Home / Browse projects / Belagavi, Karnataka / Shiv Sadan
Shiv Sadan
By a. Shivkumar M. Wali b. Pushpa M. Wali c. Rajshekhar M. Wali
RG-KA-77831 · RERA PRM/KA/RERA/1249/447/PR/190215/002382
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 9 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
Shiv Sadan is a Commercial project by a. Shivkumar M. Wali b. Pushpa M. Wali c. Rajshekhar M. Wali in Belagavi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1249/447/PR/190215/002382 on 15 Feb 2019. Possession is promised by 31 Oct 2022. The completion date has moved by 9 months from the original filing.
At a glance
Project
- NameShiv Sadan
- TypeCommercial
- Location
- Belagavi
- PincodeNot stated
- RERA no.PRM/KA/RERA/1249/447/PR/190215/002382
- ReraGenie IDRG-KA-77831
Builder
- Namea. Shivkumar M. Wali b. Pushpa M. Wali c. Rajshekhar M. Wali
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on15 Feb 2019
- Promised completion31 Oct 2022
- Revised completionRevised to 31 Oct 2022 (originally 31 Jan 2022)
- Buildings1 building record
- Documents filed39 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHIV SADAN | - | - | - | 0 | 17 | 17 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | Not applicable |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | Not applicable |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | No | Not applicable |
| Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sadashiv G Arbole |
| Engineer | Vijendra Yellappa Patil |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed39
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1249/447/PR/190215/002382 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| shiv sadan approved certificate | - |
| Approved plan | - |
| Approved plan | - |
| Not yet done | - |
| Not yet done | - |
| Sale Deed with English Translation | - |
| Approved plan with comment on area | - |
| Approved plan with comment on area | - |
| Not yet done | - |
| Not yet done | - |
| project specification | - |
| EC WALI | - |
| aff wali | - |
| Khata | - |
| clarification of area with acquisation notice of CCB | - |
| clarification of area with acquisation notice of CCB | - |
| NOC HESCOM | - |
| NOC water Supply | - |
| Approved plan with comment on area | - |
| Approved plan | - |
| Approved plan | - |
| Balance Sheet 2017 - 2018File: balance sheet 2018-19.pdf | - |
| Balance Sheet 2016 - 2017File: balance sheet 2017-18.pdf | - |
| Balance Sheet 2015 - 2016File: balance sheet 2016-17.pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: P & L 2018-19.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: P & L 2017-18.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: P & L 2016-17.pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: IT 2018-19.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: IT 2017-18.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: IT 2016-17.pdf | - |
| declaration wali | - |
| Prospectus/BrochureFile: No Broucher.pdf | - |
| Advertisement Copy 1File: No ad.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1249_447_PR_190215_002382.xlsx | - |
| Loan raised documentFile: samarth_compressed.pdf | - |
| Occupancy CertificateFile: Completion Certificate - Shiv Sadan.pdf | - |
| Architect certificate for having completed the work(in format no 5)File: 2022-23 Q2 architect.pdf | - |
| Chartered Accountant certificate for having completed the work(in format no 4)File: Form 4 CC (2).pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Completion affidavit.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Belagavi
Computed across the 460+ Belagavi projects on ReraGenie, from their own filings.
Keep Shiv Sadan on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Belagavi460+ in Belagavi
Swarna Griha - 4 Phase 1
Felicity Adobe LLP
SkyCity Homes
M/s. Vishal Infra Built Ltd.
Shree Sant Babamaharaj Complex
Ratuja Developers
Pinnacle
Lotus Landmakrs (I) Pvt Ltd
JYOTICHANDRA
G P DEVELOPERS
SHIVNERI Apartment
SHIVNERI CONSTRUCTIONS
See every Belagavi project, with the district possession charts
Builder: a. Shivkumar M. Wali b. Pushpa M. Wali c. Rajshekhar M. Wali
a. Shivkumar M. Wali b. Pushpa M. Wali c. Rajshekhar M. Wali has 1 registration on RERA Karnataka, including Shiv Sadan. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Belagavi district page.
Frequently asked questions
What are my rights if Shiv Sadan is delayed beyond 31 Oct 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Shiv Sadan?
The registered promoter entity is a. Shivkumar M. Wali b. Pushpa M. Wali c. Rajshekhar M. Wali. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Shiv Sadan?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Shiv Sadan?
The professionals named in the filing: Architect: Sadashiv G Arbole; Engineer: Vijendra Yellappa Patil. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Shiv Sadan?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback