ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / SIGNATURE PRISTINE

Registration approved No litigation declared Residential/Group Housing project

SIGNATURE PRISTINE

By SIGNATURE DWELLINGS PRIVATE LIMITED

RG-KA-22749 · RERA PRM/KA/RERA/1251/308/PR/281223/006516 · Last updated on RERA Karnataka portal: 15 Dec 2023

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2025Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 115 documents Report an error

SIGNATURE PRISTINE is a Residential/Group Housing project by SIGNATURE DWELLINGS PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/281223/006516 on 28 Dec 2023. Possession is promised by 31 Dec 2025.

At a glance

Project

  • NameSIGNATURE PRISTINE
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
    • 562130
  • Pincode562130
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/281223/006516
  • ReraGenie IDRG-KA-22749

Builder

  • NameSIGNATURE DWELLINGS PRIVATE LIMITED
  • Entity typeCompany
  • CINU70200KL2012PTC030293
  • GSTIN29AARCS0900K1Z1
  • Authorized SignatoryPRASANTH NARAYANAN
  • Managing DirectorPRASANTH NARAYANAN
  • DirectorsPRASANTH NARAYANAN, SEEMA PRASANTH
  • Project HeadPRASANTH NARAYANAN
  • Other registrations9 more →
  • Declared earlier projects6 →

Key dates

this monthRegisteredDec 2023PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on28 Dec 2023
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed115 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SIGNATURE PRISTINE---1560156

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Dec 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)Not applicable
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 15 Dec 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsNoNot applicable
Use of renewable energyYes-
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingYes-
Street LightingYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityNoNot applicable
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areasYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership3

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,708 sq m
Named landowners3
LandownerVillageDistrict
MANJUNATH M--
ASHOK--
R K CORTINA a Partnership Firm Rep by its Partner S MANOHAR and others--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 44.72 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 35.47 cr-
Administrative CostsRs 8.00 cr-
On-site expenditure-Consultants FeesRs 75.00 lakh-
Payment of taxesRs 50.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRamesh Babu J P
EngineerRAMESHA D B
Chartered AccountantPRAVEEN SHETTER

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed115

As listed on the registration, under the names the promoter filed them with; the newest 80 of 115 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/281223/006516 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Clarification for OCFile: Clarification For OC.pdf15 Dec 2023
Form - 7 Annual Report Signature MeadowsFile: SIGNTURE MEADOWS - Form 7 FY 2022-23.pdf8 Dec 2023
Form - 7 Annual Report Signature SplendorFile: Form 7 SIGNATURE SPLENDOR.pdf8 Dec 2023
Confirmation SplendorFile: Submission Confirmation 08-12-2023.pdf8 Dec 2023
Confirmation MeadowsFile: Submission Confirmation 08-12-2023.pdf8 Dec 2023
Bank AffidavitFile: Bank Affidavit.pdf4 Dec 2023
Financial Statement 2020-21 Self AttestedFile: Financial Statement FY 2020-21.pdf4 Dec 2023
Financial Statement 2021-22 Self AttestedFile: Financial Statement FY 2021-22.pdf4 Dec 2023
Financial Statement 2022-23 Self AttestedFile: Financial Statement FY 2022-23.pdf4 Dec 2023
Company PAN Self AttestedFile: Signature PAN Self Attested.pdf4 Dec 2023
Certified Carpet Area CalculationFile: Certified Carpet area calculation.pdf4 Dec 2023
CDP DemarcationFile: CDP Demarcation.jpg4 Dec 2023
Village MapFile: Village Map.pdf4 Dec 2023
ZR CopyFile: Zonal Regulation - Anekal.pdf4 Dec 2023
SEIAA and KSPCB No of Units ClarificationFile: Clarification.pdf4 Dec 2023
Auditors Report 2022-23File: Audit Report FY 2022-23.pdf4 Dec 2023
BESCOM Fees Paid Self AttestedFile: BESCOM-BILL.pdf4 Dec 2023
BESCOM NOC Self AttestedFile: BESCOM-NOC.pdf4 Dec 2023
Water NOC with Fees Paid Self AttestedFile: WATER-NOC.pdf4 Dec 2023
Sale Agreement ProformaFile: Sale Agreement Draft.pdf4 Dec 2023
STP DrawingFile: STP Drawing Certified.jpeg4 Dec 2023
STP Drawing CertifiedFile: STP Drawing Certified.pdf4 Dec 2023
Land Cost CalculationFile: Land Cost Calculation.pdf4 Dec 2023
Building LicenseFile: Building License.pdf4 Dec 2023
Form - 2 Architect CertificateFile: Form - 2 Architect Certificate.pdf4 Dec 2023
Architect COA CertificateFile: Architect COA.pdf4 Dec 2023
Engineer License Self AttestedFile: Ramesh Engineer Self Attested.pdf4 Dec 2023
RTC, survey 57/9 (Old Sy. No. 57)-
Mutation, survey 57/9 (Old Sy. No. 57)-
Encumbrance Certificate, survey 57/9 (Old Sy. No. 57)-
Conversion/Alienation Order, survey 57/9 (Old Sy. No. 57)-
JDA, survey 57/9 (Old Sy. No. 57)-
Khatha, survey 57/9 (Old Sy. No. 57)-
RTC, survey 57/1-
Mutation, survey 57/1-
Encumbrance Certificate, survey 57/1-
Conversion/Alienation Order, survey 57/1-
JDA, survey 57/1-
Khatha, survey 57/1-
Registration CertificateFile: Certificate of Incorporation.pdf-
Organization StructureFile: Certificate of Incorporation.pdf-
Certificate issued by CA Form 1File: Form-1- Chartered Accountant.pdf-
Certificate issued by Architect Form 2File: Form - 2 Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Form - 3 Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non Litigation Affidavit.pdf-
Certificate from Chartered AccountFile: Form-1- Chartered Accountant.pdf-
Balance Sheet 2022 - 2023File: Financials Balance Sheet - 2022-23.pdf-
Balance Sheet 2021 - 2022File: Financials_FY_2020-21_11.pdf-
Balance Sheet 2020 - 2021File: Balance Sheet.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Financials Balance Sheet - 2022-23.pdf-
Audited Profit and Loss Statement 2021 - 2022File: Financials_FY_2020-21_11.pdf-
Audited Profit and Loss Statement 2020 - 2021File: P and L.pdf-
Director's Report 2022 - 2023File: Financials Balance Sheet - 2022-23.pdf-
Director's Report 2021 - 2022File: Audit Report uploaded.pdf-
Director's Report 2020 - 2021File: P and L.pdf-
Cash Flow Statement 2022 - 2023File: Financials Balance Sheet - 2022-23.pdf-
Cash Flow Statement 2021 - 2022File: Audit Report uploaded.pdf-
Auditor's Report 2022 - 2023File: Financials Balance Sheet - 2022-23.pdf-
Auditor's Report 2021 - 2022File: Financials_FY_2020-21_11.pdf-
Auditor's Report 2020 - 2021File: Audit report.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: Financials Balance Sheet - 2022-23.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITR - 2021-22 - Ack.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: Ack.pdf-
Commencement Certificate-
BESCOM NOC-
Water NOC with Fees Paid-
SINGLE SKETCH-
Typical First Second and Third Floor Plan-
single sketch approval letter-
Ground Floor Plan-
Stilt Floor Plan-
Specifications And Amenities - Pristine-
Site Plan-
Terrace Floor Plan-
Structural Stability Certificate Pristine-
Legal Opinion-
JDA-

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 not delivered by the promised date3 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
SIGNATURE SPLENDORSurvey No's.170/1, 171/1, 171/2A and 171/2B of Madivala village , Kasaba Hobli, Anekal Taluk , Madivala village , Anekal , Bengaluru UrbanOngoingDec 2025Not delivered
SIGNATURE MEADOWSConverted Sy No.37/5 and 37/6, Khata No 150200101600720802 , Situated at Gonigattapura Village, Sarjapura Hobli, Anekal Taluk , Gonigattapura Village , Anekal , Bengaluru UrbanOngoingDec 2024Not delivered
SIGNATURE CRESTSurvey No.44/4, Khatha No.386/44/4/198, Gonigattapura Village, Sarjapura HobliCompleted-No date filed
SIGNATURE CLASSIC - 2Converted Survey No.71, Situated at Sompura Village, Sarjapura HobliCompleted-No date filed
SIGNATURE CLASSICSy No 71, Sompura Village, Sarjapura Hobli, Anekal Taluk.Completed-No date filed

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SIGNATURE PRISTINE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSIGNATURE PRISTINEOther 40Dot size: filed unitsN

Filed coordinates, straight-line distance. 40 registered projects within 2 km.

Builder: SIGNATURE DWELLINGS PRIVATE LIMITED

SIGNATURE DWELLINGS PRIVATE LIMITED has 10 registrations on RERA Karnataka, including SIGNATURE REGAL and SIGNATURE PREMIER. Its filings declare 6 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SIGNATURE PRISTINE is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SIGNATURE PRISTINE?

The registered promoter entity is SIGNATURE DWELLINGS PRIVATE LIMITED, a company as per the filing. Its CIN U70200KL2012PTC030293 and GSTIN 29AARCS0900K1Z1 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SIGNATURE PRISTINE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SIGNATURE PRISTINE?

The professionals named in the filing: Architect: Ramesh Babu J P; Engineer: RAMESHA D B; Chartered Accountant: PRAVEEN SHETTER. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SIGNATURE PRISTINE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SIGNATURE PRISTINE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SIGNATURE PRISTINE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.