SAI SILICON HEIGHTS

By United Developers

RG-KA-70660 · RERA PRM/KA/RERA/1251/446/PR/180424/006788 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2027Possession promisedno revision filed
6 of 17Construction stages donefurthest along: Masonry Construction, 90%
108 of 208Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 168 documents Report an error

SAI SILICON HEIGHTS is a Mixed Development project by United Developers in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/180424/006788 on 18 Apr 2024. Possession is promised by 31 Dec 2027. 100 of the 208 units on this registration are recorded sold or booked, and 6 of 17 construction stages are filed complete.

At a glance

Project

  • NameSAI SILICON HEIGHTS
  • TypeMixed Development
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560066
  • Pincode560066
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/180424/006788
  • ReraGenie IDRG-KA-70660

Builder

  • NameUnited Developers
  • Entity typePartnership Firm
  • GSTIN29AAGFU2177E1Z0
  • Authorized SignatoryP. SUBRAMANI
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredApr 2024PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on18 Apr 2024
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings3 building records
  • Documents filed168 files

Current status

48%100 of 208 units booked
132.9%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block A---1160116
Block B---90090
Commercial---022

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 17 construction stages are filed complete. The stage furthest along is Masonry Construction, at 90%.

Building: 70% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction90%
Plastering inside , outside & Ceiling85%
Joinery: Doors, Windows, Ventilators etc50%
Basic work of Water supply, Sanitary and Electrification45%
Dadoing, Skirting, Flooring, Tiles work (All types)45%
Railing and Grill fixing30%
Electrification, Water supply and Sanitary Finishing65%
Painting55%
Fire prevention and fire fighting fitting and fixture with network50%
Weather Proof work(tile,concrete)40%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work40%
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes75%
Sewage and Drainage SystemYes65%
Water conservation/rain water harvesting/recharge of ground waterYes50%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes50%
Solid waste management and disposalYes40%
Emergency Evacuation servicesYes40%
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes50%
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes50%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes25%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes20%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes0%
Swimming PoolYes45%
GymYes0%
ParksNoNot applicable
Power BackupYes10%
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes75%
LiftsYes50%
Corridor/LobbiesYes50%
Fire escapesYes50%
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementYes95%
TerraceYes50%
Outer WallNoNot applicable
Open parking areasYes25%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes25%
Common storage spacesNoNot applicable

Land and ownership3

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,806 sq m
Named landowners3
LandownerVillageDistrict
UNITED DEVELOPERS--
P. Subramani(UNITED DEVEOPERS)--
Mr.V.GOPALKRISHNA@KITTY--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 93.10 cr
Cost incurredRs 123.78 cr
Spent of the estimate132.95%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 90.00 crRs 107.05 cr
Payment of taxesRs 1.35 crRs 50.00 lakh
Principal sum and interest payable to financial institutions-Scheduled BanksRs 1.20 crRs 16.11 cr
On-site expenditure-Consultants FeesRs 35.00 lakhRs 41,435
On-site expenditure-Salaries of workersRs 20.00 lakhRs 11.76 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBommu Veera Narendranath Reddy
EngineerChanakya N
Chartered AccountantG.Raghu Nadha Mandadi

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed168

As listed on the registration, under the names the promoter filed them with; the newest 80 of 168 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/180424/006788 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 -.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: form 5.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6,.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA.PDF14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q1 2026-27 Fire and Safety14 Jul 2026
Q1 2026-27 Airport Authority of India14 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA.pdf14 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: RERA_form-5.pdf14 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6.pdf14 Apr 2026
Q4 2025-26 Water supply and sewage board14 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Apr 2026
Q4 2025-26 KPTCL- BESCOM14 Apr 2026
Q4 2025-26 Fire and Safety14 Apr 2026
Q4 2025-26 Airport Authority of India14 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department14 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4.PDF5 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: RERA_form-5.pdf5 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6.pdf5 Feb 2026
Q3 2025-26 Water supply and sewage board5 Feb 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)5 Feb 2026
Q3 2025-26 KPTCL- BESCOM5 Feb 2026
Q3 2025-26 Fire and Safety5 Feb 2026
Q3 2025-26 Airport Authority of India5 Feb 2026
Q3 2025-26 BSNL/Telecommunication Department5 Feb 2026
1)Upload certified carpet area calculation.File: 1 Certified Carpet Area Calculation.pdf4 Apr 2024
2)Upload commencement certificate.File: 2 Commencement Certificate.pdf4 Apr 2024
3)area/no of units of KSPCB CFE. is not matching with sanction planFile: 3 KSPCB units mismatch-Clarification.pdf4 Apr 2024
4)area/no of units of SEIAA. is not matching with sanction planFile: 4 SEIAA Units Mismatch-Clarification.pdf4 Apr 2024
5)Upload relinquishment deed.File: 5 Relinquishment deed clarification.pdf4 Apr 2024
5)Upload relinquishment deed.File: 5 Relinquishment Deed.pdf4 Apr 2024
6) No of parking is mention project detail page is not matching with sanction plan. upload samFile: 6 Car parking Clarification.pdf4 Apr 2024
1) please upload the self attested copy of NOC issued by the BWSSB and BESCOM along with the copy ofFile: 1 Bescom Noc-Self Attested.pdf4 Apr 2024
1) please upload the self attested copy of NOC issued by the BWSSB and BESCOM along with the copy ofFile: 1 Bescom Fee Receipt-Self Attested.pdf4 Apr 2024
1) please upload the self attested copy of NOC issued by the BWSSB and BESCOM along with the copy ofFile: 1 BWSSB Noc-Self Attested.pdf4 Apr 2024
1) please upload the self attested copy of NOC issued by the BWSSB and BESCOM along with the copy ofFile: 1 BWSSB Fee Receipts-Self Attested.pdf4 Apr 2024
2) Please upload the STP drawing certified by the Engineer as per the KSPCB NOC.File: 2 Engineer Attested STP Drawing.pdf4 Apr 2024
3) Please upload the Land cost calculation sheet as per the guidance value(Self-attested copy).File: 3 Guidance Value Report-Clarification.pdf4 Apr 2024
4) Please clarify the source of water supply to the project along with the supporting documents andFile: 4 Source of Water Supply.pdf4 Apr 2024
5) Uploaded Proforma of agreement (AFS) for sale not in accordance with the notified AFS by GOK. ForFile: 5 Proforma - Agreement for Sale(AFS) - GOK.pdf4 Apr 2024
1) current year rtc for all 3 snos of the projectFile: 1 Latest RTC of all 3 Sy Nos.pdf4 Apr 2024
2) EC from 5-12-2023 to till date for all 3 snos of the projectFile: 2 EC of all Sy Nos from 01-04-2023 to 02-04-2024.pdf4 Apr 2024
3)conversion order issued by the deputy commissioner for sno 113/6 measuring 0-21.08 guntasFile: 3 Conversion Order 113-6.pdf4 Apr 2024
4)notarized non-litigation affidavitFile: 4 Notarised Non-Litigation affadavit.pdf4 Apr 2024
RTC, survey 113/2-
Mutation, survey 113/2-
Encumbrance Certificate, survey 113/2-
Conversion/Alienation Order, survey 113/2-
Sale/Title/Gift Deed, survey 113/2-
Khatha, survey 113/2-
RTC, survey 113/1-
Mutation, survey 113/1-
Encumbrance Certificate, survey 113/1-
Conversion/Alienation Order, survey 113/1-
Sale/Title/Gift Deed, survey 113/1-
JDA, survey 113/1-
Khatha, survey 113/1-
RTC, survey 113/6-
Mutation, survey 113/6-
Encumbrance Certificate, survey 113/6-
Conversion/Alienation Order, survey 113/6-
Sale/Title/Gift Deed, survey 113/6-
JDA, survey 113/6-
Khatha, survey 113/6-
Registration CertificateFile: 1 UD Deed of Reconstitution of Partnership.pdf-
Partnership DeedFile: 1 UD Deed of Reconstitution of Partnership.pdf-
Partner Details-
Partner Details-
Partner Details-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
SAI SILICON CITY113/4, Nagondanahalli Village, K R Puram Hobli,Completed-No date filed

How this compares with Bengaluru Urban

48%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SAI SILICON HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSAI SILICON HEIGHTSOther 37Dot size: filed unitsN

Filed coordinates, straight-line distance. 37 registered projects within 2 km.

Builder: United Developers

United Developers has 2 registrations on RERA Karnataka, including SAI SILICON HEIGHTS and SAI SILICON CITY. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SAI SILICON HEIGHTS is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SAI SILICON HEIGHTS?

The registered promoter entity is United Developers, a partnership firm as per the filing. Its GSTIN 29AAGFU2177E1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SAI SILICON HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SAI SILICON HEIGHTS?

The professionals named in the filing: Architect: Bommu Veera Narendranath Reddy; Engineer: Chanakya N; Chartered Accountant: G.Raghu Nadha Mandadi. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAI SILICON HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAI SILICON HEIGHTS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAI SILICON HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.