Home / Browse projects / Bengaluru Urban, Karnataka / SAMHITA SERENE MTB-PHASE II

Registration approved No litigation declared Residential/Group Housing project

SAMHITA SERENE MTB-PHASE II

By SAMHITA ESTATES LLP

RG-KA-83362 · RERA PRM/KA/RERA/1251/446/PR/231123/006425 · Last updated on RERA Karnataka portal: 13 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2026Possession promisedno revision filed
4 of 15Construction stages donefurthest along: RCC or MS Framed structure, 95%
134 of 292Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 144 documents Report an error

SAMHITA SERENE MTB-PHASE II is a Residential/Group Housing project by SAMHITA ESTATES LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/231123/006425 on 23 Nov 2023. Possession is promised by 31 Dec 2026. 158 of the 292 units on this registration are recorded sold or booked, and 4 of 15 construction stages are filed complete.

At a glance

Project

  • NameSAMHITA SERENE MTB-PHASE II
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560049
  • Pincode560049
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/231123/006425
  • ReraGenie IDRG-KA-83362

Builder

  • NameSAMHITA ESTATES LLP
  • Entity typePartnership Firm
  • LLPINAAT-7177
  • GSTIN29AEFFS6962L1Z7
  • Authorized SignatoryBALA SAKETH REDDY RAMIREDDY
  • Other registrations2 more →
  • Declared earlier projects3 →

Key dates

this monthRegisteredNov 2023PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on23 Nov 2023
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings3 building records
  • Documents filed144 files

Current status

54%158 of 292 units booked
95.2%Of the estimated cost spent so far

Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK C---84084
BLOCK D---92092
BLOCK E---1160116

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 15 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 95%.

Building: 95% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure95%
Masonry Construction95%
Plastering inside , outside & Ceiling95%
Joinery: Doors, Windows, Ventilators etc95%
Basic work of Water supply, Sanitary and Electrification95%
Dadoing, Skirting, Flooring, Tiles work (All types)95%
Railing and Grill fixing95%
Electrification, Water supply and Sanitary Finishing90%
Painting90%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work90%
Internal and External work including landscapes as per sanctioned drawings90%

Progress on shared amenities40

As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementNoNot applicable
TerraceYes0%
Outer WallYes0%
Open parking areasYes0%
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership4

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area16,216 sq m
Named landowners4
LandownerVillageDistrict
CHANDRASHEKAR M--
N Nagaraja--
M Chandrashekar--
M Chandrashekar--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 90.50 cr
Cost incurredRs 86.16 cr
Spent of the estimate95.2%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 85.80 crRs 83.15 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 4.50 crRs 2.71 cr
On-site expenditure-Consultants FeesRs 20.00 lakhRs 29.61 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectLAKSHMAN D N
EngineerBHASKAR Y
Chartered AccountantMANOJ KIMAR DUNGARWAL

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed144

As listed on the registration, under the names the promoter filed them with; the newest 80 of 144 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/231123/006425 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Samhita estates MTB Phase 2_Form 4 Q2 of FY 2026-27 signed.pdf13 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Architech Certificate.pdf13 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate.pdf13 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Samhita estates MTB Phase 2_Form 4 Q1 of FY 2026-27 Signed.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: SAMHITA SERENE MTB - PHASE 2 Form-5, Architect(Q1).pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: SAMHITA SERENE MTB - PHASE 2 Form-6 Engineer(Q1).pdf14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Samhita estates MTB Phase 2_Form 4 Q4 of FY 2025-26 signed.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Filled - SAMHITA SERENE MTB - PHASE 2 Form-5, Architect(Q4).pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Filled - SAMHITA SERENE MTB - PHASE 2 Form-6 Engineer(Q4).pdf15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Samhita estates MTB Phase 2_Form 4 Q3 of FY 2025-26 signed.pdf19 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5_Architect Certificate.pdf19 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6_Engineer Certificate.pdf19 Jan 2026
Power Supply NOCFile: 2 Power Supply NOC.pdf10 Nov 2023
Water NOC with supporting DocFile: 3 Water NOC with supporting Doc.pdf10 Nov 2023
Modified Development Plan ClarificationFile: 5 Modified Development Plan.pdf10 Nov 2023
Land Cost Calculation SheetFile: 4 Land Cost Calculation Sheet.pdf10 Nov 2023
Revised Area StatementFile: 1 Revised Area Statement.pdf10 Nov 2023
Structural Engineer's Self Attested CertificateFile: Structural Engineer's Self Attested Certificate.pdf20 Oct 2023
Commencement Letter Applied ACKFile: Commencement Letter Applied ACK.pdf20 Oct 2023
CDP Serene Phase 2File: CDP Serene Phase 2.pdf20 Oct 2023
BDA Developmental PlanFile: BDA Developmental Plan.pdf20 Oct 2023
Plan Sanction Letter Phase 2File: Plan Sanction Letter Phase 2.pdf20 Oct 2023
Revised and Old Plan Sanction LetterFile: Revised and Old Plan Sanction Letter.pdf20 Oct 2023
Combined Floor Area Statement Phase 2File: Combined Floor Area Statement Phase 2.pdf20 Oct 2023
EC - Sy No132-2 (01-10-19 to 31-03-20)File: EC - Sy No132-2 (01-10-19 to 31-03-20).pdf20 Oct 2023
EC - Sy No132-1 (09-10-19 to 31-03-22)File: EC - Sy No132-1 (09-10-19 to 31-03-22).pdf20 Oct 2023
EC - Sy No132-3 (01-10-19 to 31-03-20)File: EC - Sy No132-3 (01-10-19 to 31-03-20).pdf20 Oct 2023
MR Sy No 132-3File: MR Sy No 132-3.pdf20 Oct 2023
MR Sy No 132-2 NagarajFile: MR Sy No 132-2 Nagaraj.pdf20 Oct 2023
RTC SY NO 132-2File: RTC SY NO 132-2.pdf20 Oct 2023
RTC SY NO 132-3File: RTC SY NO 132-3.pdf20 Oct 2023
RTC SY NO 132-1File: RTC SY NO 132-1.pdf20 Oct 2023
Land Cost - Self Attested BSR Signed LetterFile: Land Cost - Self Attested BSR Signed Letter.pdf20 Oct 2023
Lakshman DN Architect LicenceFile: Lakshman DN Architect Licence.png20 Oct 2023
Kithanganur Deed of RelinquishmentFile: Kithanganur Deed of Relinquishment.pdf20 Oct 2023
Kithanganur DLP - 23File: Kithanganur DLP - 23.pdf20 Oct 2023
Clarification on Samhita Phase-2File: Clarification on Samhita Phase-2.pdf20 Oct 2023
Commencement certificate Phase 2File: Commencement certificate Phase 2.pdf20 Oct 2023
WATER NOCFile: WATER NOC.pdf20 Oct 2023
RTC, survey 132/1-
Mutation, survey 132/1-
Encumbrance Certificate, survey 132/1-
Conversion/Alienation Order, survey 132/1-
Sale/Title/Gift Deed, survey 132/1-
JDA, survey 132/1-
Khatha, survey 132/1-
RTC, survey 132/2-
Mutation, survey 132/2-
Encumbrance Certificate, survey 132/2-
Conversion/Alienation Order, survey 132/2-
Sale/Title/Gift Deed, survey 132/2-
JDA, survey 132/2-
Khatha, survey 132/2-
RTC, survey 132/3-
Mutation, survey 132/3-
Encumbrance Certificate, survey 132/3-
Conversion/Alienation Order, survey 132/3-
Sale/Title/Gift Deed, survey 132/3-
JDA, survey 132/3-
Khatha, survey 132/3-
RTC, survey 132/4-
Mutation, survey 132/4-
Encumbrance Certificate, survey 132/4-
Conversion/Alienation Order, survey 132/4-
Sale/Title/Gift Deed, survey 132/4-
JDA, survey 132/4-
Khatha, survey 132/4-
Registration CertificateFile: Certificate of Incorporation.PDF-
Partnership DeedFile: Samhita Estates LLP Agreement.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form-1 CA Certificate.pdf-
Certificate issued by Architect Form 2File: Form-2 Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Form-3 Samhita Serene MTB Phase 2.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non-Litigation Affidavit.pdf-
Certificate from Chartered AccountFile: Form-1 CA Certificate.pdf-
Balance Sheet 2020 - 2021File: Balance Sheet with Schedule FY 2021-22.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
SAMHITA SERENE MTB-PHASE 1KITHIGANURU VILLAGE, BIDARAHALLI HOBLIOngoingDec 2024Not delivered

How this compares with Bengaluru Urban

54%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SAMHITA SERENE MTB-PHASE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSAMHITA SERENE MTB-PHASEOther 20Dot size: filed unitsN

Filed coordinates, straight-line distance. 20 registered projects within 2 km.

Builder: SAMHITA ESTATES LLP

SAMHITA ESTATES LLP has 3 registrations on RERA Karnataka, including SAMHITA FINESSE and SAMHITA SERENE MTB - PHASE I. Its filings declare 3 earlier projects, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SAMHITA SERENE MTB-PHASE II is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SAMHITA SERENE MTB-PHASE II?

The registered promoter entity is SAMHITA ESTATES LLP, a partnership firm as per the filing. Its LLPIN AAT-7177 and GSTIN 29AEFFS6962L1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SAMHITA SERENE MTB-PHASE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SAMHITA SERENE MTB-PHASE II?

The professionals named in the filing: Architect: LAKSHMAN D N; Engineer: BHASKAR Y; Chartered Accountant: MANOJ KIMAR DUNGARWAL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAMHITA SERENE MTB-PHASE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAMHITA SERENE MTB-PHASE II. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAMHITA SERENE MTB-PHASE II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.