Home / Browse projects / Gandhinagar, Gujarat / Shalvik Homes 2

Valid until 31 Dec 2018 Residential/Group Housing project

Shalvik Homes 2

By Aakar Infrastructure

RG-GJ-08092 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA01098/261217 · Last updated on GujRERA portal: 13 Dec 2018

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Dec 2018Possession promisedno revision filed
377 of 377Construction stages doneacross 54 buildings; every applicable stage filed complete
Jump to the 89 documents Report an error

Shalvik Homes 2 is a Residential/Group Housing project by Aakar Infrastructure in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA01098/261217 on 26 Dec 2017. Possession is promised by 31 Dec 2018.

At a glance

Project

  • NameShalvik Homes 2
  • TypeResidential/Group Housing
  • Location
    • Shalik Homes 2
    • Vavol Uvarsad Road Vavol
    • Vavol
    • Gandhinagar
    • 382016
  • Pincode382016
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA01098/261217
  • ReraGenie IDRG-GJ-08092

Builder

  • NameAakar Infrastructure
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredDec 2017PromisedDec 2018

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2018
  • Registered on26 Dec 2017
  • Promised completion31 Dec 2018
  • Revised completionNone
  • Buildings54 building records
  • Documents filed89 files

Current status

100.0%Of the estimated cost spent so far

Figures as on 13 Dec 2018, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A1-----1
B12-----1
D23-----1
C34-----1
E45-----1
A2-----1
B13-----1
D24-----1
C35-----1
E46-----1
A3-----1
B14-----1
D25-----1
E36-----1
E47-----1
A4-----1
B15-----1
D26-----1
E37-----1
E48-----1
A5-----1
C16-----1
D27-----1
E38-----1
E49-----1
A6-----1
C17-----1
D28-----1
E39-----1
E50-----1
A7-----1
C18-----1
D29-----1
E40-----1
E51-----1
A8-----1
C19-----1
C30-----1
E41-----1
E52-----1
B9-----1
C20-----1
C31-----1
E42-----1
E53-----1
B10-----1
C21-----1
C32-----1
E43-----1
E54-----1
B11-----1
D22-----1
C33-----1
E44-----1

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building20

As on 13 Dec 2018, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 54 buildings; the table lists the first 20.

377 of 377 construction stages are filed complete across 54 buildings.

A1100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B12100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D23100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C34100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E45100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A2100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B13100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D24100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
C35100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E46100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A3100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B14100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D25100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E36100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E47100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A4100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B15100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D26100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E37100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
E48100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 13 Dec 2018, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,440 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 8.51 cr
Cost incurredRs 8.51 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
A1NARs 15.76 lakhRs 15.76 lakh
B12NARs 15.76 lakhRs 15.76 lakh
D23NARs 15.76 lakhRs 15.76 lakh
C34NARs 15.76 lakhRs 15.76 lakh
E45NARs 15.76 lakhRs 15.76 lakh
A2NARs 15.76 lakhRs 15.76 lakh
B13NARs 15.76 lakhRs 15.76 lakh
D24NARs 15.76 lakhRs 15.76 lakh
C35NARs 15.76 lakhRs 15.76 lakh
E46NARs 15.76 lakhRs 15.76 lakh
A3NARs 15.76 lakhRs 15.76 lakh
B14NARs 15.76 lakhRs 15.76 lakh

Documents filed89

As listed on the registration, under the names the promoter filed them with; the newest 80 of 89 are shown. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA01098/261217 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)13 Dec 2018
Engineer's certificate (Form 2)13 Dec 2018
Site photograph, A113 Dec 2018
Site photograph, B1213 Dec 2018
Site photograph, D2313 Dec 2018
Site photograph, C3413 Dec 2018
Site photograph, E4513 Dec 2018
Site photograph, A213 Dec 2018
Site photograph, B1313 Dec 2018
Site photograph, D2413 Dec 2018
Site photograph, C3513 Dec 2018
Site photograph, E4613 Dec 2018
Site photograph, A313 Dec 2018
Site photograph, B1413 Dec 2018
Site photograph, D2513 Dec 2018
Site photograph, E3613 Dec 2018
Site photograph, E4713 Dec 2018
Site photograph, A413 Dec 2018
Site photograph, B1513 Dec 2018
Site photograph, D2613 Dec 2018
Site photograph, E3713 Dec 2018
Site photograph, E4813 Dec 2018
Site photograph, A513 Dec 2018
Site photograph, C1613 Dec 2018
Site photograph, D2713 Dec 2018
Site photograph, E3813 Dec 2018
Site photograph, E4913 Dec 2018
Site photograph, A613 Dec 2018
Site photograph, C1713 Dec 2018
Site photograph, D2813 Dec 2018
Site photograph, E3913 Dec 2018
Site photograph, E5013 Dec 2018
Site photograph, A713 Dec 2018
Site photograph, C1813 Dec 2018
Site photograph, D2913 Dec 2018
Site photograph, E4013 Dec 2018
Site photograph, E5113 Dec 2018
Site photograph, A813 Dec 2018
Site photograph, C1913 Dec 2018
Site photograph, C3013 Dec 2018
Site photograph, E4113 Dec 2018
Site photograph, E5213 Dec 2018
Site photograph, B913 Dec 2018
Site photograph, C2013 Dec 2018
Site photograph, C3113 Dec 2018
Site photograph, E4213 Dec 2018
Site photograph, E5313 Dec 2018
Site photograph, B1013 Dec 2018
Site photograph, C2113 Dec 2018
Site photograph, C3213 Dec 2018
Site photograph, E4313 Dec 2018
Site photograph, E5413 Dec 2018
Site photograph, B1113 Dec 2018
Site photograph, D2213 Dec 2018
Site photograph, C3313 Dec 2018
Site photograph, E4413 Dec 2018
RERA registration certificate26 Dec 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-

How this compares with Gandhinagar

16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep Shalvik Homes 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Vavol1,600+ in Gandhinagar

2 kmShalvik Homes 2Other 124Dot size: filed unitsN

Filed coordinates, straight-line distance. 124 registered projects within 2 km.

Builder: Aakar Infrastructure

Aakar Infrastructure has 1 registration on GujRERA, including Shalvik Homes 2. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if Shalvik Homes 2 is delayed beyond 31 Dec 2018?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Shalvik Homes 2?

The registered promoter entity is Aakar Infrastructure, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Shalvik Homes 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in Shalvik Homes 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shalvik Homes 2. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shalvik Homes 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.