SHREYA SERENITY

By SHRIYA HOLDINGS & PROPERTIES PRIVATE LIMITED

RG-KA-39596 · RERA PRM/KA/RERA/1259/479/PR/130525/007734 · Last updated on RERA Karnataka portal: 13 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jan 2031Possession promisedno revision filed
3 of 15Construction stages donefurthest along: Sub-structure flooring (Parking Floor, 90%
106 of 142Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 120 documents Report an error

SHREYA SERENITY is a Mixed Development project by SHRIYA HOLDINGS & PROPERTIES PRIVATE LIMITED in Dharwad, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1259/479/PR/130525/007734 on 13 May 2025. Possession is promised by 15 Jan 2031. 36 of the 142 units on this registration are recorded sold or booked, and 3 of 15 construction stages are filed complete.

At a glance

Project

  • NameSHREYA SERENITY
  • TypeMixed Development
  • Location
    • Hubballi
    • Dharwad
    • 580030
  • Pincode580030
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1259/479/PR/130525/007734
  • ReraGenie IDRG-KA-39596

Builder

  • NameSHRIYA HOLDINGS & PROPERTIES PRIVATE LIMITED
  • Entity typeCompany
  • CINU45309KA2019PTC130176
  • GSTIN29ABCCS9963L1ZF
  • Authorized SignatorySURAJ ALAVANDI
  • CeoSURAJ ALAVANDI
  • DirectorsPRAKASH CHAVAN, ANKIT KUMAR JAIN, SHIVAPPA Y KUNDARGI, SURAJ ALAVANDI
  • Project HeadSURAJ ALAVANDI

Key dates

this monthRegisteredMay 2025PromisedJan 2031

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on13 May 2025
  • Promised completion15 Jan 2031
  • Revised completionNone
  • Buildings4 building records
  • Documents filed120 files

Current status

25%36 of 142 units booked
3.0%Of the estimated cost spent so far

Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING - A---38038
WING B---36036
WING -C---38038
WING D---30030

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 15 construction stages are filed complete. The stage furthest along is Sub-structure flooring (Parking Floor, at 90%.

Building: 32% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)90%
Retaining wall (All types)40%
RCC or MS Framed structure31%
Masonry Construction12%
Plastering inside , outside & Ceiling2%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes0%
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallYes0%
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes0%
GymNoNot applicable
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementNoNot applicable
TerraceYes0%
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,892 sq m
Named landowners1
LandownerVillageDistrict
Veerendra Koujalagi--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 89.90 cr
Cost incurredRs 2.68 cr
Spent of the estimate2.98%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 87.00 crRs 2.67 cr
Payment of taxesRs 2.90 cr-
On-site expenditure-Consultants Fees-Rs 5,000
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)-Rs 72,738

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBakul Bindumadhav Joshi
EngineerAshok Associates
Chartered AccountantSantoshkumar Patil

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed120

As listed on the registration, under the names the promoter filed them with; the newest 80 of 120 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1259/479/PR/130525/007734 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate-SERENITY -RERA -Q2.pdf13 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Q2 - 26-27 Form - 5, Architect Certificate (QU).pdf13 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Q2 - 26-27 Form - 6, Engineer Certificate (QU).pdf13 Oct 2026
Q2 2026-27 Water supply and sewage board13 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)13 Oct 2026
Q2 2026-27 KPTCL- BESCOM13 Oct 2026
Q2 2026-27 Fire and Safety13 Oct 2026
Q2 2026-27 Airport Authority of India13 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: RERA signed CA form - Q1-26-27.pdf12 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Q1 - 26-27 Form - 5, Architect Certificate (QU).pdf12 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Q1 - 26-27 Form - 6, Engineer Certificate (QU).pdf12 Jul 2026
Q1 2026-27 Water supply and sewage board12 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)12 Jul 2026
Q1 2026-27 KPTCL- BESCOM12 Jul 2026
Q1 2026-27 Fire and Safety12 Jul 2026
Q1 2026-27 Airport Authority of India12 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA RERA certificate-Q-4_c.pdf29 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Q4- 25-26 Form - 5, Architect Certificate (QU).pdf29 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Q4-25-26 Form - 6, Engineer Certificate (QU).pdf29 Apr 2026
Q4 2025-26 Water supply and sewage board29 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)29 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)29 Apr 2026
Q4 2025-26 KPTCL- BESCOM29 Apr 2026
Q4 2025-26 Fire and Safety29 Apr 2026
Q4 2025-26 Airport Authority of India29 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM -4 Q3 Serenity.pdf19 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Architect Certificate Serenity.pdf19 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate Serenity.pdf19 Jan 2026
Q3 2025-26 Water supply and sewage board19 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)19 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)19 Jan 2026
Q3 2025-26 KPTCL- BESCOM19 Jan 2026
Q3 2025-26 Fire and Safety19 Jan 2026
Q3 2025-26 Airport Authority of India19 Jan 2026
Revenue From Operation DeclarationFile: 1 Revenue From Operation Declaration.pdf3 May 2025
Source of funds With supporting documentFile: 2 Source of funds With supporting document.pdf3 May 2025
Query 2 AnswersFile: Query 2 Answers.pdf3 May 2025
Revenue from Operation -Not related to this projectFile: 1 Revenue from Operation -Not related to this project.pdf11 Apr 2025
Source of Fund With supporting DocumentFile: 2 Source of Fund With supporting Document.pdf11 Apr 2025
Approval Building PlanFile: 3 Approval Building Plan.pdf11 Apr 2025
Query 1File: Query 1.pdf11 Apr 2025
RTC, survey 99/3/1-
Mutation, survey 99/3/1-
Encumbrance Certificate, survey 99/3/1-
Conversion/Alienation Order, survey 99/3/1-
JDA, survey 99/3/1-
Khatha, survey 99/3/1-
Registration CertificateFile: Certificate of Incorporation.pdf-
Memorandum of AssociationFile: Company MOA.pdf-
Article of AssociationFile: Company AOA.pdf-
GST CertificateFile: Company GST Certificate.pdf-
Organization StructureFile: Organization Structure.pdf-
Certificate issued by CA Form 1File: From 1 CA Certificate.pdf-
Certificate issued by Architect Form 2File: Form 2 Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Form 3 Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non litigation notarized affidavit.pdf-
Balance Sheet 2023 - 2024File: Balance sheet 2023-2024.pdf-
Balance Sheet 2022 - 2023File: Balance Sheet 2022-2023.pdf-
Balance Sheet 2021 - 2022File: Balance sheet 21-22.pdf-
Audited Profit and Loss Statement 2023 - 2024File: Profit & Loss 2023 2024.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Profit & Loss 2022-2023.pdf-
Audited Profit and Loss Statement 2021 - 2022File: Profit & Loss 2021-2022.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: ITR 2023 2024.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ITR 2022 2023.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITR 2021-2022.pdf-
Director's Report 2023 - 2024File: Directors Report 2324.pdf-
Director's Report 2022 - 2023File: Directors Report 2022-2023.pdf-
Director's Report 2021 - 2022File: Director Report 2122.pdf-
Cash Flow Statement 2023 - 2024File: Cash flow sttement 2324.pdf-
Cash Flow Statement 2022 - 2023File: Cash flow sttement 2223.pdf-
Auditor's Report 2023 - 2024File: Auditors report 2324.pdf-
Auditor's Report 2022 - 2023File: Auditors report 2223.pdf-
Auditor's Report 2021 - 2022File: Auditors report 2122.pdf-
Approval Letter-
Approval Building Plan-
82-Sectional drawing of the Apartmrnts-

How this compares with Dharwad

25%of this project is bookeddistrict median 38%
29%of Dharwad projects moved their completion datethis one has not
0%of Dharwad registrations are shown as withdrawn or revokedthis one is not

Computed across the 250+ Dharwad projects on ReraGenie, from their own filings.

Keep SHREYA SERENITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dharwad250+ in Dharwad

2 kmSHREYA SERENITYOther 20Dot size: filed unitsN

Filed coordinates, straight-line distance. 20 registered projects within 2 km.

Builder: SHRIYA HOLDINGS & PROPERTIES PRIVATE LIMITED

SHRIYA HOLDINGS & PROPERTIES PRIVATE LIMITED has 1 registration on RERA Karnataka, including SHREYA SERENITY. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dharwad district page.

Frequently asked questions

What are my rights if SHREYA SERENITY is delayed beyond 15 Jan 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SHREYA SERENITY?

The registered promoter entity is SHRIYA HOLDINGS & PROPERTIES PRIVATE LIMITED, a company as per the filing. Its CIN U45309KA2019PTC130176 and GSTIN 29ABCCS9963L1ZF can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SHREYA SERENITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHREYA SERENITY?

The professionals named in the filing: Architect: Bakul Bindumadhav Joshi; Engineer: Ashok Associates; Chartered Accountant: Santoshkumar Patil. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREYA SERENITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREYA SERENITY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREYA SERENITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.