SHYAM VILLA
RG-GJ-68419 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA02984/250618 · Last updated on GujRERA portal: 28 Sep 2019
Source: official GujRERA filing
Red flags
- No red flags in this filing
Clear
- Completion date never moved
- Separate project account declared
Saved.
SHYAM VILLA is a Residential/Group Housing project by SIDDH DEVELOPERS in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA02984/250618 on 25 Jun 2018. Possession is promised by 28 Sep 2019. 53 of the 56 units on this registration are recorded sold or booked, and 448 of 504 construction stages are filed complete.
At a glance
Project
- NameSHYAM VILLA
- TypeResidential/Group Housing
- Location
- SHYAM VILLA B/S VATSALYA KUNJ
- ATLADRA-BIL ROAD
- Bill
- Vadodara
- 391410
- Pincode391410
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA02984/250618
- ReraGenie IDRG-GJ-68419
Builder
- NameSIDDH DEVELOPERS
- Entity typePARTNERSHIP FIRM
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 28 Sep 2019
- Registered on25 Jun 2018
- Promised completion28 Sep 2019
- Revised completionNone
- Buildings56 building records
- Documents filed93 files
Current status
Figures as on 28 Sep 2019, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| 23 | - | - | - | 1 | 0 | 1 |
| 24 | - | - | - | 1 | 0 | 1 |
| 25 | - | - | - | 1 | 0 | 1 |
| 26 | - | - | - | 1 | 0 | 1 |
| 27 | - | - | - | 1 | 0 | 1 |
| 28 | - | - | - | 1 | 0 | 1 |
| 29 | - | - | - | 1 | 0 | 1 |
| 30 | - | - | - | 1 | 0 | 1 |
| 31 | - | - | - | 1 | 0 | 1 |
| 32 | - | - | - | 1 | 0 | 1 |
| 33 | - | - | - | 1 | 0 | 1 |
| 34 | - | - | - | 1 | 0 | 1 |
| 35 | - | - | - | 1 | 0 | 1 |
| 36 | - | - | - | 1 | 0 | 1 |
| 37 | - | - | - | 1 | 0 | 1 |
| 38 | - | - | - | 1 | 0 | 1 |
| 39 | - | - | - | 1 | 0 | 1 |
| 40 | - | - | - | 1 | 0 | 1 |
| 41 | - | - | - | 1 | 0 | 1 |
| 42 | - | - | - | 1 | 0 | 1 |
| 43 | - | - | - | 1 | 0 | 1 |
| 44 | - | - | - | 1 | 0 | 1 |
| 45 | - | - | - | 1 | 0 | 1 |
| 46 | - | - | - | 1 | 0 | 1 |
| 47 | - | - | - | 1 | 0 | 1 |
| 48 | - | - | - | 1 | 0 | 1 |
| 49 | - | - | - | 1 | 0 | 1 |
| 50 | - | - | - | 1 | 0 | 1 |
| 51 | - | - | - | 1 | 0 | 1 |
| 52 | - | - | - | 1 | 0 | 1 |
| 53 | - | - | - | 1 | 0 | 1 |
| 54 | - | - | - | 1 | 0 | 1 |
| 55 | - | - | - | 1 | 0 | 1 |
| 56 | - | - | - | 1 | 0 | 1 |
| 1 | - | - | - | 1 | 0 | 1 |
| 2 | - | - | - | 1 | 0 | 1 |
| 3 | - | - | - | 1 | 0 | 1 |
| 4 | - | - | - | 1 | 0 | 1 |
| 5 | - | - | - | 1 | 0 | 1 |
| 6 | - | - | - | 1 | 0 | 1 |
| 7 | - | - | - | 1 | 0 | 1 |
| 8 | - | - | - | 1 | 0 | 1 |
| 9 | - | - | - | 1 | 0 | 1 |
| 10 | - | - | - | 1 | 0 | 1 |
| 11 | - | - | - | 1 | 0 | 1 |
| 12 | - | - | - | 1 | 0 | 1 |
| 13 | - | - | - | 1 | 0 | 1 |
| 14 | - | - | - | 1 | 0 | 1 |
| 15 | - | - | - | 1 | 0 | 1 |
| 16 | - | - | - | 1 | 0 | 1 |
| 17 | - | - | - | 1 | 0 | 1 |
| 18 | - | - | - | 1 | 0 | 1 |
| 19 | - | - | - | 1 | 0 | 1 |
| 20 | - | - | - | 1 | 0 | 1 |
| 21 | - | - | - | 1 | 0 | 1 |
| 22 | - | - | - | 1 | 0 | 1 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building20
As on 28 Sep 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 56 buildings; the table lists the first 20.
448 of 504 construction stages are filed complete across 56 buildings. The stage furthest along is Stilt Floor, at 0%.
2389%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
2489%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
2589%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
2689%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
2789%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
2889%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
2989%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
3089%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
3189%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
3289%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
3389%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
3489%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
3589%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
3689%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
3789%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
3889%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
3989%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
4089%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
4189%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
4289%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Progress on shared amenities19
As on 28 Sep 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 100% |
| Water supply | Yes | 100% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 100% |
| Storm water drains | No | Not applicable |
| Landscaping and tree planting | No | Not applicable |
| Street lighting | No | Not applicable |
| Community buildings | Yes | 100% |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation, rain water harvesting | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Fire fighting | No | Not applicable |
| Drinking water facilities | No | Not applicable |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | No | Not applicable |
| Letter box | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| 1 | NA | Rs 32.94 lakh | Rs 17.54 lakh |
| 2 | NA | Rs 32.94 lakh | Rs 17.54 lakh |
| 3 | NA | Rs 32.94 lakh | Rs 17.54 lakh |
| 4 | NA | Rs 32.94 lakh | Rs 17.54 lakh |
| 5 | NA | Rs 32.94 lakh | Rs 17.54 lakh |
| 6 | NA | Rs 32.94 lakh | Rs 17.54 lakh |
| 7 | NA | Rs 32.94 lakh | Rs 17.54 lakh |
| 8 | NA | Rs 32.94 lakh | Rs 17.54 lakh |
| 9 | NA | Rs 32.94 lakh | Rs 17.54 lakh |
| 10 | NA | Rs 32.94 lakh | Rs 17.54 lakh |
| 11 | NA | Rs 32.94 lakh | Rs 17.54 lakh |
| 12 | NA | Rs 32.94 lakh | Rs 17.54 lakh |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PATEL ASSOCIATES |
| Engineer | PRAMUKH ASSOCIATES |
Documents filed93
As listed on the registration, under the names the promoter filed them with; the newest 80 of 93 are shown. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA02984/250618 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect's certificate (Form 1) | 28 Sep 2019 |
| Engineer's certificate (Form 2) | 28 Sep 2019 |
| Engineer's certificate annexure | 28 Sep 2019 |
| Site photograph, 23 | 28 Sep 2019 |
| Site photograph, 24 | 28 Sep 2019 |
| Site photograph, 25 | 28 Sep 2019 |
| Site photograph, 26 | 28 Sep 2019 |
| Site photograph, 27 | 28 Sep 2019 |
| Site photograph, 28 | 28 Sep 2019 |
| Site photograph, 29 | 28 Sep 2019 |
| Site photograph, 30 | 28 Sep 2019 |
| Site photograph, 31 | 28 Sep 2019 |
| Site photograph, 32 | 28 Sep 2019 |
| Site photograph, 33 | 28 Sep 2019 |
| Site photograph, 34 | 28 Sep 2019 |
| Site photograph, 35 | 28 Sep 2019 |
| Site photograph, 36 | 28 Sep 2019 |
| Site photograph, 37 | 28 Sep 2019 |
| Site photograph, 38 | 28 Sep 2019 |
| Site photograph, 39 | 28 Sep 2019 |
| Site photograph, 40 | 28 Sep 2019 |
| Site photograph, 41 | 28 Sep 2019 |
| Site photograph, 42 | 28 Sep 2019 |
| Site photograph, 43 | 28 Sep 2019 |
| Site photograph, 44 | 28 Sep 2019 |
| Site photograph, 45 | 28 Sep 2019 |
| Site photograph, 46 | 28 Sep 2019 |
| Site photograph, 47 | 28 Sep 2019 |
| Site photograph, 48 | 28 Sep 2019 |
| Site photograph, 49 | 28 Sep 2019 |
| Site photograph, 50 | 28 Sep 2019 |
| Site photograph, 51 | 28 Sep 2019 |
| Site photograph, 52 | 28 Sep 2019 |
| Site photograph, 53 | 28 Sep 2019 |
| Site photograph, 54 | 28 Sep 2019 |
| Site photograph, 55 | 28 Sep 2019 |
| Site photograph, 56 | 28 Sep 2019 |
| Site photograph, 1 | 28 Sep 2019 |
| Site photograph, 2 | 28 Sep 2019 |
| Site photograph, 3 | 28 Sep 2019 |
| Site photograph, 4 | 28 Sep 2019 |
| Site photograph, 5 | 28 Sep 2019 |
| Site photograph, 6 | 28 Sep 2019 |
| Site photograph, 7 | 28 Sep 2019 |
| Site photograph, 8 | 28 Sep 2019 |
| Site photograph, 9 | 28 Sep 2019 |
| Site photograph, 10 | 28 Sep 2019 |
| Site photograph, 11 | 28 Sep 2019 |
| Site photograph, 12 | 28 Sep 2019 |
| Site photograph, 13 | 28 Sep 2019 |
| Site photograph, 14 | 28 Sep 2019 |
| Site photograph, 15 | 28 Sep 2019 |
| Site photograph, 16 | 28 Sep 2019 |
| Site photograph, 17 | 28 Sep 2019 |
| Site photograph, 18 | 28 Sep 2019 |
| Site photograph, 19 | 28 Sep 2019 |
| Site photograph, 20 | 28 Sep 2019 |
| Site photograph, 21 | 28 Sep 2019 |
| Site photograph, 22 | 28 Sep 2019 |
| RERA registration certificate | 25 Jun 2018 |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Vadodara
Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.
Keep SHYAM VILLA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bill2,900+ in Vadodara
Filed coordinates, straight-line distance. 308 registered projects within 2 km.
SAMANVAY STATUS 2
Status Realty
PMAY BILL 532 EWS-II FP 38
VADODARA URBAN DEVELOPMENT AUTHORITY
THE MARK
SHREE GANESH DEVLOPERS
ANANTA SAVERA SWAGATAM
S S INFRA
PMAY BHAYLI 392 EWS-II FP 114
VADODARA URBAN DEVELOPMENT AUTHORITY
PMAY BHAYLI 360 EWS-I FP 100
VADODARA URBAN DEVELOPMENT AUTHORITY
See every Vadodara project, with the district possession charts
Builder: SIDDH DEVELOPERS
SIDDH DEVELOPERS has 2 registrations on GujRERA, including SIDDH DEVELOPER and SHYAM VILLA. Read the full track record. See more projects on the Vadodara district page.
Frequently asked questions
What are my rights if SHYAM VILLA is delayed beyond 28 Sep 2019?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of SHYAM VILLA?
The registered promoter entity is SIDDH DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in SHYAM VILLA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SHYAM VILLA?
The professionals named in the filing: Architect: PATEL ASSOCIATES; Engineer: PRAMUKH ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHYAM VILLA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.