ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / SHRINATH ENCLAVE

Valid until 31 Dec 2025 Plotted Development project

SHRINATH ENCLAVE

By SHRI RADHAAVALLABHA INFRACON LLP

RG-GJ-13764 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/PAA13156/EX1/EX3/011025/311225 · Last updated on GujRERA portal: 30 Aug 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 15 months
  • 3 extensions taken

Clear

  • Nothing verified clear yet
Dec 2025Possession promisedmoved 15 months from the original
6 of 9Construction stages donefurthest along: Plinth, 0%
1 of 9Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

SHRINATH ENCLAVE is a Plotted Development project by SHRI RADHAAVALLABHA INFRACON LLP in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/PAA13156/EX1/EX3/011025/311225 on 19 Mar 2024. Possession is promised by 31 Dec 2025. The completion date has moved by 15 months from the original filing. 8 of the 9 units on this registration are recorded sold or booked, and 6 of 9 construction stages are filed complete.

At a glance

Project

  • NameSHRINATH ENCLAVE
  • TypePlotted Development
  • Location
    • Survey No:157/3
    • TPS No:239
    • Near Shree Krusn Crystal Flat & Shops at Village BHATT
    • BHAT
    • GANDHINAGAR
    • Gandhinagar
    • 382428
  • Pincode382428
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/PAA13156/EX1/EX3/011025/311225
  • ReraGenie IDRG-GJ-13764

Builder

  • NameSHRI RADHAAVALLABHA INFRACON LLP
  • Entity typeLIMITED LIABILITY PARTNERSHIP FIRM

Key dates

this monthRegisteredMar 2024First promiseSep 2024Revised toDec 2025

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2025
  • Registered on19 Mar 2024
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 1 Sep 2024)
  • Buildings1 building record
  • Documents filed43 files

Current status

89%8 of 9 units booked

Figures as on 30 Aug 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
OPEN PLOT (1 TO 9)---009

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 30 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 9 construction stages are filed complete. The stage furthest along is Plinth, at 0%.

OPEN PLOT (1 TO 9): 67% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 30 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,069 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHARSHADKUMAR K. PRAJAPATI
EngineerJIGARKUMAR GHANSHYAMBHAI SHAH

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/PAA13156/EX1/181124/310325Applied Sep 2024; approved Nov 2024
PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/PAA13156/EX1/EX2/230625/310825Applied Mar 2025; approved Jun 2025
PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/PAA13156/EX1/EX3/011025/311225Applied Aug 2025; approved Oct 2025

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/PAA13156/EX1/EX3/011025/311225 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)30 Aug 2025
Engineer's certificate (Form 2)30 Aug 2025
Engineer's certificate annexure30 Aug 2025
Accountant's certificate (Form 3)30 Aug 2025
Site photograph, OPEN PLOT (1 TO 9)30 Aug 2025
RERA registration certificate19 Mar 2024
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

89%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one moved by 15 months

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep SHRINATH ENCLAVE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near BHAT,GANDHINAGAR1,600+ in Gandhinagar

2 kmSHRINATH ENCLAVEOther 41Dot size: filed unitsN

Filed coordinates, straight-line distance. 41 registered projects within 2 km.

Builder: SHRI RADHAAVALLABHA INFRACON LLP

SHRI RADHAAVALLABHA INFRACON LLP has 1 registration on GujRERA, including SHRINATH ENCLAVE. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if SHRINATH ENCLAVE is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHRINATH ENCLAVE?

The registered promoter entity is SHRI RADHAAVALLABHA INFRACON LLP, a limited liability partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHRINATH ENCLAVE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHRINATH ENCLAVE?

The professionals named in the filing: Architect: HARSHADKUMAR K. PRAJAPATI; Engineer: JIGARKUMAR GHANSHYAMBHAI SHAH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHRINATH ENCLAVE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHRINATH ENCLAVE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHRINATH ENCLAVE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.