How this compares with Bengaluru Urban

100%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Sobha Galera on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSobha GaleraOther 23Dot size: filed unitsN

Filed coordinates, straight-line distance. 23 registered projects within 2 km.

Builder: SOBHA LIMITED

SOBHA LIMITED has 120 registrations on RERA Karnataka, including Sobha Oakshire Phase 1 Wing 1,2,7 and 8 and Sobha Oakshire Phase 2 Wing 3,4,9 and 10. Its filings declare 196 earlier projects, 85 of them declared completed. Litigation is declared on 33 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Sobha Galera is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Sobha Galera?

The registered promoter entity is SOBHA LIMITED, a company as per the filing. Its CIN L45201KA1995PLC018475 and GSTIN 29AABCS7723E1ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Sobha Galera?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Sobha Galera?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Sobha Galera?

The professionals named in the filing: Architect: Geetha K Nair; Engineer: Mr. Durga Prasad KVR; Chartered Accountant: Balaji D. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sobha Galera?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sobha Galera. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sobha Galera to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.