Home / Browse projects / Dharwad, Karnataka / ONE HUBLI PHASE-1

Registration approved Mixed Development project

ONE HUBLI PHASE-1

By SHETTY-PATIL DEVELOPERS LLP

RG-KA-29106 · RERA PRM/KA/RERA/1259/410/PR/180329/001132 · Last updated on RERA Karnataka portal: 28 Mar 2022

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • No complaints on record
  • Separate project account declared
Dec 2022Possession promisedmoved 21 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 185 documents Report an error

ONE HUBLI PHASE-1 is a Mixed Development project by SHETTY-PATIL DEVELOPERS LLP in Dharwad, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1259/410/PR/180329/001132 on 29 Mar 2018. Possession is promised by 30 Dec 2022. The completion date has moved by 21 months from the original filing.

At a glance

Project

  • NameONE HUBLI PHASE-1
  • TypeMixed Development
  • Location
    • Dharwad
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1259/410/PR/180329/001132
  • ReraGenie IDRG-KA-29106

Builder

  • NameSHETTY-PATIL DEVELOPERS LLP
  • Entity typeOther
  • Authorized SignatorySharatKumar B. Shetty
  • OthersRenuka patil, Sunilgouda patil, Kamalabai Patil, Chandrakant Baburao Shetty, Sharatkumar Baburao Shetty
  • Other registrations1 more →

Key dates

this monthRegisteredMar 2018First promiseMar 2021Revised toDec 2022

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on29 Mar 2018
  • Promised completion30 Dec 2022
  • Revised completionRevised to 30 Dec 2022 (originally 31 Mar 2021)
  • Buildings1 building record
  • Documents filed185 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ONE HUBLI PHASE 1-----891

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 28 Mar 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)Not applicable
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 28 Mar 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalNoNot applicable
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationYes-
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area18,215 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 91.59 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectA X E S ARCHITECTURAL CONSULTANTS
EngineerD L Kulkarni Associates

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionMar 2021 → Dec 2021

No reason recorded in the filing

EX/PRM/KA/RERA/1259/410/PR/220824/001132Dec 2021 → Dec 2022

Reason as filed by the promoterShortage of Building Materials, Concrete, Jalli etc

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed185

As listed on the registration, under the names the promoter filed them with; the newest 80 of 185 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1259/410/PR/180329/001132 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
STP DRAWINGFile: STP Drawings 1 (2).pdf28 Mar 2022
AFFIDAVIT FOR COMPENSATIONFile: Affidavit Declaration for compensation 1-converted-compressed.pdf28 Mar 2022
FORM EX 7File: FORM EX-7 AFFIDAVIT 1-converted.pdf28 Mar 2022
HESCOM NOCFile: PDF OF HESCOM NOC.pdf28 Mar 2022
STABILITY CERTIFICATEFile: Stability Certificate latest.jpeg28 Mar 2022
CONSENT LETTER -ALLOTEESFile: concent letter customers (4)-1-40.pdf28 Mar 2022
CONSENT LETTER -ALLOTEESFile: concent letter customers (4)-41-90 (1).pdf28 Mar 2022
CONSENT LETTER -ALLOTEESFile: concent letter customers (4)-91-136.pdf28 Mar 2022
AFFIDAVITFile: Affidavit.jpg29 Jan 2022
AIRPORT NOCFile: Airport Noc.pdf29 Jan 2022
ARCHITECT CERTIFICATEFile: Architect pending work.jpeg29 Jan 2022
ARCHITECT CERTIFICATEFile: Architect Status of work.jpeg29 Jan 2022
ENGINEER CERTIFICATEFile: Engineer Pending work.jpeg29 Jan 2022
ENGINEER CERTIFICATEFile: Engineer status of work.jpg29 Jan 2022
FORM BFile: Form B.pdf29 Jan 2022
SALE DEED PERFORMAFile: SALE DEED (6).pdf29 Jan 2022
STABILITY CERTIFICATEFile: STABILITY CERTIFICATE.jpeg29 Jan 2022
BASEMENT PLANFile: BASMENT-1.pdf29 Jan 2022
BASEMENT PLANFile: BASMENT-2.pdf29 Jan 2022
GROUND FLOOR PLANFile: GROUND FLOOR.pdf29 Jan 2022
FIRTS FLOOR PLANFile: FIRST FLOOR.pdf29 Jan 2022
SECOND FLOOR PLANFile: SECOND FLOOR.pdf29 Jan 2022
THIRD FLOOR PLANFile: THIRD FLOOR.pdf29 Jan 2022
FOURTH FLOOR PLANFile: FOURTH FLOOR.pdf29 Jan 2022
FIFTH FLOOR PLANFile: FIFTH FLOOR.pdf29 Jan 2022
SIXTH FLOOR PLANFile: SIXTH FLOOR.pdf29 Jan 2022
SEVENTH FLOOR PLANFile: SEVENTH FLOOR.pdf29 Jan 2022
EIGHT FLOOR PLANFile: EIGHT FLOOR.pdf29 Jan 2022
NINTH FLOOR PLANFile: NINGTH FLOOR.pdf29 Jan 2022
TENTH FLOOR PLANFile: 10 th floor.pdf29 Jan 2022
Fire NOCFile: Fire NOC.pdf16 Sep 2021
KSPCB NOCFile: KSPCB NOC.pdf16 Sep 2021
Water NOCFile: Water Supply Noc.pdf16 Sep 2021
BASMENT 1File: BASMENT-1.pdf16 Sep 2021
BASMENT 2File: BASMENT-2.pdf16 Sep 2021
GROUND FLOORFile: GROUND FLOOR.pdf16 Sep 2021
FIRST FLOORFile: FIRST FLOOR.pdf16 Sep 2021
SECOND FLOORFile: SECOND FLOOR.pdf16 Sep 2021
THIRD FLOORFile: THIRD FLOOR.pdf16 Sep 2021
FOURTH FLOORFile: FOURTH FLOOR.pdf16 Sep 2021
FIFTH FLOORFile: FIFTH FLOOR.pdf16 Sep 2021
SIXTH FLOORFile: SIXTH FLOOR.pdf16 Sep 2021
SEVENTH FLOORFile: SEVENTH FLOOR.pdf16 Sep 2021
EIGHT FLOORFile: EIGHT FLOOR.pdf16 Sep 2021
NINTH FLOORFile: NINGTH FLOOR.pdf16 Sep 2021
TENTH FLOORFile: 10 FLOOR.pdf16 Sep 2021
ELEVATIONFile: ELEVATION SECTION.pdf16 Sep 2021
TARRACEFile: TARRACE FLOOR.pdf16 Sep 2021
SITE PLANFile: Site PLAN.pdf16 Sep 2021
Demarcation PlanFile: Demarcation Plan.pdf4 Sep 2021
BASMENTFile: BASMENT-1.pdf4 Sep 2021
BASMENTFile: BASMENT-2.pdf4 Sep 2021
FIRST FLOORFile: FIRST FLOOR.pdf4 Sep 2021
SECOND FLOORFile: SECOND FLOOR.pdf4 Sep 2021
THIRD FLOORFile: THIRD FLOOR.pdf4 Sep 2021
FOURTH FLOORFile: FOURTH FLOOR.pdf4 Sep 2021
FIFTH FLOORFile: FIFTH FLOOR.pdf4 Sep 2021
SIXTH FLOORFile: SIXTH FLOOR.pdf4 Sep 2021
SEVENTH FLOORFile: SEVENTH FLOOR.pdf4 Sep 2021
EIGHT FLOORFile: EIGHT FLOOR.pdf4 Sep 2021
NINTH FLOORFile: NINGTH FLOOR.pdf4 Sep 2021
TENTH FLOORFile: 10 th floor.pdf4 Sep 2021
ELEVATION SECTIONFile: ELEVATION SECTION.pdf4 Sep 2021
CLARIFICATION for ModificationFile: Clarification Regarding Modification.pdf4 Sep 2021
Mixed to Commercial ExplanationFile: Mixed to Commercial.pdf26 Aug 2021
Consent Letters Obtained ListFile: Consent Letters.pdf26 Aug 2021
Ground Floor Customers Consent LettersFile: Ground Floor concent letter.pdf26 Aug 2021
First Floor Customers Consent LettersFile: First Floor Consent Letters.pdf26 Aug 2021
Second Floor Customers Consent LettersFile: second floor concent letter.pdf26 Aug 2021
Third Floor Customer Consent LettersFile: Third Floor concent letters.pdf26 Aug 2021
Cancellation Deed with ExplanationFile: Cancelation Deeds.pdf26 Aug 2021
CA CERTIFICATEFile: Ca certificate for modification paln.pdf26 Aug 2021
CA CERTIFICATEFile: CA CERTIFICATE.pdf28 Apr 2021
CANCELATION DEEDFile: CANCELATION DEED 1.pdf28 Apr 2021
CANCELATION DEEDFile: CANCELATION DEED 2.pdf28 Apr 2021
CANCELATION DEEDFile: CANCELATION DEED.pdf28 Apr 2021
DeclarationFile: Declaration.pdf27 Feb 2021
CA CERTIFICATEFile: CA CERTIFICATE.pdf27 Feb 2021
Building PermissionFile: Building Permision.pdf27 Feb 2021
Bank StatementFile: bank Statment.jpg17 Dec 2020

How this compares with Dharwad

29%of Dharwad projects moved their completion datethis one moved by 21 months
0%of Dharwad registrations are shown as withdrawn or revokedthis one is not

Computed across the 250+ Dharwad projects on ReraGenie, from their own filings.

Keep ONE HUBLI PHASE-1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dharwad250+ in Dharwad

Builder: SHETTY-PATIL DEVELOPERS LLP

SHETTY-PATIL DEVELOPERS LLP has 2 registrations on RERA Karnataka, including ONE HUBLI PHASE-1 and MY HOME. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dharwad district page.

Frequently asked questions

What are my rights if ONE HUBLI PHASE-1 is delayed beyond 30 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ONE HUBLI PHASE-1?

The registered promoter entity is SHETTY-PATIL DEVELOPERS LLP. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ONE HUBLI PHASE-1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ONE HUBLI PHASE-1?

The professionals named in the filing: Architect: A X E S ARCHITECTURAL CONSULTANTS; Engineer: D L Kulkarni Associates. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ONE HUBLI PHASE-1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ONE HUBLI PHASE-1. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ONE HUBLI PHASE-1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.