Home / Browse projects / Bengaluru Urban, Karnataka / Meridian Park Phase I @ The Prestige City
Meridian Park Phase I @ The Prestige City
By PRESTIGE PROJECTS PRIVATE LIMITED
RG-KA-02430 · RERA PRM/KA/RERA/1251/308/PR/090222/004684 · Last updated on RERA Karnataka portal: 14 Jan 2026
Source: official RERA Karnataka filing
Red flags
- 3 complaints at RERA Karnataka
- Completion date moved by 6 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
Saved.
Meridian Park Phase I @ The Prestige City is a Residential/Group Housing project by PRESTIGE PROJECTS PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/090222/004684 on 9 Feb 2022. Possession is promised by 14 Jan 2026. The completion date has moved by 6 months from the original filing. 898 of the 898 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete. 3 complaints are on record with the regulator.
At a glance
Project
- NameMeridian Park Phase I @ The Prestige City
- TypeResidential/Group Housing
- Location
- Anekal
- Bengaluru Urban
- 562125
- Pincode562125
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/308/PR/090222/004684
- ReraGenie IDRG-KA-02430
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on9 Feb 2022
- Promised completion14 Jan 2026
- Revised completionRevised to 14 Jan 2026 (originally 14 Jul 2025)
- Buildings5 building records
- Documents filed245 files
Current status
Figures as on 14 Jan 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building 5 - T6 | - | - | - | 180 | 0 | 180 |
| Building 5 - T7 | - | - | - | 180 | 0 | 180 |
| Building 5 - T8 | - | - | - | 180 | 0 | 180 |
| Building 5 - T9 | - | - | - | 178 | 0 | 178 |
| Building 5 - T10 | - | - | - | 180 | 0 | 180 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 14 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
18 of 18 construction stages are filed complete.
Building: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | 100% |
| RCC or MS Framed structure | 100% |
| Masonry Construction | 100% |
| Plastering inside , outside & Ceiling | 100% |
| Joinery: Doors, Windows, Ventilators etc | 100% |
| Basic work of Water supply, Sanitary and Electrification | 100% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 100% |
| Railing and Grill fixing | 100% |
| Electrification, Water supply and Sanitary Finishing | 100% |
| Painting | 100% |
| Fire prevention and fire fighting fitting and fixture with network | 100% |
| Weather Proof work(tile,concrete) | 100% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 100% |
| Internal and External work including landscapes as per sanctioned drawings | 100% |
Progress on shared amenities32
As on 14 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 100% |
| Sewage and Drainage System | Yes | 100% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 100% |
| Energy management | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Solid waste management and disposal | Yes | 100% |
| Emergency Evacuation services | Yes | 100% |
| Internal Roads & Footpaths | Yes | 100% |
| Electricity supply transformer and substation | No | Not applicable |
| Storm water drains | Yes | 100% |
| Use of renewable energy | Yes | 100% |
| Sewage Treatment Plant (STP) | Yes | 100% |
| Parks & Tree planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Electricity | Yes | 100% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 100% |
| Club House | Yes | 100% |
| Community Hall | Yes | 100% |
| Outdoor Sports facility | Yes | 100% |
| Indoor Sports facility | Yes | 100% |
| Swimming Pool | Yes | 100% |
| Gym | Yes | 100% |
| Parks | Yes | 100% |
| Power Backup | Yes | 100% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 100% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 100% |
| Lifts | Yes | 100% |
| Corridor/Lobbies | Yes | 100% |
| Fire escapes | No | Not applicable |
Land and ownership17
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Prestige Proejcts Private Limited | - | - |
| Prestige Projects Private Limited | - | - |
| Prestige Projects Private Limited | - | - |
| Prestige Projects Private Limited | - | - |
| Prestige Projects Private Limited | - | - |
| Prestige Projects Private Limited | - | - |
| Prestige Projects Private Limited | - | - |
| Prestige Projects Private Limited | - | - |
| Prestige Projects Private Limited | - | - |
| Prestige Projects Private Limited | - | - |
| Prestige Projects Private Limited | - | - |
| Prestige Projects Private Limited | - | - |
| Prestige Projects Private Limited | - | - |
| Prestige Projects Private Limited | - | - |
| Prestige Projects Private Limited | - | - |
| Prestige Projects Private Limited | - | - |
| Prestige Projects Private Limited | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 324.66 cr | Rs 315.19 cr |
| On-site expenditure-Site Overhead | Rs 86.10 cr | Rs 90.41 cr |
| On-site expenditure-Cost Of Services(Water, Electricity, Sewage) | Rs 78.08 cr | Rs 83.24 cr |
| Principal sum and interest payable to financial institutions-Scheduled Banks | Rs 66.27 cr | Rs 70.41 cr |
| Payment of taxes | Rs 40.22 cr | Rs 46.58 cr |
| On-site expenditure-Consultants Fees | Rs 13.18 cr | Rs 65.58 cr |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RSP Design Consultants (India) Pvt Ltd |
| Engineer | Design Tree Service Consultants |
| Chartered Accountant | M Padmanabha Bhat |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterForce Majeure; Shortage of Labour; Shortage of Labour; Shortage of Building Materials, Concrete, Jalli etc; Shortage of Building Materials, Concrete, Jalli etc; Shortage of Building Materials, Concrete, Jalli etc; Shortage of Labour; others; Transport strike - Delay in Delivery of Material; others; others; others; others; Force Majeure; Force Majeure; Force Majeure; Force Majeure; Force Majeure; Force Majeure; Force Majeure; Force Majeure
Complaints filed with RERA Karnataka3
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| 01283/2025 | - | PRESTIGE PROJECTS PRIVATE LIMITED | 15/10/2025 |
| 00291/2026 | - | PRESTIGE PROJECTS PRIVATE LIMITED | 24/03/2026 |
| 00737/2026 | - | PRESTIGE PROJECTS PRIVATE LIMITED | 24/06/2026 |
Documents filed245
As listed on the registration, under the names the promoter filed them with; the newest 80 of 245 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/090222/004684 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Q3 Meridian Ph I.pdf | 14 Jan 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Q3 Meridian Ph I.pdf | 14 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Q3 Meridian Ph I.pdf | 14 Jan 2026 |
| Q3 2025-26 Water supply and sewage board | 14 Jan 2026 |
| Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 14 Jan 2026 |
| Q3 2025-26 KSPCB- MOEF (Above 50 Acres) | 14 Jan 2026 |
| Q3 2025-26 KPTCL- BESCOM | 14 Jan 2026 |
| Q3 2025-26 Fire and Safety | 14 Jan 2026 |
| Q3 2025-26 Airport Authority of India | 14 Jan 2026 |
| Q3 2025-26 BSNL/Telecommunication Department | 14 Jan 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Q3 Meridian Ph I.pdf | 14 Jan 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Q3 Meridian Ph I.pdf | 14 Jan 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Q3 Meridian Ph I.pdf | 14 Jan 2026 |
| Q4 2025-26 Water supply and sewage board | 14 Jan 2026 |
| Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 14 Jan 2026 |
| Q4 2025-26 KSPCB- MOEF (Above 50 Acres) | 14 Jan 2026 |
| Q4 2025-26 KPTCL- BESCOM | 14 Jan 2026 |
| Q4 2025-26 Fire and Safety | 14 Jan 2026 |
| Q4 2025-26 Airport Authority of India | 14 Jan 2026 |
| Q4 2025-26 BSNL/Telecommunication Department | 14 Jan 2026 |
| Fee paid receitpFile: RE0122021612182858.pdf | 25 Jan 2022 |
| MOA AOA and change of Partnership from RR estates to PPPLFile: RR estates to PPPL.pdf | 25 Jan 2022 |
| Sale Deed-20/2File: SD-20-2.pdf | 25 Jan 2022 |
| EC-20/2File: EC-20-2.pdf | 25 Jan 2022 |
| OM-20/2File: OM-20-2-21.pdf | 25 Jan 2022 |
| RTC 20/2File: RTC-20-2.pdf | 25 Jan 2022 |
| Total Extent of 1 A 37 G is purchased in terms of 2 Sale Deeds (25+31+21) All 3 deeds mergedFile: SD-21-1-Meged.pdf | 25 Jan 2022 |
| OM for Sy.No.21/1 is attached (3 OM is merged)File: OM-21-1-Merged.pdf | 25 Jan 2022 |
| RTC for Sy.No.21/1 is attachedFile: RTC-21-1.pdf | 25 Jan 2022 |
| Sy.No.21 was bifurcated into 5 portions Phodi Mutation attachedFile: Phodi Mutation -21-4.pdf | 25 Jan 2022 |
| ECfor Sy.No.21/1 old No.21 is attachedFile: EC-21.pdf | 25 Jan 2022 |
| Sale Ded-22/1File: Sd-22-1.pdf | 25 Jan 2022 |
| EC-22/1File: EC-22-1.pdf | 25 Jan 2022 |
| RTC-22/1File: RTC-22-1.pdf | 25 Jan 2022 |
| MR-22/1File: MR-22-1.pdf | 25 Jan 2022 |
| OM-22/1File: OM-22-1.pdf | 25 Jan 2022 |
| Sale Deed-22/5File: SD-22-5 old No22-2A.pdf | 25 Jan 2022 |
| OM-22/5File: OM-22-5(Old No22-2A).pdf | 25 Jan 2022 |
| RTC-22/5File: RTC-22-5.pdf | 25 Jan 2022 |
| Phodi MR-22/5File: Phodi-22-2A-5.pdf | 25 Jan 2022 |
| EC-22/2File: EC-22-2A.pdf | 25 Jan 2022 |
| Sale Deed-22/3 1 Acre 10 guntas consisting of 2 Deeds of 25 guntas each and the same is mergedFile: SD-22-3-Merged.pdf | 25 Jan 2022 |
| SD-22/3-25 guntasFile: SD-21-1-22-3.pdf | 25 Jan 2022 |
| OM-22/3 1 Acre 10 guntasFile: OM-22-3-merged.pdf | 25 Jan 2022 |
| OM-22/3-25 guntasFile: OM-22-3.pdf | 25 Jan 2022 |
| EC-22/3File: EC-22-3.pdf | 25 Jan 2022 |
| RTC-22/3File: RTC-22-3.pdf | 25 Jan 2022 |
| MR 22/3File: MR-22-3.pdf | 25 Jan 2022 |
| SD-23/3 and 23/5 (OldNo.23/2) 35.75 guntas is purchased as 23/2 and phodied as (23.5+12.5)File: SD-23-3_5 (old No23-2).pdf | 25 Jan 2022 |
| EC-23/2File: EC-23-2.pdf | 25 Jan 2022 |
| OM-23/3 and 5 old No.23/2File: OM-23-3-5.pdf | 25 Jan 2022 |
| RTC-23/3File: RTC-23-3.pdf | 25 Jan 2022 |
| RTC-23/5File: RTC-23-5.pdf | 25 Jan 2022 |
| Phodi MR-23/5File: Phodi Mutation-23-2-5.pdf | 25 Jan 2022 |
| Total Extent is of purhased in 3 documents (1 Acre 1 G +30 G+10 G)-SD for 1 Acre 1 GFile: SD-25-1A1G.pdf | 25 Jan 2022 |
| SD for 30 G-25 Sy.No.File: SD-25-30G.pdf | 25 Jan 2022 |
| Exchange Deed for Sy.No.25-10 GFile: ED-25-10G.pdf | 25 Jan 2022 |
| OM for Sy.No.25File: OM-25.pdf | 25 Jan 2022 |
| RTC for Sy.No25File: RTC-25.pdf | 25 Jan 2022 |
| EC for Sy.No.25File: EC-25.pdf | 25 Jan 2022 |
| EC for Sy.No.19/2File: EC-19-2.pdf | 25 Jan 2022 |
| EC for Sy.No.19/3 and 4File: EC-19-3-4.pdf | 25 Jan 2022 |
| EC for Sy.No.120/1File: EC-20-1.pdf | 25 Jan 2022 |
| EC for Sy.No.21 (new numbers 21/1,4)File: EC-21 (2).pdf | 25 Jan 2022 |
| EC for Sy.No.21 (new numbers 21/1,4)File: EC-21.pdf | 25 Jan 2022 |
| EC for Sy.No.21/5File: EC-21-5.pdf | 25 Jan 2022 |
| EC for Sy.No.22/2AFile: EC-22-2a (2).pdf | 25 Jan 2022 |
| EC for Sy.No.23/2File: EC-23-2.pdf | 25 Jan 2022 |
| EC for Sy.No.24/1File: EC-24-1.pdf | 25 Jan 2022 |
| EC for Sy.No.24/2File: EC-24-2.pdf | 25 Jan 2022 |
| EC for Sy.No.25File: EC-25.pdf | 25 Jan 2022 |
| Project wise details of Sy.Nos are attachedFile: Projectwise-survey numbers-The Prestige City.pdf | 25 Jan 2022 |
| Exact extent in each project is attachedFile: TPC parcel wise details.pdf | 25 Jan 2022 |
| Area Statement of Meridian Park Phase IFile: Area Statement.pdf | 25 Jan 2022 |
| Site PlanFile: Site Plan.pdf | 25 Jan 2022 |
| All the plans mergedFile: Sanctioned Plan-all-c.pdf | 25 Jan 2022 |
| Commencement certificateFile: CC Sarjapura.pdf | 25 Jan 2022 |
| Phasing Plan attached.File: Phasing.pdf | 25 Jan 2022 |
| Specification signedFile: Specification-signed.pdf | 25 Jan 2022 |
| Draft AgreemebntFile: AGS-Meridian Park-Phase I.pdf | 25 Jan 2022 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| PRESTIGE GREAT ACRES | The Prestige City, near Yamare Panchayath Office, V.K.Halli and Ittangur Village, Sarjapura Hobli, Anekal Taluk, | Ongoing | Aug 2022 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Meridian Park Phase I @ The Prestige City on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 70 registered projects within 2 km.
Nambiar District 25 Phase 3
Nambiar EnsembleResidential Projects LLP
Meridian Park Phase II @ The Prestige City
PRESTIGE PROJECTS PRIVATE LIMITED
Meridian Park Phase III @ The Prestige City
PRESTIGE PROJECTS PRIVATE LIMITED
Nambiar District 25 Phase 2
Nambiar EnsembleResidential Projects LLP
SEVEN SARJAPUR
FORTUNE PRIMERO LLP
SIPANI CITY PHASE-1
SIPANI PROPERTIES PVT LTD
See every Bengaluru Urban project, with the district possession charts
Builder: PRESTIGE PROJECTS PRIVATE LIMITED
PRESTIGE PROJECTS PRIVATE LIMITED has 12 registrations on RERA Karnataka, including Aston Park @ The Prestige City and Garden Breeze @ The Prestige City. Its filings declare 6 earlier projects, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Meridian Park Phase I @ The Prestige City is delayed beyond 14 Jan 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Meridian Park Phase I @ The Prestige City?
The registered promoter entity is PRESTIGE PROJECTS PRIVATE LIMITED, a company as per the filing. Its CIN U45201KA2008PTC046784 and GSTIN 29AAECP7361E1Z9 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Meridian Park Phase I @ The Prestige City?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Meridian Park Phase I @ The Prestige City?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
Who certifies construction progress at Meridian Park Phase I @ The Prestige City?
The professionals named in the filing: Architect: RSP Design Consultants (India) Pvt Ltd; Engineer: Design Tree Service Consultants; Chartered Accountant: M Padmanabha Bhat. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Meridian Park Phase I @ The Prestige City?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.