Brigade Belvedere
RG-KA-38389 · RERA PRM/KA/RERA/1251/446/PR/240326/008549 · Last updated on RERA Karnataka portal: 15 Oct 2026
Source: official RERA Karnataka filing
Red flags
- Litigation declared, 4 cases
Clear
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Brigade Belvedere is a Residential/Group Housing project by Brigade Enterprises Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/240326/008549 on 24 Mar 2026. Possession is promised by 31 Mar 2031. 320 of the 773 units on this registration are recorded sold or booked, and 0 of 16 construction stages are filed complete.
At a glance
Project
- NameBrigade Belvedere
- TypeResidential/Group Housing
- Location
- Bengaluru East
- Bengaluru Urban
- 560049
- Pincode560049
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/446/PR/240326/008549
- ReraGenie IDRG-KA-38389
Builder
- NameBrigade Enterprises Ltd
- Entity typeCompany
- CINL85110KA1995PLC019126
- GSTIN29AAACB7459F1ZI
- Authorized SignatoryMr. Viswa Prathap Desu
- Managing DirectorPavitra Shankar
- DirectorsMr. M. R. Jaishankar, Ms. Pavitra Shankar, Ms. Nirupa Shankar, Mr. Roshin Mathew, Mr. Amar Mysore, Mr. Pradyumna Krishna Kumar, Ms. Lakshmi Venkatachalam, Mr. Pradeep Kumar Panja, Dr. Venkatesh Panchapagesan, Mr. Velloor Venkatakrishnan Ranganathan, Mr. Abraham Stephanos, Ms. Padmaja Chunduru
- Project HeadManjunatha Prasad
- Other registrations45 more →
- No longer live1 withdrawn or revoked
- Declared earlier projects67 →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on24 Mar 2026
- Promised completion31 Mar 2031
- Revised completionNone
- Buildings2 building records
- Documents filed149 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Tower A | - | - | - | 428 | 0 | 428 |
| Tower B | - | - | - | 345 | 0 | 345 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 16 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 95%.
Building: 6% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 95% |
| Foundation footing work | 0% |
| Upto Plinth Level | 0% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 0% |
| Retaining wall (All types) | Not applicable |
| RCC or MS Framed structure | 0% |
| Masonry Construction | 0% |
| Plastering inside , outside & Ceiling | 0% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | 0% |
| Weather Proof work(tile,concrete) | 0% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | Not applicable |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Solid waste management and disposal | Yes | 0% |
| Emergency Evacuation services | Yes | 0% |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | Yes | 0% |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | Yes | 0% |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 0% |
| Lifts | Yes | 0% |
| Corridor/Lobbies | Yes | 0% |
| Fire escapes | Yes | 0% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 0% |
| Basement | Yes | 0% |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 0% |
| Open parking areas | Yes | 0% |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | 0% |
| Common storage spaces | No | Not applicable |
Land and ownership5
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| M/s. TULIP ENTERPRISES | - | - |
| M/s. TULIP ENTERPRISES | - | - |
| M/s. TULIP ENTERPRISES | - | - |
| M/s. TULIP ENTERPRISE | - | - |
| M/s. TULIP ENTERPRISES | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 488.47 cr | Rs 6.38 cr |
| On-site expenditure-Site Overhead | Rs 27.30 cr | - |
| Principal sum and interest payable to financial institutions-Scheduled Banks | Rs 15.53 cr | Rs 3.41 cr |
| On-site expenditure-Salaries of workers | Rs 1.18 cr | - |
| On-site expenditure-Consultants Fees | Rs 47.40 lakh | - |
| Payment of taxes | Rs 31.64 lakh | - |
| Payment of Premiums | Rs 2.05 lakh | - |
| Payment of cess | Rs 1.81 lakh | - |
Certifying professionals and partners4
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Paul Manoharan Moses |
| Engineer | RENUKA PRASAD H N |
| Engineer | Balasubramanian M N |
| Chartered Accountant | R. Srinivasan |
Litigation declared4
| Case | Court | Status |
|---|---|---|
| 662 | Sr. Civil & Sessions Judge and JMFC, Bangalore Rural Dist. | - |
| 23614 | High Court of Karnataka | - |
| 2572 | High Court of Karnataka | - |
| 1760 | Senior Civil Judge Bangalore Rural District | - |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed149
As listed on the registration, under the names the promoter filed them with; the newest 80 of 149 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/240326/008549 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Brigade Belvedere - Form 4 - Q2.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Brigade Belvedere - Form 5 - Q2.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Brigade Belvadere - Form 6 - Q2.pdf | 15 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 15 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Oct 2026 |
| Q2 2026-27 KSPCB- MOEF (Above 50 Acres) | 15 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 15 Oct 2026 |
| Q2 2026-27 Fire and Safety | 15 Oct 2026 |
| Q2 2026-27 Airport Authority of India | 15 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Brigade Belvedere - Form 4 - Q1.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Brigade Belvedere - Form 5 - Q1.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Brigade Belvedere - Form 6 - Q1.pdf | 15 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 15 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Jul 2026 |
| Q1 2026-27 KSPCB- MOEF (Above 50 Acres) | 15 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 15 Jul 2026 |
| Q1 2026-27 Fire and Safety | 15 Jul 2026 |
| Q1 2026-27 Airport Authority of India | 15 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Brigade Belvedere - Form 4 - Q4.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Brigade Belvedere - Form 5 - Q4.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Brigade Belvedere - Form 6 - Q4.pdf | 15 Apr 2026 |
| Q4 2025-26 Water supply and sewage board | 15 Apr 2026 |
| Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 15 Apr 2026 |
| Q4 2025-26 KSPCB- MOEF (Above 50 Acres) | 15 Apr 2026 |
| Q4 2025-26 KPTCL- BESCOM | 15 Apr 2026 |
| Q4 2025-26 Fire and Safety | 15 Apr 2026 |
| Q4 2025-26 Airport Authority of India | 15 Apr 2026 |
| ADLR SketchFile: ADLR Sketch.pdf | 24 Mar 2026 |
| CLU OrderFile: Brigade Belvedere - CLU Order.pdf | 24 Mar 2026 |
| Amenities DetailsFile: Amenities Details.pdf | 24 Mar 2026 |
| Encumbrance CertificateFile: Brigade Belvedere - Encumbrance Certificate.pdf | 24 Mar 2026 |
| Agreement to SellFile: Agreement for Sale - Brigade Belvedere - for RERA.pdf | 24 Mar 2026 |
| Reply to the QueriesFile: Brigade Belvedere - Reply to the Queries.pdf | 24 Mar 2026 |
| Water NOCFile: Brigade Belvedere - Water NOC.pdf | 24 Mar 2026 |
| E-Khata ApplicationFile: Brigade Belvedere - E-Khata Application.jpg | 24 Mar 2026 |
| Affidavit - KhataFile: Brigade Belvedere - Affidavit - Khata.pdf | 24 Mar 2026 |
| MR 17_1File: M R T8 Sy No 171.pdf | 24 Mar 2026 |
| MR 17_2File: M R 9 T9 Sy No 172.pdf | 24 Mar 2026 |
| MR 17_3File: M R T10 Sy No 173.pdf | 24 Mar 2026 |
| MR 17_4File: M R T11 Sy No 174.pdf | 24 Mar 2026 |
| MR 17_5File: M R T12 Sy No 175.pdf | 24 Mar 2026 |
| TITLE DEEDFile: TITLE DEED.pdf | 24 Mar 2026 |
| RTC, survey 17/1 | - |
| Mutation, survey 17/1 | - |
| Encumbrance Certificate, survey 17/1 | - |
| Conversion/Alienation Order, survey 17/1 | - |
| Sale/Title/Gift Deed, survey 17/1 | - |
| JDA, survey 17/1 | - |
| Khatha, survey 17/1 | - |
| RTC, survey 17/2 | - |
| Mutation, survey 17/2 | - |
| Encumbrance Certificate, survey 17/2 | - |
| Conversion/Alienation Order, survey 17/2 | - |
| Sale/Title/Gift Deed, survey 17/2 | - |
| JDA, survey 17/2 | - |
| Khatha, survey 17/2 | - |
| RTC, survey 17/3 | - |
| Mutation, survey 17/3 | - |
| Encumbrance Certificate, survey 17/3 | - |
| Conversion/Alienation Order, survey 17/3 | - |
| Sale/Title/Gift Deed, survey 17/3 | - |
| JDA, survey 17/3 | - |
| Khatha, survey 17/3 | - |
| RTC, survey 17/4 | - |
| Mutation, survey 17/4 | - |
| Encumbrance Certificate, survey 17/4 | - |
| Conversion/Alienation Order, survey 17/4 | - |
| Sale/Title/Gift Deed, survey 17/4 | - |
| JDA, survey 17/4 | - |
| Khatha, survey 17/4 | - |
| RTC, survey 17/5 | - |
| Mutation, survey 17/5 | - |
| Encumbrance Certificate, survey 17/5 | - |
| Conversion/Alienation Order, survey 17/5 | - |
| Sale/Title/Gift Deed, survey 17/5 | - |
| JDA, survey 17/5 | - |
| Khatha, survey 17/5 | - |
| Registration CertificateFile: Certificate of Incorporation - BEL copy.pdf | - |
| Memorandum of AssociationFile: MOA and AOA - BEL.pdf | - |
| Article of AssociationFile: MOA and AOA - BEL.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Brigade Belvedere on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 36 registered projects within 2 km.
Floris & Commercial at Brigade Autograph
Ananthay Properties Private Limited
Godrej Woodscapes
Godrej Properties Limited
Sattva Songbird
Sattva Resi Private Limited
Godrej Splendour
Godrej Properties Limited
PAVANI MIRABILIA PHASE I
Sai Sravanthi Infra Projects Pvt Ltd
Godrej Splendour Phase II
Godrej Properties Limited
See every Bengaluru Urban project, with the district possession charts
Builder: Brigade Enterprises Ltd
Brigade Enterprises Ltd has 46 registrations on RERA Karnataka, including Brigade Oasis - Phase 1 and Brigade Atmosphere- Phase 1. Its filings declare 67 earlier projects, 41 of them declared completed. Litigation is declared on 10 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Brigade Belvedere is delayed beyond 31 Mar 2031?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Brigade Belvedere?
The registered promoter entity is Brigade Enterprises Ltd, a company as per the filing. Its CIN L85110KA1995PLC019126 and GSTIN 29AAACB7459F1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Brigade Belvedere?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Brigade Belvedere?
The professionals named in the filing: Architect: Paul Manoharan Moses; Engineer: RENUKA PRASAD H N; Engineer: Balasubramanian M N; Chartered Accountant: R. Srinivasan. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Brigade Belvedere?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback