Home / Browse projects / Kalaburagi, Karnataka / SHARANARA ASHIRWAD APARTMENT
SHARANARA ASHIRWAD APARTMENT
RG-KA-23165 · RERA PRM/KA/RERA/1263/419/PR/230223/005750 · Last updated on RERA Karnataka portal: 2 Feb 2023
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 10 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
Saved.
SHARANARA ASHIRWAD APARTMENT is a Residential/Group Housing project by LINGARAJ BASAWARAJ APPA in Kalaburagi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1263/419/PR/230223/005750 on 23 Feb 2023. Possession is promised by 30 Jun 2024. The completion date has moved by 10 months from the original filing.
At a glance
Project
- NameSHARANARA ASHIRWAD APARTMENT
- TypeResidential/Group Housing
- Location
- Kalaburagi
- 585102
- Pincode585102
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1263/419/PR/230223/005750
- ReraGenie IDRG-KA-23165
Builder
- NameLINGARAJ BASAWARAJ APPA
- Entity typeOther ( PROPRIETORSHIP )
- GSTIN29ABGPA4427L1ZL
- Authorized SignatoryLINGARAJ BASAWARAJ APPA
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on23 Feb 2023
- Promised completion30 Jun 2024
- Revised completionRevised to 30 Jun 2024 (originally 31 Aug 2023)
- Buildings1 building record
- Documents filed116 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHARANARA ASHIRWAD APARTMENT | - | - | - | 8 | 0 | 8 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 2 Feb 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Upto Plinth Level | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| Retaining wall (All types) | - |
| RCC or MS Framed structure | - |
| Masonry Construction | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Painting | - |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | - |
| Internal and External work including landscapes as per sanctioned drawings | Not applicable |
Progress on shared amenities32
As on 2 Feb 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Sewage and Drainage System | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | - |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | No | Not applicable |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Corridor/Lobbies | No | Not applicable |
| Fire escapes | Yes | - |
Land and ownership2
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SRI LINGARAJ s/o BASAWARAJ APPA | - | - |
| LINGARAJ BASAWARAJ APPA | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 2.90 cr | - |
| Principal sum and interest payable to financial institutions-Scheduled Banks | Rs 54.00 lakh | - |
| ADMINISTRATIVE COSTS | Rs 8.00 lakh | - |
| On-site expenditure-Consultants Fees | Rs 2.00 lakh | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SHREY MALHAR RAO |
| Engineer | RAMESH DHULAPPA |
| Chartered Accountant | SHRISHAIL VEERANNA MANTGOL |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterothers
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed116
As listed on the registration, under the names the promoter filed them with; the newest 80 of 116 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1263/419/PR/230223/005750 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| FORM B OF RERA AFFADAVIT CUM DECLARTION WITH REVISED DATE IN POINT NO. 3File: AFFADAVIT CUM DECLARTION LATEST.pdf | 2 Feb 2023 |
| CA CERTFICATEFile: FORM 1 CA_compressed.pdf | 26 Dec 2022 |
| ENGINEER VALUTION REPORTFile: ENGINEER VALUATION REPORT BY RAMESH.pdf | 26 Dec 2022 |
| FORM B OF RERA, REVISEDFile: Affadavit Cum Declartion 3_compressed.pdf | 26 Dec 2022 |
| ENGINEER ESTIMATION AND VALUATION CERTIFICATEFile: Lingraj appa valuation report 12 (1).pdf | 9 Oct 2022 |
| ENGINEER CONSTRUCTION ESTIMATION CERTIFICATEFile: 22 MELKUNDI SIR PROJECT COST ESTIMATION.pdf | 9 Oct 2022 |
| CA CERTIFICATE AS PER RERA FORMATFile: FORM 1 CA.pdf | 9 Oct 2022 |
| FORM B IN RERA FORMAT MENTIONED WITH COMPLETION DATE IN PAGE 2, 11TH POINTFile: AFFADAVIT CUM DECLARTION RECT.pdf | 9 Oct 2022 |
| LBPAS APPROVED PLAN ALONG WITH NAME AND ADDRESSFile: LBPAS PLAN (2).pdf | 9 Oct 2022 |
| CA CERTIFICATEFile: FORM 1 CA.pdf | 14 Sep 2022 |
| ENGINEER VALUATION REPORTFile: Lingraj appadocx.pdf | 14 Sep 2022 |
| FORM B RECTIFIED AS PER NEW QUERYFile: AFFADAVIT CUM DECLARTION RECT.pdf | 14 Sep 2022 |
| DETAILED LEGAL SEARCH REPORTEDFile: LSR.pdf | 14 Sep 2022 |
| APPROVED DRAWING PDF FILE FOR BETTER VIEWING AND CLEAR VISIBLITY OF VALUESFile: 17 PERMISSION PLAN LAYOUT BY SB.pdf | 14 Sep 2022 |
| FORM1 CAFile: FORM 1 CA.pdf | 20 Aug 2022 |
| AUDIT REPORT FY 2018-19File: LBA AR 19-20.pdf | 20 Aug 2022 |
| AUDIT REPORT FY 2019-20File: LBA AR 20-21.pdf | 20 Aug 2022 |
| AUDIT REPORT FY 2020-21File: LBA AR 21-22.pdf | 20 Aug 2022 |
| KALABURAGI CDP MAPFile: CDP MAP .pdf | 20 Aug 2022 |
| BHRAMPUR VILLAGE MAPFile: VILLAGE MAP RERA.pdf | 20 Aug 2022 |
| LSRFile: LSR BY SHIVEELA.pdf | 20 Aug 2022 |
| FORM B OF RERAFile: SECTION 3 (1) RERA.pdf | 20 Aug 2022 |
| NON LITIGATATION AFFADAVITFile: NON LITIGATION AFFADAVIT.pdf | 20 Aug 2022 |
| COMMENCEMENT CERTIFICATE ACKNOWLDEGMENTFile: CMC COMMENCEMENT CERTF ACK.pdf | 20 Aug 2022 |
| GODUTAI NAGAR LAYOUT MAP SYNO 102 & 103File: 102 AND 103 MAP GODUTAI NAGAR.pdf | 20 Aug 2022 |
| SURVEY NO 102 NA ORDER COPYFile: SY 102 ORDER COPY.pdf | 20 Aug 2022 |
| SURVEY NO 102 OF BHRAMPUR LAYOUT MAPFile: SY NO 102 LAYOUT MAP.pdf | 20 Aug 2022 |
| SURVEY NO 102 RORFile: SY 102 ROR.pdf | 20 Aug 2022 |
| SURVEY NO 103 LAYOUT MAP WITH DEMARCATION OF PLOT NO 7 & 8 OF PROPOSED SITEFile: Syno103 Layout And plot demarcation .pdf | 20 Aug 2022 |
| PLOT NO 7 & 8, AMELGAMATION OF PLOTSFile: 12 Amalgamation.pdf | 20 Aug 2022 |
| PROJECT PLAN WITH ADDRESSFile: PLAN .pdf | 20 Aug 2022 |
| CDP MAP OF VILLAGE AND DEMARCATIONFile: CDP MAP KLBG-merged_compressed.pdf | 30 Jul 2022 |
| FORM BFile: AFFADAVIT AND DECLARATION.pdf | 30 Jul 2022 |
| RTC RECENTFile: BHOOMI SY 103.pdf | 30 Jul 2022 |
| MUTATION REPORT MRFile: 6 KHATA 13-14-pages-1.pdf | 30 Jul 2022 |
| KHATA OF 2022-23File: 6 KHATA 2022.pdf | 30 Jul 2022 |
| TITLE DEED OF DR MALLINATH KOLOLGIFile: 1st deed.pdf | 30 Jul 2022 |
| LAYOUT PLAN OF 103File: 4 LAYOUT PLAN MAP.pdf | 30 Jul 2022 |
| LAYOUT PLAN OF 102 AND 103 COMBINED BELONING TO ONE OWNER ( BASAWARAJ DODDAPPA APPA)File: LAYOUT OF 102 & 103.pdf | 30 Jul 2022 |
| GUIDANCE VALUE OBTAINED BY SUB REGISTRARFile: SUB REGISTRAR VALUE.pdf | 30 Jul 2022 |
| NON LITIGATATION AFFADAVITFile: ANNEX 45 NON LIT AFFADAVIT.pdf | 30 Jul 2022 |
| SECTION 3 (1) AFFADAVITFile: SECTION 3(1).pdf | 30 Jul 2022 |
| LBPAS APPROVED ACKNOWLEGEMENT AND COMMENCEMENT CERTIFICIATEFile: 18 APPROVED PLAN ACK.pdf | 30 Jul 2022 |
| RTC FROM 1963-64 TO 2021-22File: RTC.pdf | 30 Jul 2022 |
| SOAK PIT, SEPTIC TANK AND SEWER LINE PROJECTIONFile: PIT DESGIN.pdf | 30 Jul 2022 |
| REVISED AGREEMENT FOR SALEFile: AOS FINAL.pdf | 30 Jul 2022 |
| APPROVED PLAN SIGNED COPYFile: PLAN SIGN COPY.pdf | 30 Jul 2022 |
| ALLOTMENT LETTERFile: allotement letter.pdf | 30 Jul 2022 |
| RTC, survey 103 | - |
| Mutation, survey 103 | - |
| Encumbrance Certificate, survey 103 | - |
| Conversion/Alienation Order, survey 103 | - |
| Sale/Title/Gift Deed, survey 103 | - |
| Khatha, survey 103 | - |
| Registration CertificateFile: AA290317096226V_RC08072018.pdf | - |
| Certificate issued by CA Form 1File: FORM 1 CA_compressed.pdf | - |
| Certificate issued by Architect Form 2 | - |
| Certificate issued by Engineer Form 3File: ENGINEER VALUATION REPORT BY RAMESH.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: NON LITIGATION AFFADAVIT.pdf | - |
| Certificate from Chartered AccountFile: FORM 1 CA_compressed.pdf | - |
| Balance Sheet 2020 - 2021File: 21-22 BS.pdf | - |
| Balance Sheet 2019 - 2020File: 20-21 BS.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: 21-22 PL.pdf | - |
| Audited Profit and Loss Statement 2019 - 2020File: 20-21 PL.pdf | - |
| Cash Flow Statement 2020 - 2021File: ic statement 2122.pdf | - |
| Cash Flow Statement 2019 - 2020File: IC STATEMENT 20-21.pdf | - |
| Income Tax Return Acknowledgement 2020 - 2021File: 21-22 ITR.pdf | - |
| Income Tax Return Acknowledgement 2019 - 2020File: 20-21 ITR.pdf | - |
| Income Tax Return Acknowledgement 2018 - 2019File: 19-20 itr-compressed.pdf | - |
| 18 APPROVED PLAN ACK | - |
| 19 GESCOM NOC | - |
| 21 WATER BOARD NOC_compressed | - |
| 4 LAYOUT PLAN MAP | - |
| 17 PERMISSION PLAN LAYOUT BY SB | - |
| 4 LAYOUT PLAN MAP | - |
| sectional plan | - |
| specs | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Kalaburagi
Computed across the 210+ Kalaburagi projects on ReraGenie, from their own filings.
Keep SHARANARA ASHIRWAD APARTMENT on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kalaburagi210+ in Kalaburagi
Filed coordinates, straight-line distance. 24 registered projects within 2 km.
S R Darshanapur Apartments
MOHAMMAD SHAFEEQ UR RAHMAN
PRIME-ELITE
M/S ISHANYA BUILDERS AND DEVELOPERS
Arya
Arya Builders & Developers
S.R. Galaxy Apartments
MOHAMMAD SHAFEEQ UR RAHMAN
S.R. NAJMA TOWER
S R Constructions
S R Pearl
SR Constructions
See every Kalaburagi project, with the district possession charts
Builder: LINGARAJ BASAWARAJ APPA
LINGARAJ BASAWARAJ APPA has 1 registration on RERA Karnataka, including SHARANARA ASHIRWAD APARTMENT. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Kalaburagi district page.
Frequently asked questions
What are my rights if SHARANARA ASHIRWAD APARTMENT is delayed beyond 30 Jun 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SHARANARA ASHIRWAD APARTMENT?
The registered promoter entity is LINGARAJ BASAWARAJ APPA, an other ( proprietorship ) as per the filing. Its GSTIN 29ABGPA4427L1ZL can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SHARANARA ASHIRWAD APARTMENT?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SHARANARA ASHIRWAD APARTMENT?
The professionals named in the filing: Architect: SHREY MALHAR RAO; Engineer: RAMESH DHULAPPA; Chartered Accountant: SHRISHAIL VEERANNA MANTGOL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHARANARA ASHIRWAD APARTMENT?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.