Home / Browse projects / Bengaluru Urban, Karnataka / SAIKAM AANANDA
SAIKAM AANANDA
By M/S SAIKAM DREAM ACRES PVT. LTD
RG-KA-15408 · RERA PRM/KA/RERA/1251/308/PR/290423/005903 · Last updated on RERA Karnataka portal: 20 Apr 2023
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
SAIKAM AANANDA is a Plotted Development project by M/S SAIKAM DREAM ACRES PVT. LTD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/290423/005903 on 29 Apr 2023. Possession is promised by 2 Feb 2025.
At a glance
Project
- NameSAIKAM AANANDA
- TypePlotted Development
- Location
- Anekal
- Bengaluru Urban
- 562125
- Pincode562125
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/308/PR/290423/005903
- ReraGenie IDRG-KA-15408
Builder
- NameM/S SAIKAM DREAM ACRES PVT. LTD
- Entity typeCompany
- CINU45203AP2007PTC053786
- Authorized SignatorySiva Chaitanya Saikam
- DirectorsSivaChaitanya Saikam, Saikam jayachandra reddy, Sivachaitanya saikam, Saikam sai ramani, Saikam Sai swetha
- Project HeadSivachaitanya Saikam
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on29 Apr 2023
- Promised completion2 Feb 2025
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed148 files
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Land and ownership5
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| M/S SAIKAM DREAM ACRES PVT. LTD. | - | - |
| SRINIVASAMURTHY C | - | - |
| SRINIVASAMURTHY | - | - |
| SRINIVASAMURTHY | - | - |
| SRINIVASAMURTHY | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 3.60 cr | - |
| Payment of fees | Rs 57.58 lakh | - |
| On-site expenditure-Consultants Fees | Rs 28.79 lakh | - |
| Payment of taxes | Rs 14.39 lakh | - |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Engineer | S.N. Arun Kumar |
| Chartered Accountant | Girish J S |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed148
As listed on the registration, under the names the promoter filed them with; the newest 80 of 148 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/290423/005903 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Gopi Partition DeedFile: Gopi Partition Deed.pdf | 20 Apr 2023 |
| M R sy no 11_1File: M R sy no 11_1.pdf | 20 Apr 2023 |
| MR 1 SY NO 7File: MR 1 SY NO 7.pdf | 20 Apr 2023 |
| MR Sy No 70File: MR Sy No 70.pdf | 20 Apr 2023 |
| MR SY NO8_3File: MR SY NO8_3.pdf | 20 Apr 2023 |
| Partition Deed 8_3File: Partition Deed 8_3.pdf | 20 Apr 2023 |
| Partition Deed 11_1 & 70File: Partition Deed 11_1 & 70.pdf | 20 Apr 2023 |
| Partition Deed 1972File: Partition Deed 1972.pdf | 20 Apr 2023 |
| Proforma Agreement of SaleFile: Proforma Agreement of Sale.pdf | 20 Apr 2023 |
| Sale Deed 691File: Sale Deed 691.pdf | 20 Apr 2023 |
| Sale Deed 692File: Sale Deed 692.pdf | 20 Apr 2023 |
| 3(1) AffidavitFile: 3(1) Affidavit.pdf | 11 Apr 2023 |
| Approval planFile: Approval plan.pdf | 11 Apr 2023 |
| CDP MapFile: CDP Map.pdf | 11 Apr 2023 |
| Conversion Order for sy 8_3File: Conversion Order for sy 8_3.pdf | 11 Apr 2023 |
| Draft Agreement for SaleFile: Draft Agreement for Sale.pdf | 11 Apr 2023 |
| Financial Year 2019_20File: Financial Year 2019_20.pdf | 11 Apr 2023 |
| Financial Year 2020_21File: Financial Year 2020_21.pdf | 11 Apr 2023 |
| Financial Year 2021_22File: Financial Year 2021_22.pdf | 11 Apr 2023 |
| Inventory Details PlotwiseFile: Inventory Details Plotwise.xlsx | 11 Apr 2023 |
| JDA for Sy No 7 2Acre 7_5 GuntaFile: JDA for Sy No 7 2Acre 7_5 Gunta.pdf | 11 Apr 2023 |
| JDA for Sy No 8_3 38 GuntasFile: JDA for Sy No 8_3 38 Guntas.pdf | 11 Apr 2023 |
| JDA for Sy No 11_1 1 Acre 10 GuntaFile: JDA for Sy No 11_1 1 Acre 10 Gunta.pdf | 11 Apr 2023 |
| JDA for Sy No 70 15 Gunta and 15 GuntaFile: JDA for Sy No 70 15 Gunta and 15 Gunta.pdf | 11 Apr 2023 |
| Sale deed For Sy No 70 VinodammaFile: Sale deed For Sy No 70 Vinodamma.pdf | 11 Apr 2023 |
| sale deed for Sy No 70 LakshmammaFile: sale deed for Sy No 70 Lakshmamma.pdf | 11 Apr 2023 |
| Sale deed for Sy No 70 PrakashFile: Sale deed for Sy No 70 Prakash.pdf | 11 Apr 2023 |
| Village MapFile: Village Map.pdf | 11 Apr 2023 |
| Water NOCFile: Water NOC.pdf | 11 Apr 2023 |
| Joint AffidavitFile: Joint Affidavit.pdf | 11 Apr 2023 |
| Model Form of Allotment LetterFile: Model Form of Allotment Letter.pdf | 11 Apr 2023 |
| Non Litigation AffidavitFile: Non Litigation Affidavit.pdf | 11 Apr 2023 |
| Project SpecificationFile: Project Specification.pdf | 11 Apr 2023 |
| Relinquishment DeedFile: Relinquishment Deed.pdf | 11 Apr 2023 |
| Septic Tank and Soak PitFile: Septic Tank and Soak Pit.pdf | 11 Apr 2023 |
| Source of FundFile: Source of Fund.pdf | 11 Apr 2023 |
| RTC, survey 70 | - |
| Mutation, survey 70 | - |
| Encumbrance Certificate, survey 70 | - |
| Conversion/Alienation Order, survey 70 | - |
| Sale/Title/Gift Deed, survey 70 | - |
| Khatha, survey 70 | - |
| RTC, survey 70 | - |
| Mutation, survey 70 | - |
| Encumbrance Certificate, survey 70 | - |
| Conversion/Alienation Order, survey 70 | - |
| JDA, survey 70 | - |
| Khatha, survey 70 | - |
| RTC, survey 7 | - |
| Mutation, survey 7 | - |
| Encumbrance Certificate, survey 7 | - |
| Conversion/Alienation Order, survey 7 | - |
| JDA, survey 7 | - |
| Khatha, survey 7 | - |
| RTC, survey 11/1 | - |
| Mutation, survey 11/1 | - |
| Encumbrance Certificate, survey 11/1 | - |
| Conversion/Alienation Order, survey 11/1 | - |
| JDA, survey 11/1 | - |
| Khatha, survey 11/1 | - |
| RTC, survey 8/3 | - |
| Mutation, survey 8/3 | - |
| Encumbrance Certificate, survey 8/3 | - |
| Conversion/Alienation Order, survey 8/3 | - |
| JDA, survey 8/3 | - |
| Khatha, survey 8/3 | - |
| Registration CertificateFile: SDA reg certificate.pdf | - |
| Organization StructureFile: SDA reg certificate.pdf | - |
| Certificate issued by CA Form 1File: ca certificate for project registration.pdf | - |
| Certificate issued by Engineer Form 3File: Engineer Certificate Form_3.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| AffidavitFile: form b.pdf | - |
| Certificate from Chartered AccountFile: ca certificate for project registration.pdf | - |
| Certificate issued by ArchitectFile: SAIKAM AANANDA- RERA- ARCHITECT CERTIFICATE.pdf | - |
| Balance Sheet 2021 - 2022File: SDA FY 2021-22_compressed.pdf | - |
| Balance Sheet 2020 - 2021File: SDA FY 2020-21_compressed.pdf | - |
| Balance Sheet 2019 - 2020File: SDA FY 2019-20_compressed.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: SDA FY 2021-22_compressed.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: SDA FY 2020-21_compressed.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep SAIKAM AANANDA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 40 registered projects within 2 km.
Nambiar District 25 Phase 3
Nambiar EnsembleResidential Projects LLP
Meridian Park Phase II @ The Prestige City
PRESTIGE PROJECTS PRIVATE LIMITED
Meridian Park Phase I @ The Prestige City
PRESTIGE PROJECTS PRIVATE LIMITED
Meridian Park Phase III @ The Prestige City
PRESTIGE PROJECTS PRIVATE LIMITED
Nambiar District 25 Phase 2
Nambiar EnsembleResidential Projects LLP
SEVEN SARJAPUR
FORTUNE PRIMERO LLP
See every Bengaluru Urban project, with the district possession charts
Builder: M/S SAIKAM DREAM ACRES PVT. LTD
M/S SAIKAM DREAM ACRES PVT. LTD has 1 registration on RERA Karnataka, including SAIKAM AANANDA. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if SAIKAM AANANDA is delayed beyond 2 Feb 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SAIKAM AANANDA?
The registered promoter entity is M/S SAIKAM DREAM ACRES PVT. LTD, a company as per the filing. Its CIN U45203AP2007PTC053786 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SAIKAM AANANDA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SAIKAM AANANDA?
The professionals named in the filing: Engineer: S.N. Arun Kumar; Chartered Accountant: Girish J S. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAIKAM AANANDA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback