ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / SKANDHA AMORIS

Registration approved No litigation declared Residential/Group Housing project

SKANDHA AMORIS

By Srivari Estates

RG-KA-75382 · RERA PRM/KA/RERA/1251/310/PR/250523/005940 · Last updated on RERA Karnataka portal: 14 May 2023

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
Dec 2024Possession promisedno revision filed
1Complaints at RERA Karnatakaon this registration
Jump to the 136 documents Report an error

SKANDHA AMORIS is a Residential/Group Housing project by Srivari Estates in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/250523/005940 on 25 May 2023. Possession is promised by 30 Dec 2024. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSKANDHA AMORIS
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560087
  • Pincode560087
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/250523/005940
  • ReraGenie IDRG-KA-75382

Builder

  • NameSrivari Estates
  • Entity typePartnership Firm
  • GSTIN29AEJFS3093L1ZB
  • Authorized SignatoryM Bhargava Chowdary

Key dates

this monthRegisteredMay 2023PromisedDec 2024

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on25 May 2023
  • Promised completion30 Dec 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed136 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1---909

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 May 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 14 May 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Solid waste management and disposalYes-
Emergency Evacuation servicesYes-
Internal Roads & FootpathsYes-
Electricity supply transformer and substationNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes-
LiftsNoNot applicable
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes-
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,517 sq m
Named landowners1
LandownerVillageDistrict
Rekha M--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 6.58 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 5.13 cr-
Payment of taxesRs 70.00 lakh-
Principal sum and interest payable to financial institutions-Scheduled BanksRs 50.00 lakh-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 15.00 lakh-
On-site expenditure-Consultants FeesRs 10.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectV Shiva Kumar
EngineerSrinivasa Rao B
Chartered AccountantK Mahesh Kumar

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
00579/2026-Srivari Estates25/05/2026

Documents filed136

As listed on the registration, under the names the promoter filed them with; the newest 80 of 136 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/250523/005940 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Sources of the funds to manage the Project Cost of Skanda AmorisFile: Sources of Funds.pdf14 May 2023
Own Funds Rs 2,15,50000 as certified by CAFile: SKANDA AMORIS CA CERTIFICATE ON FUNDS FOR UTILIZATION.pdf14 May 2023
Proposal given tom bank and sanction is subject to RERA Registration of the ProjectFile: Bank Proposal SBI Mahadevapura Branch.pdf14 May 2023
Village Map with full viewFile: SKANDA AMORIS VILLAGE MAP FULL VIEW.pdf20 Apr 2023
Village Map confined to project and adjacent areasFile: SKANDA AMORIS VILLAGE MAP.jpg20 Apr 2023
Profit & Loss Account for 2021-22File: SKANDA AMORIS P&L Ac with partners signature 21-22.pdf20 Apr 2023
Balance Sheet for 2021-22File: SKANDA AMORIS BS WITH ANNEXURE AND PARTNERS SIGNATURE 21-22.pdf20 Apr 2023
CDP Map/PlanFile: SKANDA AMORIS Bengaluru-BDA-RMP-2015-PLU_PD_316-Varthur.pdf20 Apr 2023
Profit & Loss Account 2020-21 with UDINFile: Upload 20-21 Profit & Loss Account.pdf22 Mar 2023
Balance Sheet 2020-21 with UDINFile: Upload Balance Sheet 20-21 with annexure.pdf22 Mar 2023
Profit & Loss Account 2021-22 with UDINFile: Upload 21-22 Profit & Loss Account.pdf22 Mar 2023
Balance Sheet 2021-22 with UDINFile: Upload Balance Sheet 20-21 with annexure.pdf22 Mar 2023
ECFile: Upload EC.pdf22 Mar 2023
Guidance Value CircularFile: Guidance Value Varthur.pdf22 Mar 2023
Guidance Value Statement with INDEX of cost in Varthur and adjacent areasFile: Guidance Value Statement.jpg22 Mar 2023
Joint AffidavitFile: Upload Joint Affidavit.pdf22 Mar 2023
No Litigation AffidavitFile: Upload No Litigation.pdf22 Mar 2023
CDPFile: Upload CDP map.jpg22 Mar 2023
Village MapFile: Uplaod Varthur Village Map Final.jpg22 Mar 2023
NOC BWSSBFile: Upload NOC BWSSB.pdf22 Mar 2023
BWSSB PAYT RECEIPT FOR NOCFile: Upload BWSSB Payt Voucher.pdf22 Mar 2023
Structural Stability CertificateFile: Upload Structural Stabi;ity Certificate.jpg22 Mar 2023
Proforma Allotment LetterFile: Upload Proforma allotment letter.pdf22 Mar 2023
Signed Project SpecificationFile: Upload Signed Project Specification.pdf22 Mar 2023
Declaration for not having submitted Balance Sheet & Profit & Loss AccountFile: B Declaration.PDF26 Feb 2023
RTC LatestFile: RTC.pdf26 Feb 2023
Latest Mutation CertificateFile: MUTATION LATEST.pdf26 Feb 2023
MR 1File: MR.pdf26 Feb 2023
MR 2File: MR 2.pdf26 Feb 2023
MR 3File: MR 3.pdf26 Feb 2023
Advocate Search ReportFile: SRIVARI ESTATES ADVOCATE SEARCH REPORT.pdf26 Feb 2023
B Declaration revised with date, month and year of completionFile: B Declaration.PDF26 Feb 2023
EC from 1/4/2005 to 1/4/2009File: EC.jpg26 Feb 2023
Guidance Value StatementFile: Guidance Value Statement.jpg26 Feb 2023
BESCOM NOCFile: BESCOM_NOC (2).pdf26 Feb 2023
BESCOM NOC payt receiptFile: BESCOM_NOC Pat receipt.pdf26 Feb 2023
Proforma of Agreement of Sale as per GOK and RERAFile: Srivari - Agreement of Sale Proforma (1) (Autosaved).pdf26 Feb 2023
Project Specification with the address of the projectFile: Srivari Project Specification with Landmarks.pdf26 Feb 2023
STP Drawings with clear demarcationFile: STP Drawings.pdf26 Feb 2023
Architect's Certificate as a member of Architect's AssociationFile: Ar's COA Certificate-1.pdf26 Feb 2023
Commencement CertificateFile: COMMENCE CERTIFICATE FROM BBMP.pdf26 Feb 2023
Village MapFile: Village Map.pdf26 Feb 2023
No Litigation AffidavitFile: Bhargav's No litigation Affidavit.pdf24 Nov 2022
AffidavitFile: Bhargav's Affidavit.pdf24 Nov 2022
B DeclarationFile: Bhargav's B Declaration.pdf24 Nov 2022
Guidance ValueFile: Bhargav's guidence_varthur.pdf24 Nov 2022
Project SpecificationFile: Bhargav's Project Specification_compressed.pdf24 Nov 2022
Conversion CertificateFile: Bhargav's Land Conversion Certficate_compressed.pdf24 Nov 2022
Village Location MapFile: Bhargav's Location Map.pdf24 Nov 2022
Title DeedFile: Bhargav's Plotted Sale Deed.pdf24 Nov 2022
ECFile: Bhargav's EC.pdf24 Nov 2022
Khatha ExtractFile: Bhargav's Khatha Extract.jpg24 Nov 2022
KhathaFile: Bhargav's Khatha.jpg24 Nov 2022
Building LicenseFile: Bhargav's Building licence BBMP.pdf24 Nov 2022
BBMP Tax Paid ReceiptFile: Bhargav's BBMP Tax Paid receipt 2.jpg24 Nov 2022
RTC, survey Old 95/1 New 95/7-
Mutation, survey Old 95/1 New 95/7-
Encumbrance Certificate, survey Old 95/1 New 95/7-
Conversion/Alienation Order, survey Old 95/1 New 95/7-
JDA, survey Old 95/1 New 95/7-
Khatha, survey Old 95/1 New 95/7-
Registration CertificateFile: Bhargav's Partnership Registration Certificate.jpg-
Partnership DeedFile: Bhargav's Partnership Deed.pdf-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Bhargav's CA Form 1_compressed.pdf-
Certificate issued by Architect Form 2File: Bhargav's Ar's Form 2.pdf-
Certificate issued by Engineer Form 3File: Bhargav's Er Form 3.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Bhargav's JDA_SRIVARI_ESTATES_compressed.pdf-
Certificate from Chartered Account-
Balance Sheet 2021 - 2022File: Bhargav's Supriya ITR 21-22.pdf-
Balance Sheet 2020 - 2021File: Bhargav's ITR 20-21.pdf-
Balance Sheet 2019 - 2020File: Bhargav's ITR 19-20.pdf-
Audited Profit and Loss Statement 2021 - 2022File: Bhargav's R POORNACHANDRA ITR 21-22.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SKANDHA AMORIS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSKANDHA AMORISOther 42Dot size: filed unitsN

Filed coordinates, straight-line distance. 42 registered projects within 2 km.

Builder: Srivari Estates

Srivari Estates has 1 registration on RERA Karnataka, including SKANDHA AMORIS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SKANDHA AMORIS is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SKANDHA AMORIS?

The registered promoter entity is Srivari Estates, a partnership firm as per the filing. Its GSTIN 29AEJFS3093L1ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SKANDHA AMORIS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SKANDHA AMORIS?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at SKANDHA AMORIS?

The professionals named in the filing: Architect: V Shiva Kumar; Engineer: Srinivasa Rao B; Chartered Accountant: K Mahesh Kumar. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SKANDHA AMORIS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SKANDHA AMORIS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SKANDHA AMORIS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.