Home / Browse projects / Kalaburagi, Karnataka / S.R. NAJMA TOWER
S.R. NAJMA TOWER
RG-KA-61509 · RERA PRM/KA/RERA/1263/419/PR/060525/007713 · Last updated on RERA Karnataka portal: 7 Feb 2025
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
S.R. NAJMA TOWER is a Commercial project by S R Constructions in Kalaburagi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1263/419/PR/060525/007713 on 6 May 2025. Possession is promised by 12 Jun 2025.
At a glance
Project
- NameS.R. NAJMA TOWER
- TypeCommercial
- Location
- Kalaburagi
- 585102
- Pincode585102
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1263/419/PR/060525/007713
- ReraGenie IDRG-KA-61509
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on6 May 2025
- Promised completion12 Jun 2025
- Revised completionNone
- Buildings1 building record
- Documents filed116 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| S.R. NAJMA TOWER | - | - | - | 0 | 31 | 31 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 7 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Upto Plinth Level | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| Retaining wall (All types) | - |
| RCC or MS Framed structure | - |
| Masonry Construction | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Painting | - |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | - |
| Internal and External work including landscapes as per sanctioned drawings | - |
Progress on shared amenities40
As on 7 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Sewage and Drainage System | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | - |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | Yes | - |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | No | Not applicable |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Piped Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Corridor/Lobbies | No | Not applicable |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | No | Not applicable |
| Basement | Yes | - |
| Terrace | No | Not applicable |
| Outer Wall | No | Not applicable |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| MOHMMED GALIB PASHA | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 3.32 cr | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Siraj Ahmed |
| Engineer | Mohammed Irfan |
| Chartered Accountant | Amogh Srikant Dharwadkar |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed116
As listed on the registration, under the names the promoter filed them with; the newest 80 of 116 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1263/419/PR/060525/007713 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CA CertificateFile: CA Certificate.pdf | 7 Feb 2025 |
| form 1 CAFile: FORM 1 CA.pdf | 20 Jan 2025 |
| Mutation copyFile: Mutation copy.pdf | 20 Jan 2025 |
| Najma begum death certificateFile: Najma Begum - Death Certificate.pdf | 20 Jan 2025 |
| commencement certificateFile: commencement certificate.pdf | 20 Jan 2025 |
| KSPCBFile: KSPCB.pdf | 20 Jan 2025 |
| CDP MAPFile: CDP Map of SR Najma Tower.pdf | 20 Jan 2025 |
| GUIDANCE VALUE CERTIFICATEFile: Land cost calculation sheet as per the guidance va.pdf | 20 Jan 2025 |
| INVENTORY SIGNED BY ENGINEERFile: Inventory Details Signed by Engineer.pdf | 20 Jan 2025 |
| NA ORDER COPYFile: NA ORDER COPY.pdf | 20 Jan 2025 |
| engineer licenseFile: engineer certificate.pdf | 20 Jan 2025 |
| Joint Development NajmaFile: Joint Development NAJMA.pdf | 20 Jan 2025 |
| Declaration for FAR mentionedFile: Declaration for FAR mentioned.pdf | 25 Apr 2024 |
| Self-attested Land cost calculation as per guidance valueFile: Land cost calculation sheet as per the guidance va.pdf | 25 Apr 2024 |
| Water NOC Request letterFile: Waterboard NOC Applied CopySelf Attested (1).pdf | 25 Apr 2024 |
| Latest RTCFile: RTC.pdf | 25 Apr 2024 |
| CA Certificate - FORM-1File: Form-1 CA.pdf | 25 Apr 2024 |
| Mutation RecordFile: Mutation copy.pdf | 25 Apr 2024 |
| Village MapFile: Village Map_001.jpg | 25 Apr 2024 |
| Commencement CertificateFile: Permission copy.pdf | 25 Apr 2024 |
| Structural SafetyFile: SAFETY CERTIFICATE.pdf | 25 Apr 2024 |
| Engineer Certificate- FORM 3File: FORM3.pdf | 25 Apr 2024 |
| Area DetailsFile: Area Details.pdf | 25 Apr 2024 |
| KSPCB CFE NOC DeclarationFile: Declaration for KSPCB CFE NOC.pdf | 25 Apr 2024 |
| STP Drawing DeclarationFile: Declaration for STP Drawing.pdf | 25 Apr 2024 |
| Engineer License CertificateFile: Declaration for Engineer license certificate.pdf | 25 Apr 2024 |
| Declaration for Single plot LayoutFile: Declaration for Single plot layout.pdf | 25 Apr 2024 |
| CDP MapFile: CDP Map of SR Najma Tower.pdf | 25 Apr 2024 |
| AmenitiesFile: ameneties.pdf | 25 Apr 2024 |
| Encumbrance CertificateFile: EC Upto 26-03-2024.pdf | 2 Apr 2024 |
| Latest KhathaFile: Khata.pdf | 2 Apr 2024 |
| Advocate Search ReportFile: Title Report.pdf | 2 Apr 2024 |
| Permission CopyFile: Permission copy.pdf | 2 Apr 2024 |
| Town Planning, Village MapFile: Town Planning, Village Map.pdf | 2 Apr 2024 |
| Premium FAR Copy (Approved Plan)File: Approved Plan.pdf | 2 Apr 2024 |
| GST CertificateFile: SR Construction - GST Copy.pdf | 2 Apr 2024 |
| Financials Combined profit and loss account, balance sheet & ITR, (2021-22, 2022-23 & 2023-24)File: SR Constructions-IT Assessment YEAR 2023-24_compressed.pdf | 2 Apr 2024 |
| Financials Combined profit and loss account, balance sheet & ITR, (2021-22, 2022-23 & 2023-24)File: SR Constructions-IT Assessment YEAR 2022-23_compressed.pdf | 2 Apr 2024 |
| Financials Combined profit and loss account, balance sheet & ITR, (2021-22, 2022-23 & 2023-24)File: SR Constructions-IT Assessment YEAR 2021-22_compressed.pdf | 2 Apr 2024 |
| MutationFile: Mutation copy.pdf | 2 Apr 2024 |
| Declaration for Relinquishment DeedFile: Declaration for Relinquishment Deed.pdf | 2 Apr 2024 |
| Bank Details MergedFile: Bank Merged.pdf | 2 Apr 2024 |
| Bank AffidavitFile: Bank Affidavit.pdf | 2 Apr 2024 |
| CA Registration CertificateFile: CA-Self Attested Registration copy.pdf | 2 Apr 2024 |
| current year RTCFile: SR Najma Towers-RTC.pdf | 2 Apr 2024 |
| Certified Carpet AreaFile: Certified Carpet Area.pdf | 2 Apr 2024 |
| Engineer Certificate- FORM 3File: FORM 3.pdf | 2 Apr 2024 |
| Engineer Registration CertificateFile: Engineer License Self Attested.pdf | 2 Apr 2024 |
| Amenities and Common area detailsFile: Amenities & project details.pdf | 2 Apr 2024 |
| Details of Exclusive Common Area Allottee, Common Area Alloted To Association, Undivided Share and NFile: Inventory Details Signed by Engineer.pdf | 2 Apr 2024 |
| GESCOMFile: GESCOME NOC SELF ATTESTED.pdf | 2 Apr 2024 |
| GESCOM PaymentFile: GESCOME PAYMENT SELF ATTESTED.pdf | 2 Apr 2024 |
| Brief estimated cost of construction certified by the engineerFile: Brief estimated cost of construction.pdf | 2 Apr 2024 |
| Land cost calculation sheet as per the guidance valueFile: Land cost calculation sheet as per the guidance value.pdf | 2 Apr 2024 |
| Project SpecificationsFile: PROJECT SPECIFICATION.pdf | 2 Apr 2024 |
| Chartered accountant certificate in prescribed format form -01 in new formatFile: Form-1 CA.pdf | 2 Apr 2024 |
| Water NOCFile: Waterboard NOC Applied Copy-Self Attested.pdf | 2 Apr 2024 |
| Declaration for FAR mentionedFile: Declaration for FAR mentioned.pdf | 2 Apr 2024 |
| Agreement of Sale Proforma final-S R Najma TowerFile: Agreement of Sale Proforma final-S R Najma Tower.pdf | 2 Apr 2024 |
| Permission LetterFile: Permission copy.pdf | 2 Apr 2024 |
| Permission ReceiptFile: Permission Payment Receipt.pdf | 2 Apr 2024 |
| RTC, survey 73 | - |
| Mutation, survey 73 | - |
| Encumbrance Certificate, survey 73 | - |
| Sale/Title/Gift Deed, survey 73 | - |
| JDA, survey 73 | - |
| Khatha, survey 73 | - |
| Registration CertificateFile: RC.pdf | - |
| GST CertificateFile: SR Construction - GST Copy.pdf | - |
| Partnership DeedFile: SR PARTNERSHIP DEED.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: Form-1 CA.pdf | - |
| Certificate issued by Architect Form 2File: FORM-2 ARCHIETECT CERTIFICATE (PR).pdf | - |
| Certificate issued by Engineer Form 3File: FORM3.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Non-Litigation.pdf | - |
| Certificate from Chartered AccountFile: Form-1 CA.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Kalaburagi
Computed across the 210+ Kalaburagi projects on ReraGenie, from their own filings.
Keep S.R. NAJMA TOWER on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kalaburagi210+ in Kalaburagi
Filed coordinates, straight-line distance. 30 registered projects within 2 km.
S R Darshanapur Apartments
MOHAMMAD SHAFEEQ UR RAHMAN
PRIME-ELITE
M/S ISHANYA BUILDERS AND DEVELOPERS
Arya
Arya Builders & Developers
S.R. Galaxy Apartments
MOHAMMAD SHAFEEQ UR RAHMAN
S R Pearl
SR Constructions
MAGNUM INDRAPRASTA
MAGNUM INITIATIVES
See every Kalaburagi project, with the district possession charts
Builder: S R Constructions
S R Constructions has 5 registrations on RERA Karnataka, including S R APARTMENTS and S.R. NAJMA TOWER. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Kalaburagi district page.
Frequently asked questions
What are my rights if S.R. NAJMA TOWER is delayed beyond 12 Jun 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of S.R. NAJMA TOWER?
The registered promoter entity is S R Constructions, a partnership firm as per the filing. Its GSTIN 29ACCFS2533C1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in S.R. NAJMA TOWER?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at S.R. NAJMA TOWER?
The professionals named in the filing: Architect: Siraj Ahmed; Engineer: Mohammed Irfan; Chartered Accountant: Amogh Srikant Dharwadkar. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in S.R. NAJMA TOWER?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback