Registration approved No litigation declared Mixed Development project

S.V.Prime

By S V INFRA HOLDINGS LIMITED

RG-KA-63786 · RERA PRM/KA/RERA/1251/446/PR/230522/004896 · Last updated on RERA Karnataka portal: 29 Nov 2025

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Nov 2025Possession promisedno revision filed
18 of 18Construction stages doneevery applicable stage filed complete
78 of 256Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 111 documents Report an error

S.V.Prime is a Mixed Development project by S V INFRA HOLDINGS LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/230522/004896 on 23 May 2022. Possession is promised by 30 Nov 2025. 178 of the 256 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete.

At a glance

Project

  • NameS.V.Prime
  • TypeMixed Development
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560066
  • Pincode560066
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/230522/004896
  • ReraGenie IDRG-KA-63786

Builder

  • NameS V INFRA HOLDINGS LIMITED
  • Entity typeCompany
  • CINU74999KA2018PLC112142
  • GSTIN29ABACS1458C1ZI
  • Authorized SignatoryMADHUSUDHANA RAO KONDA
  • Managing DirectorJANARDHANA RAO KOTAPATI
  • DirectorsMADHUSUDHANA RAO KONDA, GUNTUPALLI NAGESWARA RAO, MEDASANI RAMANAIAH, KONDA MAHESWARA RAO, MALAKONDAIAH GUNTUPALLI
  • Project HeadKonda madhusudhanarao

Key dates

this monthRegisteredMay 2022PromisedNov 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on23 May 2022
  • Promised completion30 Nov 2025
  • Revised completionNone
  • Buildings3 building records
  • Documents filed111 files

Current status

70%178 of 256 units booked
3.7%Of the estimated cost spent so far

Figures as on 29 Nov 2025, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A-----72
B---1040104
C---84084

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 29 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 18 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 29 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Solid waste management and disposalYes100%
Emergency Evacuation servicesYes100%
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes100%
Storm water drainsYes100%
Use of renewable energyYes100%
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingNoNot applicable
Street LightingYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseYes100%
Community HallNoNot applicable
Outdoor Sports facilityYes100%
Indoor Sports facilityYes100%
Swimming PoolYes100%
GymYes100%
ParksYes100%
Power BackupYes100%
Piped GasNoNot applicable
Water and SanitationYes100%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesYes100%
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areasYes100%
Provision for lodging of management staff and security staffYes100%
Water conservation and renewable energyYes100%
Common storage spacesYes100%

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,599 sq m
Named landowners1
LandownerVillageDistrict
C R Guruprasath--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 155.30 cr
Cost incurredRs 5.70 cr
Spent of the estimate3.67%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 130.30 crRs 5.21 cr
Payment of taxesRs 14.24 cr-
On-site expenditure-Salaries of workersRs 4.10 crRs 32.89 lakh
On-site expenditure-Site OverheadRs 3.97 crRs 10.36 lakh
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 1.52 crRs 6.33 lakh
On-site expenditure-Consultants FeesRs 97.00 lakh-
Payment of PremiumsRs 20.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSreenivasa Rao G
EngineerSai Krishna Mohan Vardhaneni
Chartered AccountantGadde Bhaskara Rao

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed111

As listed on the registration, under the names the promoter filed them with; the newest 80 of 111 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/230522/004896 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: SV Infra Q3 RERA Certificate_compressed (1).pdf29 Nov 2025
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Architect Certificate (1).pdf29 Nov 2025
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer certificate (2).pdf29 Nov 2025
Q3 2025-26 Water supply and sewage board29 Nov 2025
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)29 Nov 2025
Q3 2025-26 KPTCL- BESCOM29 Nov 2025
Q3 2025-26 Fire and Safety29 Nov 2025
Q3 2025-26 Airport Authority of India29 Nov 2025
Updated Proforma AOSFile: Updated Agreement of Sale.pdf21 May 2022
BBMP Building LicenseFile: Building license SVP.pdf21 May 2022
Site PlanFile: Sheet no 1 Site plan.pdf21 May 2022
Second Basement Floor PlanFile: Sheet no 2 Second basement floor plan.pdf21 May 2022
First Basement Floor PlanFile: Sheet no 3 First basement floor plan.pdf21 May 2022
Ground Floor PlanFile: Sheet no 4 Ground Floor plan.pdf21 May 2022
First and Second Floor PlanFile: Sheet no 5 First and second floor plan.pdf21 May 2022
Third and Fourth Floor PlanFile: Sheet no 6 third and fourth floor plan.pdf21 May 2022
Typical 5th to 13th and terrace floor planFile: Sheet no 7 typical 5th to 13th and terrace floor plan.pdf21 May 2022
Section and Elevation PlanFile: Sheet no 8 section and elevation.pdf21 May 2022
proforma of agreement for saleFile: SV Prime AOS Proforma.pdf27 Apr 2022
proforma of agreement for saleFile: SV Prime AOS 01-04-2022.pdf1 Apr 2022
Agreement for saleFile: Agreement of sale.pdf16 Mar 2022
title deed and partition deedFile: Title deed and partition deed.pdf3 Dec 2021
non litigation regarding project landFile: non litigation.pdf3 Dec 2021
Plan sanction letterFile: Plan Sanction letter.pdf3 Dec 2021
1st and 2nd floor planFile: 1st and 2nd floor plan.pdf3 Dec 2021
3rd and 4th floor planFile: 3rd and 4th floor plan.pdf3 Dec 2021
Ground Floor planFile: Ground Floor plan.pdf3 Dec 2021
Lower Basement floor planFile: lower basement floor plan.pdf3 Dec 2021
Upper Basement floor planFile: Upper basement floor plan.pdf3 Dec 2021
Section and ElevationFile: Section and Elevation.pdf3 Dec 2021
Site PlanFile: Site Plan.pdf3 Dec 2021
Typical 5th to 13th floor plan and terrace floor planFile: Typical 5th to 13th floor plan and terrace floor plan.pdf3 Dec 2021
STPFile: STP.pdf3 Dec 2021
Building license letterFile: Building license letter.pdf3 Dec 2021
RTC, survey 38-
Mutation, survey 38-
Encumbrance Certificate, survey 38-
Conversion/Alienation Order, survey 38-
JDA, survey 38-
Khatha, survey 38-
Registration CertificateFile: Incorporation Certificate (1) (1).pdf-
Organization StructureFile: SV Infra MOA (1) (1).PDF-
Certificate issued by CA Form 1File: Form-4 CA Certificate SV Prime.pdf-
Certificate issued by Architect Form 2File: FORM-2 ARCHITECT.pdf-
Certificate issued by Engineer Form 3File: FORM -3 ENGENNER.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Notarized Affidavit for 3(1) Voliation (1) (1).pdf-
Certificate from Chartered AccountFile: Ca cert approvals.pdf-
Balance Sheet 2020 - 2021File: S V INFRA Balance Sheet FY 2020-21.pdf-
Balance Sheet 2019 - 2020File: SV INFRA BALANCE SHEET FY 2019-20.pdf-
Balance Sheet 2018 - 2019File: BALANCE SHEET FY 2018-19.pdf-
Audited Profit and Loss Statement 2020 - 2021File: S V INFRA P&L FY 2020-21.pdf-
Audited Profit and Loss Statement 2019 - 2020File: SV INFRA P&L FY 2019-20.pdf-
Audited Profit and Loss Statement 2018 - 2019File: SV INFRA P&L FY 2018-19.pdf-
Director's Report 2020 - 2021File: S V INFRA Directors Report FY 2020-21.pdf-
Director's Report 2019 - 2020File: SV INFRA Directors Report FY 2019-20.pdf-
Director's Report 2018 - 2019File: SV INFRA Directors Report FY 2018-19.pdf-
Cash Flow Statement 2020 - 2021File: S V INFRA Cash Flow FY 2020-21.pdf-
Cash Flow Statement 2019 - 2020File: SV INFRA Cash Flow FY 2019-20.pdf-
Auditor's Report 2020 - 2021File: S V INFRA Auditors Report FY 2020-21.pdf-
Auditor's Report 2019 - 2020File: SV INFRA Auditors Report FY 2019-20.pdf-
Auditor's Report 2018 - 2019File: SV INFRA Auditors report FY 2018-19.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: S V INFRA ITR FY 2019-20.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: SV INFRA ITR FY 2018-19.pdf-
Ground Floor plan-
Ground Floor plan (2)-
Ground Floor plan-
Section and Elevation-
Section and Elevation-
SV Prime Safety Certificate (1)-
Advocate Search report-
JDA And JDA Rectification merged-
Change of land-
as pattanduru Agrahara-rera (1)-converted-
SV prime Allotment letter draft (2)-
sd of pattanduru Agrahara-rera-
SV PRIME MOD_1 (1) (3)-1 (2)-
ReraFormB-

How this compares with Bengaluru Urban

70%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep S.V.Prime on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmS.V.PrimeOther 44Dot size: filed unitsN

Filed coordinates, straight-line distance. 44 registered projects within 2 km.

Builder: S V INFRA HOLDINGS LIMITED

S V INFRA HOLDINGS LIMITED has 1 registration on RERA Karnataka, including S.V.Prime. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if S.V.Prime is delayed beyond 30 Nov 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of S.V.Prime?

The registered promoter entity is S V INFRA HOLDINGS LIMITED, a company as per the filing. Its CIN U74999KA2018PLC112142 and GSTIN 29ABACS1458C1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in S.V.Prime?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at S.V.Prime?

The professionals named in the filing: Architect: Sreenivasa Rao G; Engineer: Sai Krishna Mohan Vardhaneni; Chartered Accountant: Gadde Bhaskara Rao. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in S.V.Prime?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About S.V.Prime. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save S.V.Prime to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.