SAGAR PARADISE
RG-GJ-61858 · RERA PR/GJ/GANDHINAGAR/KALOL/AUDA/MAA02062/EX2/A1M/200522 · Last updated on GujRERA portal: 6 Jul 2022
Source: official GujRERA filing
Red flags
- Completion date moved by 27 months
- 2 extensions taken
Clear
- Nothing verified clear yet
Saved.
SAGAR PARADISE is a Mixed Development project by Sthapatya Infracon in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/KALOL/AUDA/MAA02062/EX2/A1M/200522 on 17 Mar 2018. Possession is promised by 31 Jul 2022. The completion date has moved by 27 months from the original filing. 40 of the 47 units on this registration are recorded sold or booked, and 9 of 9 construction stages are filed complete.
At a glance
Project
- NameSAGAR PARADISE
- TypeMixed Development
- Location
- Sagar Paradise
- Opposite Sindbad Hotel
- KIRC Collage Road
- Kalol
- Gandhinagar
- 382721
- Pincode382721
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR/GJ/GANDHINAGAR/KALOL/AUDA/MAA02062/EX2/A1M/200522
- ReraGenie IDRG-GJ-61858
Builder
- NameSthapatya Infracon
- Entity typePARTNERSHIP FIRM
Key dates
Key facts
Registration and timeline
- StatusValid until 31 Jul 2022
- Registered on17 Mar 2018
- Promised completion31 Jul 2022
- Revised completionRevised to 31 Jul 2022 (originally 30 Apr 2020)
- Buildings1 building record
- Documents filed38 files
Current status
Figures as on 6 Jul 2022, this project's latest GujRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Sagar Paradise | - | - | - | 39 | 8 | 47 |
The full filing
Everything below is from the project's own GujRERA filing, free to read.
Construction progress by building1
As on 6 Jul 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 9 construction stages are filed complete.
Sagar Paradise: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, internal plaster, floorings, doors and windows within flats | 100% |
| Sanitary fittings within the flats | 100% |
| Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing | 100% |
| Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing | 100% |
Progress on shared amenities19
As on 6 Jul 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal roads and footpaths | Yes | 100% |
| Water supply | Yes | 100% |
| Sewerage (chamber, lines, septic tank, STP) | Yes | 100% |
| Storm water drains | No | Not applicable |
| Landscaping and tree planting | Yes | 100% |
| Street lighting | No | Not applicable |
| Community buildings | No | Not applicable |
| Treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Water conservation, rain water harvesting | Yes | 100% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Fire fighting | No | Not applicable |
| Drinking water facilities | No | Not applicable |
| Emergency evacuation | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Security | No | Not applicable |
| Letter box | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Sagar Paradise | NA | Rs 3.38 cr | Rs 3.38 cr |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Manoj Kanani |
| Engineer | Shashin K Shah |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Documents filed38
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/KALOL/AUDA/MAA02062/EX2/A1M/200522 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Accountant's certificate (Form 3) | 6 Jul 2022 |
| Architect's certificate (Form 1) | 5 Jul 2022 |
| Engineer's certificate (Form 2) | 5 Jul 2022 |
| Engineer's certificate annexure | 5 Jul 2022 |
| Site photograph, Sagar Paradise | 5 Jul 2022 |
| RERA registration certificate | 17 Mar 2018 |
| Proforma agreement for sale | - |
| Auditor's report (1 of 3) | - |
| Auditor's report (2 of 3) | - |
| Auditor's report (3 of 3) | - |
| Income tax return (1 of 3) | - |
| Income tax return (2 of 3) | - |
| Income tax return (3 of 3) | - |
| Project specific document | - |
| Directors' report (1 of 3) | - |
| Directors' report (2 of 3) | - |
| Directors' report (3 of 3) | - |
| Commencement certificate | - |
| Approved sanctioned plan | - |
| Approved layout plan | - |
| Agreement | - |
| Land location | - |
| Encumbrance certificate | - |
| Area development document | - |
| Proforma allotment letter | - |
| Brochure | - |
| Project related document | - |
| Declaration in Form B | - |
| Project photograph | - |
| Audited balance sheet (1 of 3) | - |
| Audited balance sheet (2 of 3) | - |
| Audited balance sheet (3 of 3) | - |
| Audited profit and loss statement (1 of 3) | - |
| Audited profit and loss statement (2 of 3) | - |
| Audited profit and loss statement (3 of 3) | - |
| Cash flow statement (1 of 3) | - |
| Cash flow statement (2 of 3) | - |
| Cash flow statement (3 of 3) | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Gandhinagar
Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.
Keep SAGAR PARADISE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kalol1,600+ in Gandhinagar
Filed coordinates, straight-line distance. 61 registered projects within 2 km.
Greencity
GREEN CITY INFRASTRUCTURE
GRACE
SHRINIVAS ORGANISORS PRIVATE LIMITED
SUPER CITY PHASE 1
SHRINIVAS ORGANISORS PRIVATE LIMITED
LALJI LUXURIA
LALJI BUILDER
Tirupati Empire
Tirupati Empire Enterprise
siddhraj homes
Siddhraj Developers
See every Gandhinagar project, with the district possession charts
Builder: Sthapatya Infracon
Sthapatya Infracon has 1 registration on GujRERA, including SAGAR PARADISE. Read the full track record. See more projects on the Gandhinagar district page.
Frequently asked questions
What are my rights if SAGAR PARADISE is delayed beyond 31 Jul 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.
How do I verify and contact the developer of SAGAR PARADISE?
The registered promoter entity is Sthapatya Infracon, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.
Is my payment protected in SAGAR PARADISE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SAGAR PARADISE?
The professionals named in the filing: Architect: Manoj Kanani; Engineer: Shashin K Shah. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAGAR PARADISE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.