Registration approved No litigation declared Plotted Development project

Silver Kites -LUXUS

By ESSENN INFRA TOWNSHIP PRIVATE LIMITED

RG-KA-25175 · RERA PRM/KA/RERA/1254/465/PR/051125/008226 · Last updated on RERA Karnataka portal: 14 Apr 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2027Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 129 documents Report an error

Silver Kites -LUXUS is a Plotted Development project by ESSENN INFRA TOWNSHIP PRIVATE LIMITED in Chikkaballapura, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1254/465/PR/051125/008226 on 5 Nov 2025. Possession is promised by 31 Dec 2027.

At a glance

Project

  • NameSilver Kites -LUXUS
  • TypePlotted Development
  • Location
    • Sidlaghatta
    • Chikkaballapura
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1254/465/PR/051125/008226
  • ReraGenie IDRG-KA-25175

Builder

  • NameESSENN INFRA TOWNSHIP PRIVATE LIMITED
  • Entity typeCompany
  • Authorized SignatoryMr. S.SURYANARAYANA
  • DirectorsMr. SHREEVATHSAA, Mr. S.SURYANARAYANA, Mr. SHREEVATHSAA
  • Project HeadMr. SHREEVATHSAA
  • Other registrations2 more →

Key dates

this monthRegisteredNov 2025PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on5 Nov 2025
  • Promised completion31 Dec 2027
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed129 files

Current status

56.4%Of the estimated cost spent so far

Figures as on 14 Apr 2026, this project's latest RERA Karnataka filing.

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Land and ownership5

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners5
LandownerVillageDistrict
ESSENN INFRA TOWNSHIP PRIVATE LIMITED--
ESSENN INFRA TOWNSHIP PRIVATE LIMITED--
ESSENN INFRA TOWNSHIP PRIVATE LIMITED--
ESSENN INFRA TOWNSHIP PRIVATE LIMITED--
ESSENN INFRA TOWNSHIP PRIVATE LIMITED--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 15.90 cr
Cost incurredRs 8.96 cr
Spent of the estimate56.37%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 11.70 crRs 8.38 cr
On-site expenditure-Salaries of workersRs 1.40 crRs 29.00 lakh
On-site expenditure-Consultants FeesRs 1.40 crRs 20.00 lakh
On-site expenditure-Site OverheadRs 1.40 crRs 7.50 lakh
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)-Rs 2.20 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
EngineerMr. B E Divakara
Chartered AccountantMrs. Aishwarya Nityananda

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed129

As listed on the registration, under the names the promoter filed them with; the newest 80 of 129 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1254/465/PR/051125/008226 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 - CA CERTIFICATE - LUXUS.pdf14 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM 6-ENGINEER CERTIFICATE-LUXUS (2).pdf14 Apr 2026
Q4 2025-26 Water supply and sewage board14 Apr 2026
Q4 2025-26 Engineering Department (PWD) for completion of development works14 Apr 2026
Q4 2025-26 KPTCL- BESCOM14 Apr 2026
Q4 2025-26 Horticulture department14 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Certification.pdf14 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer -Silver KItes Luxus.pdf14 Jan 2026
PRM/KA/RERA/1254/465/PR/271222/005561 Upload quarterly report of projectFile: letter to RERA SILVER KITE LEXUS upload quarterly udated 1.pdf4 Nov 2025
Upload GST registration certificateFile: NA6.pdf4 Nov 2025
Upload chartered accountant certificate (CA) in prescribed format form -01.( With details of 3 bankFile: Form-1 - CA CERTIFICATE 2.pdf4 Nov 2025
Upload profit and loss account and balance sheet for 2024-25 CA certification with schedules and CAFile: P&L Sign- 2024-25.pdf4 Nov 2025
Upload profit and loss account and balance sheet for 2024-25 CA certification with schedules and CAFile: Balance Sheet Sign - 2024-25.pdf4 Nov 2025
Upload profit and loss account and balance sheet for 2024-25 CA certification with schedules and CAFile: Cash Flow Statement Sign - 2024-25.pdf4 Nov 2025
Upload profit and loss account and balance sheet for 2024-25 CA certification with schedules and CAFile: Directors REPORT - 2024-25.pdf4 Nov 2025
Upload profit and loss account and balance sheet for 2024-25 CA certification with schedules and CAFile: ITR - 2024-25.pdf4 Nov 2025
Upload the bank affidavit in the prescribed format documentsFile: Bank Affidavit & HDFC Letter for 100, 30 & 70% accounts.pdf4 Nov 2025
Bank 100%, 70%, and 30% account pass sheets or statements, the bank account name should be as per thFile: HDFC - 100% Account.pdf4 Nov 2025
Bank 100%, 70%, and 30% account pass sheets or statements, the bank account name should be as per thFile: HDFC 70% Account.pdf4 Nov 2025
Bank 100%, 70%, and 30% account pass sheets or statements, the bank account name should be as per thFile: HDFC 30% Account.pdf4 Nov 2025
There is revenue from sales/ operation why it is not considered for section 3(1) violation of the acFile: letter to RERA SILVER KITE LEXUS revenue for sales.pdf4 Nov 2025
What are all the sources of funds to complete the project? With supporting documentsFile: Sorce of fund-.pdf4 Nov 2025
Notarized affidavit regarding all pending or cleared litigations /non-litigation by clearly mentioniFile: non liti affi.pdf4 Nov 2025
Defect free EC from 1-4-2011 to till date.File: Sy No 74 - EC.pdf4 Nov 2025
Defect free EC from 1-4-2011 to till date.File: Sy No 75-2 - EC.pdf4 Nov 2025
Defect free EC from 1-4-2011 to till date.File: Sy No 77-2 - EC.pdf4 Nov 2025
Defect free EC from 1-4-2011 to till date.File: Sy No 77-3 - EC.pdf4 Nov 2025
Defect free EC from 1-4-2011 to till date.File: Sy No 77-4 - EC.pdf4 Nov 2025
Approved Provisional layout plan order Original letter.File: PLAN APPROVAL LETTER.pdf4 Nov 2025
ADLR certified survey sketch Certifying the Boundary of the Proposed land original sketch.File: JOINT SKETCH - BLOCK 3 (1).pdf4 Nov 2025
KSPCB NOC.File: letter to RERA SILVER KITE LEXUS KSPCB.pdf4 Nov 2025
All Department NOC from competent authorityFile: BESCOM -.pdf4 Nov 2025
All Department NOC from competent authorityFile: Panchayath NOC - Water.pdf4 Nov 2025
Park, CA and Road area Relinquishment Deed and Katha extract for the sameFile: letter to RERA SILVER KITE LEXUS relinquehment deed.pdf4 Nov 2025
Demarcation of proposed land in original Village map certified by the competent authorityFile: THADURU Village Map.pdf4 Nov 2025
Area details in the project details page not matching with the Approved PlanFile: Engineer - Land Use Analysis -.pdf4 Nov 2025
Individual plot Size, Dimension and Area not matching with the layout planFile: Silver Kites LUXUS (1).xlsx4 Nov 2025
Reason for delay in registration in this authority so provide details of which does not involve markFile: letter to RERA SILVER KITE LEXUS reason for delay.pdf4 Nov 2025
Details of facilities provided thereof including drinking water facilities, emergency services and uFile: drinking water merg.pdf4 Nov 2025
Since the project is ongoing ,kindly upload the Form -6 Engineer's Certificate instead of Form-3.File: Engineer Certificate-Silver Kites Luxus-Form 6-.pdf4 Nov 2025
Uploaded 3(1) affidavit is not notarized.Kindly Upload the Section 3(1) Notarized affidavit in presFile: Notarized Affidavit for 3(1) Voilation - LUXUS.pdf4 Nov 2025
Upload the brief project estimation details with Engineer signature.File: Engineer - Peoject Estimation.pdf4 Nov 2025
Upload the Land cost calculation sheet as per the guidance value(Self-attested copy).File: land merg.pdf4 Nov 2025
Kindly clarify the source of water supply to the project along with the supporting documents and GPSFile: source of water merg new.pdf4 Nov 2025
Kindly upload the STP drawing certified by the Engineer as per the guidelines.File: STP new.pdf4 Nov 2025
RTC, survey 74-
Mutation, survey 74-
Encumbrance Certificate, survey 74-
Conversion/Alienation Order, survey 74-
Sale/Title/Gift Deed, survey 74-
Khatha, survey 74-
RTC, survey New Sy No.75/2 Old Sy No.75-
Mutation, survey New Sy No.75/2 Old Sy No.75-
Encumbrance Certificate, survey New Sy No.75/2 Old Sy No.75-
Conversion/Alienation Order, survey New Sy No.75/2 Old Sy No.75-
Sale/Title/Gift Deed, survey New Sy No.75/2 Old Sy No.75-
Khatha, survey New Sy No.75/2 Old Sy No.75-
RTC, survey 77/2-
Mutation, survey 77/2-
Encumbrance Certificate, survey 77/2-
Conversion/Alienation Order, survey 77/2-
Sale/Title/Gift Deed, survey 77/2-
Khatha, survey 77/2-
RTC, survey 77/3-
Mutation, survey 77/3-
Encumbrance Certificate, survey 77/3-
Conversion/Alienation Order, survey 77/3-
Sale/Title/Gift Deed, survey 77/3-
Khatha, survey 77/3-
RTC, survey 77/4-
Mutation, survey 77/4-
Encumbrance Certificate, survey 77/4-
Conversion/Alienation Order, survey 77/4-
Sale/Title/Gift Deed, survey 77/4-
Khatha, survey 77/4-
Registration CertificateFile: ESSENN Certificate of Incorporation, MOA & AOA.PDF-
Memorandum of AssociationFile: ESSENN Certificate of Incorporation, MOA & AOA.PDF-
Article of AssociationFile: ESSENN Certificate of Incorporation, MOA & AOA.PDF-
GST CertificateFile: NA6.pdf-
Organization StructureFile: NA6.pdf-

How this compares with Chikkaballapura

27%of Chikkaballapura projects moved their completion datethis one has not
1%of Chikkaballapura registrations are shown as withdrawn or revokedthis one is not

Computed across the 170+ Chikkaballapura projects on ReraGenie, from their own filings.

Keep Silver Kites -LUXUS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Chikkaballapura170+ in Chikkaballapura

Builder: ESSENN INFRA TOWNSHIP PRIVATE LIMITED

ESSENN INFRA TOWNSHIP PRIVATE LIMITED has 3 registrations on RERA Karnataka, including Silver Kites -LUXUS and SILVER KITES - ELITE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Chikkaballapura district page.

Frequently asked questions

What are my rights if Silver Kites -LUXUS is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Silver Kites -LUXUS?

The registered promoter entity is ESSENN INFRA TOWNSHIP PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Silver Kites -LUXUS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Silver Kites -LUXUS?

The professionals named in the filing: Engineer: Mr. B E Divakara; Chartered Accountant: Mrs. Aishwarya Nityananda. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Silver Kites -LUXUS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Silver Kites -LUXUS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Silver Kites -LUXUS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.