Valid until 30 Jun 2023 Mixed Development project

Shyam Heights Phase-I

By MARUTI BUILDERS

RG-GJ-19093 · RERA PR/GJ/GANDHINAGAR/KALOL/AUDA/MAA03746/A1M/200620 · Last updated on GujRERA portal: 1 Apr 2023

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jun 2023Possession promisedno revision filed
14 of 36Construction stages doneacross 4 buildings; furthest along: Installation of lifts, 99%
58 of 123Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

Shyam Heights Phase-I is a Mixed Development project by MARUTI BUILDERS in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/KALOL/AUDA/MAA03746/A1M/200620 on 19 Oct 2018. Possession is promised by 30 Jun 2023. 65 of the 123 units on this registration are recorded sold or booked, and 14 of 36 construction stages are filed complete.

At a glance

Project

  • NameShyam Heights Phase-I
  • TypeMixed Development
  • Location
    • Shyam Heights
    • B/h Ishwarkrupa Society
    • Kalol-Mansa Road
    • kalol
    • Kalol
    • Gandhinagar
    • 382721
  • Pincode382721
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/KALOL/AUDA/MAA03746/A1M/200620
  • ReraGenie IDRG-GJ-19093

Builder

  • NameMARUTI BUILDERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →
  • Past their filed date2

Key dates

this monthRegisteredOct 2018PromisedJun 2023

Key facts

Registration and timeline

  • StatusValid until 30 Jun 2023
  • Registered on19 Oct 2018
  • Promised completion30 Jun 2023
  • Revised completionNone
  • Buildings4 building records
  • Documents filed41 files

Current status

53%65 of 123 units booked
53.0%Of the estimated cost spent so far

Figures as on 1 Apr 2023, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---281139
B---28028
C---28028
D---28028

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 1 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 36 construction stages are filed complete across 4 buildings. The stage furthest along is Installation of lifts, at 99%.

A99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats95%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing99%
B99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats95%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing99%
C0%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
D0%
ActivityProgress
Excavation0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 1 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes55%
Water supplyYes75%
Sewerage (chamber, lines, septic tank, STP)Yes65%
Storm water drainsYes60%
Landscaping and tree plantingYes65%
Street lightingYes65%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes65%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes65%
Fire fightingYes55%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxYes55%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,434 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 6.49 cr
Cost incurredRs 3.44 cr
Spent of the estimate52.95%
BuildingWingEstimatedIncurred
ANARs 1.62 crRs 85.88 lakh
BNARs 1.62 crRs 85.88 lakh
CNARs 1.62 crRs 85.88 lakh
DNARs 1.62 crRs 85.88 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNrupesh Shah
EngineerKetav P Joshi

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/KALOL/AUDA/MAA03746/A1M/200620 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)1 Apr 2023
Architect's certificate (Form 1)28 Mar 2023
Engineer's certificate (Form 2)28 Mar 2023
Engineer's certificate annexure28 Mar 2023
Site photograph, A28 Mar 2023
Site photograph, B28 Mar 2023
Site photograph, C28 Mar 2023
Site photograph, D28 Mar 2023
RERA registration certificate19 Oct 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

53%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep Shyam Heights Phase-I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Kalol1,600+ in Gandhinagar

2 kmShyam Heights Phase-IOther 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 25 registered projects within 2 km.

Builder: MARUTI BUILDERS

MARUTI BUILDERS has 2 registrations on GujRERA, including Shyam Heights Phase-I and Shyam Heights Phase-II. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if Shyam Heights Phase-I is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Shyam Heights Phase-I?

The registered promoter entity is MARUTI BUILDERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Shyam Heights Phase-I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Shyam Heights Phase-I?

The professionals named in the filing: Architect: Nrupesh Shah; Engineer: Ketav P Joshi. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shyam Heights Phase-I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shyam Heights Phase-I. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shyam Heights Phase-I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.