SHIVALAY DUPLEX

By DESTINATION DEVELOPERS

RG-GJ-69977 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA10587/EX1/220926/310727 · Last updated on GujRERA portal: 8 May 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 16 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Jul 2027Possession promisedmoved 16 months from the original
2 of 9Construction stages donefurthest along: Slabs of Super Structure, 85%
17 of 33Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

SHIVALAY DUPLEX is a Residential/Group Housing project by DESTINATION DEVELOPERS in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA10587/EX1/220926/310727 on 24 Aug 2022. Possession is promised by 31 Jul 2027. The completion date has moved by 16 months from the original filing. 16 of the 33 units on this registration are recorded sold or booked, and 2 of 9 construction stages are filed complete.

At a glance

Project

  • NameSHIVALAY DUPLEX
  • TypeResidential/Group Housing
  • Location
    • SHIVALAY DUPLEX
    • BEHIND KAILASHPATI SOCIETY
    • BADIYADEV MANDIR ROAD
    • RANOLI
    • SARGASAN
    • Gandhinagar
    • 382421
  • Pincode382421
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA10587/EX1/220926/310727
  • ReraGenie IDRG-GJ-69977

Builder

  • NameDESTINATION DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredAug 2022First promiseMar 2026Revised toJul 2027

Key facts

Registration and timeline

  • StatusValid until 31 Jul 2027
  • Registered on24 Aug 2022
  • Promised completion31 Jul 2027
  • Revised completionRevised to 31 Jul 2027 (originally 31 Mar 2026)
  • Buildings1 building record
  • Documents filed41 files

Current status

48%16 of 33 units booked
81.2%Of the estimated cost spent so far

Figures as on 8 May 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DUPLEX NO 1 TO 33---33033

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 8 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 9 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 85%.

DUPLEX NO 1 TO 33: 72% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure85%
Internal walls, internal plaster, floorings, doors and windows within flats80%
Sanitary fittings within the flats70%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing80%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing52%

Progress on shared amenities19

As on 8 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,492 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 4.00 cr
Cost incurredRs 3.25 cr
Spent of the estimate81.22%
BuildingWingEstimatedIncurred
DUPLEX NO 1 TO 33NARs 4.00 crRs 3.25 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRITEKSH B PATEL
EngineerMADHUSUDAN PATEL

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/RAA10587/EX1/220926/310727Applied Mar 2026; approved Sep 2026

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA10587/EX1/220926/310727 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)8 May 2026
Architect's certificate (Form 1)2 May 2026
Engineer's certificate (Form 2)2 May 2026
Engineer's certificate annexure2 May 2026
Site photograph, DUPLEX NO 1 TO 332 May 2026
RERA registration certificate24 Aug 2022
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

48%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one moved by 16 months

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep SHIVALAY DUPLEX on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near SARGASAN1,600+ in Gandhinagar

Builder: DESTINATION DEVELOPERS

DESTINATION DEVELOPERS has 1 registration on GujRERA, including SHIVALAY DUPLEX. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if SHIVALAY DUPLEX is delayed beyond 31 Jul 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHIVALAY DUPLEX?

The registered promoter entity is DESTINATION DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHIVALAY DUPLEX?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHIVALAY DUPLEX?

The professionals named in the filing: Architect: RITEKSH B PATEL; Engineer: MADHUSUDAN PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHIVALAY DUPLEX?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHIVALAY DUPLEX. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHIVALAY DUPLEX to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.