SHREE RANG REVAA
RG-GJ-23974 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RAA17575/071126/311228 · Last updated on GujRERA portal: 7 Nov 2026
Source: official GujRERA filing
Red flags
- Loan reported on the project, Rs 0.83 crore still to repay, in favour of UNSECURED LOAN
Clear
- Completion date never moved
1 condition is on this record. The buyer report sets each one beside the rest of this filing and the projects around it.
See what the report covers Free either way: .Saved.
SHREE RANG REVAA is a Residential/Group Housing project by SHREE RANG DEVELOPERS in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RAA17575/071126/311228 on 7 Nov 2026. Possession is promised by 31 Dec 2028. 0 of the 12 units on this registration are recorded sold or booked, and 23 of 108 construction stages are filed complete.
At a glance
Project
- NameSHREE RANG REVAA
- TypeResidential/Group Housing
- Location
- SURVEY NO. 1077/1
- PETHAPUR
- GANDHINAGAR
- SURVEY NO. 1077/1
- PETHAPUR
- GANDHINAGAR
- PETHAPUR
- Gandhinagar
- 382610
- Pincode382610
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RAA17575/071126/311228
- ReraGenie IDRG-GJ-23974
Builder
- NameSHREE RANG DEVELOPERS
- Entity typePARTNERSHIP FIRM
- Other registrations3 more →
Key dates
Key facts
Registration and timeline
- StatusValid until 31 Dec 2028
- Registered on7 Nov 2026
- Promised completion31 Dec 2028
- Revised completionNone
- Buildings12 building records
- Documents filed49 files
Current status
Figures as on 7 Nov 2026, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| RESIDENTIAL UNIT 6 | - | - | - | 1 | 0 | 1 |
| RESIDENTIAL UNIT 7 | - | - | - | 1 | 0 | 1 |
| RESIDENTIAL UNIT 8 | - | - | - | 1 | 0 | 1 |
| RESIDENTIAL UNIT 9 | - | - | - | 1 | 0 | 1 |
| RESIDENTIAL UNIT 10 | - | - | - | 1 | 0 | 1 |
| RESIDENTIAL UNIT 11 | - | - | - | 1 | 0 | 1 |
| RESIDENTIAL UNIT 12 | - | - | - | 1 | 0 | 1 |
| RESIDENTIAL UNIT 1 | - | - | - | 1 | 0 | 1 |
| RESIDENTIAL UNIT 2 | - | - | - | 1 | 0 | 1 |
| RESIDENTIAL UNIT 3 | - | - | - | 1 | 0 | 1 |
| RESIDENTIAL UNIT 4 | - | - | - | 1 | 0 | 1 |
| RESIDENTIAL UNIT 5 | - | - | - | 1 | 0 | 1 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building12
As on 7 Nov 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
23 of 108 construction stages are filed complete across 12 buildings. The stage furthest along is Plinth, at 50%.
RESIDENTIAL UNIT 624%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 20% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
RESIDENTIAL UNIT 723%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 10% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
RESIDENTIAL UNIT 817%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 50% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
RESIDENTIAL UNIT 922%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
RESIDENTIAL UNIT 1023%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 5% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
RESIDENTIAL UNIT 1123%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 5% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
RESIDENTIAL UNIT 1223%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 10% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
RESIDENTIAL UNIT 122%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
RESIDENTIAL UNIT 225%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 25% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
RESIDENTIAL UNIT 325%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 25% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
RESIDENTIAL UNIT 423%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 10% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
RESIDENTIAL UNIT 524%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 20% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 0% |
| Sanitary fittings within the flats | 0% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 0% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 0% |
Progress on shared amenities19
As on 7 Nov 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 0% |
| Water supply | Yes | 0% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 0% |
| Storm water drains | Yes | 0% |
| Landscaping and tree planting | Yes | 0% |
| Street lighting | Yes | 0% |
| Community buildings | Yes | 0% |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | Yes | 0% |
| Water conservation, rain water harvesting | Yes | 0% |
| Energy management | Yes | 0% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Fire fighting | No | Not applicable |
| Drinking water facilities | No | Not applicable |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | Yes | 0% |
| Security | Yes | 0% |
| Letter box | Yes | 0% |
Land and ownership
A loan secured on the project is a charge your unit may carry until it is released. Ask the promoter for the lender's no-objection certificate for your unit before you pay any amount. This is the accountant's Form 3, not a title search.
| Lender, as filed | Loan taken | Repaid | Balance | Units mortgaged |
|---|---|---|---|---|
| UNSECURED LOAN | Rs 83.45 lakh | Nil | Rs 83.45 lakh | None |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| RESIDENTIAL UNIT 1 | NA | Rs 42.00 lakh | Rs 2.50 lakh |
| RESIDENTIAL UNIT 2 | NA | Rs 42.00 lakh | Rs 12.00 lakh |
| RESIDENTIAL UNIT 3 | NA | Rs 42.00 lakh | Rs 12.00 lakh |
| RESIDENTIAL UNIT 4 | NA | Rs 42.00 lakh | Rs 9.00 lakh |
| RESIDENTIAL UNIT 5 | NA | Rs 42.00 lakh | Rs 10.00 lakh |
| RESIDENTIAL UNIT 6 | NA | Rs 42.00 lakh | Rs 10.00 lakh |
| RESIDENTIAL UNIT 7 | NA | Rs 42.00 lakh | Rs 9.00 lakh |
| RESIDENTIAL UNIT 8 | NA | Rs 42.00 lakh | Rs 2.00 lakh |
| RESIDENTIAL UNIT 9 | NA | Rs 42.00 lakh | Rs 2.50 lakh |
| RESIDENTIAL UNIT 10 | NA | Rs 42.00 lakh | Rs 4.00 lakh |
| RESIDENTIAL UNIT 11 | NA | Rs 42.00 lakh | Rs 4.00 lakh |
| RESIDENTIAL UNIT 12 | NA | Rs 42.00 lakh | Rs 5.00 lakh |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Tarul Ghanshyambhai Patel |
| Engineer | BHUMIT SUNILKUMAR SHAH |
Documents filed49
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RAA17575/071126/311228 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| RERA registration certificate | 7 Nov 2026 |
| Architect's certificate (Form 1) | 8 Oct 2026 |
| Engineer's certificate (Form 2) | 8 Oct 2026 |
| Engineer's certificate annexure | 8 Oct 2026 |
| Accountant's certificate (Form 3) | 8 Oct 2026 |
| Site photograph, RESIDENTIAL UNIT 6 | 8 Oct 2026 |
| Site photograph, RESIDENTIAL UNIT 7 | 8 Oct 2026 |
| Site photograph, RESIDENTIAL UNIT 8 | 8 Oct 2026 |
| Site photograph, RESIDENTIAL UNIT 9 | 8 Oct 2026 |
| Site photograph, RESIDENTIAL UNIT 10 | 8 Oct 2026 |
| Site photograph, RESIDENTIAL UNIT 11 | 8 Oct 2026 |
| Site photograph, RESIDENTIAL UNIT 12 | 8 Oct 2026 |
| Site photograph, RESIDENTIAL UNIT 1 | 8 Oct 2026 |
| Site photograph, RESIDENTIAL UNIT 2 | 8 Oct 2026 |
| Site photograph, RESIDENTIAL UNIT 3 | 8 Oct 2026 |
| Site photograph, RESIDENTIAL UNIT 4 | 8 Oct 2026 |
| Site photograph, RESIDENTIAL UNIT 5 | 8 Oct 2026 |
| Proforma agreement for sale | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Drainage affidavit | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Declaration in Form B | - |
| Approved building or plotting plan | - |
| NOCs from authorities | - |
| Title clearance certificate | - |
| Title report | - |
| Property card | - |
| Statutory document | - |
| Other document | - |
| Project photograph | - |
| Proforma sale deed | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Gandhinagar
Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.
Buyer report
Built from this project's GujRERA filing, in plain language.
- 1 condition on this project's record set out, with the clear checks alongside
- Bookings building by building: units sold and booked against units sanctioned, placed against the projects around it
- Construction as filed: the stage checklist and the engineer's cost figures, building by building
- The accountant's Form 3 read beside the rest of the filing, with what to ask about any loan on it
- The parking the promoter filed, covered and open
- Who certified it: the architect and the engineer named on the filing
- Joined against the promoter's other registrations on GujRERA and every project registered within 2 km, which the register never shows together
- What to check before you book, drawn from this filing
Not included: the filed documents themselves (the report lists which are on file and does not read them) and a project watch.
Keep SHREE RANG REVAA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PETHAPUR1,600+ in Gandhinagar
Filed coordinates, straight-line distance. 33 registered projects within 2 km.
ABC INFINITY
ABC BUILDCON
RIVER FLOORA
SHREEJI DEVELOPERS
River Avenue
SHREEJI INFRACON
Panchamrut 3
RAJ INFRA
AKSHAR VANDAN
AKSHAR DEVELOPER
BANSARI GREENCITY 2
R K PATEL & COMPANY
See every Gandhinagar project, with the district possession charts
Builder: SHREE RANG DEVELOPERS
Shree Rang Developers has 4 registrations on GujRERA, including Shree Rang Nagar & Mall and SHREE RANG VATIKA. Read the full track record. See more projects on the Gandhinagar district page.
Frequently asked questions
What are my rights if SHREE RANG REVAA is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of SHREE RANG REVAA?
The registered promoter entity is SHREE RANG DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in SHREE RANG REVAA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SHREE RANG REVAA?
The professionals named in the filing: Architect: Tarul Ghanshyambhai Patel; Engineer: BHUMIT SUNILKUMAR SHAH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHREE RANG REVAA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.