Home / Browse projects / Kalaburagi, Karnataka / S R APARTMENTS
S R APARTMENTS
RG-KA-74030 · RERA PRM/KA/RERA/1263/419/PR/030524/006834 · Last updated on RERA Karnataka portal: 22 Feb 2024
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
S R APARTMENTS is a Residential/Group Housing project by S R Constructions in Kalaburagi, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1263/419/PR/030524/006834 on 3 May 2024. Possession is promised by 22 Dec 2024.
At a glance
Project
- NameS R APARTMENTS
- TypeResidential/Group Housing
- Location
- Kalaburagi
- 585102
- Pincode585102
- RERA no.PRM/KA/RERA/1263/419/PR/030524/006834
- ReraGenie IDRG-KA-74030
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on3 May 2024
- Promised completion22 Dec 2024
- Revised completionNone
- Buildings1 building record
- Documents filed133 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SR APARTMENTS | - | - | - | 16 | 0 | 16 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 22 Feb 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Upto Plinth Level | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| Retaining wall (All types) | Not applicable |
| RCC or MS Framed structure | - |
| Masonry Construction | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Painting | - |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | Not applicable |
| Internal and External work including landscapes as per sanctioned drawings | Not applicable |
Progress on shared amenities40
As on 22 Feb 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Sewage and Drainage System | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | No | Not applicable |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | No | Not applicable |
| Piped Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | - |
| Lifts | No | Not applicable |
| Corridor/Lobbies | No | Not applicable |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | No | Not applicable |
| Basement | No | Not applicable |
| Terrace | No | Not applicable |
| Outer Wall | No | Not applicable |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership5
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| BHAGAMMA | - | - |
| Mohan V BHAVIMANI | - | - |
| SANJAY KUMAR | - | - |
| SUNIL | - | - |
| RAHUL | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 3.00 cr | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Siraj Ahmed Shahna |
| Engineer | Mohammed Irfan |
| Chartered Accountant | AMOGH DHARWADHAR |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed133
As listed on the registration, under the names the promoter filed them with; the newest 80 of 133 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1263/419/PR/030524/006834 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| MUTATION, Death Certificate and DeclarationFile: MUTATION, Death Certificate and Declaration.pdf | 22 Feb 2024 |
| MutationFile: MUTATION.pdf | 13 Dec 2023 |
| RTCFile: SR Apartment-RTC.pdf | 13 Dec 2023 |
| Village MapFile: Village Map.pdf | 13 Dec 2023 |
| Project Document SummaryFile: Project Document Summary.pdf | 22 Nov 2023 |
| Need title deed of Bhagamma and others(uploaded building license instead of title deed )File: Bhagamma Family Details attached with Death Certificate-compressed.pdf | 22 Nov 2023 |
| Mutation Copy and RTCFile: RTC and MR.pdf | 22 Nov 2023 |
| Village MapFile: Townplaning.pdf | 22 Nov 2023 |
| Please upload the brief estimated cost of construction certified by the Engineer.File: SR Apartment Brief Estimate for Cost of Construction.pdf | 22 Nov 2023 |
| Allotment LetterFile: SR Apartment-Allotment Letter.pdf | 22 Nov 2023 |
| ALLOTMENT LETTERFile: ALLOTMENT LETTER.pdf | 12 Aug 2023 |
| CARPET AREA CALCULATIONFile: CARPET AREA CALCULATION.pdf | 12 Aug 2023 |
| CDP MAPFile: CDP MAP.jpeg | 12 Aug 2023 |
| cost of constrution certified by engineerFile: cost of constrution certified by engineer.pdf | 12 Aug 2023 |
| declaration for Height of the buildingFile: declaration for Height of the building.pdf | 12 Aug 2023 |
| declaration for Village MapFile: declaration for Village Map.pdf | 12 Aug 2023 |
| section 3(1) notarized affidavitFile: section 3(1) notarized affidavit.pdf | 12 Aug 2023 |
| SR APARTMENTS Query ResponseFile: SR APARTMENTS Quesry Response.pdf | 12 Aug 2023 |
| allotment letterFile: allotment letter (2).pdf | 20 Jun 2023 |
| GESCOM NOCFile: GESCOM NOC.pdf | 20 Jun 2023 |
| MUTATIONFile: MUTATION.pdf | 20 Jun 2023 |
| NOC-Water BoardFile: NOC-Water Board.jpeg | 20 Jun 2023 |
| Permission copyFile: Permission copy.pdf | 20 Jun 2023 |
| Plan Sca MapFile: Plan Sca Map.pdf | 20 Jun 2023 |
| RTCFile: RTC.pdf | 20 Jun 2023 |
| SR Aparments -Title ReportFile: SR Aparments -Title Report.pdf | 20 Jun 2023 |
| SR Apartment for RERA_DeedFile: SR Apartment for RERA_Deed.pdf | 20 Jun 2023 |
| TownplaningFile: Townplaning.pdf | 20 Jun 2023 |
| Agreement of Sale ProformaFile: Agreement of Sale Proforma final.pdf | 25 May 2023 |
| Amenities & project detailsFile: Amenities & project details.pdf | 25 May 2023 |
| DECLARATION FOR STPFile: DECLARATION FOR STP.pdf | 25 May 2023 |
| Form-1File: Form-1.pdf | 25 May 2023 |
| Form-2File: Form-2.pdf | 25 May 2023 |
| Form-3File: Form-3.pdf | 25 May 2023 |
| InventoryFile: Inventory.xlsx | 25 May 2023 |
| JDAFile: JDA.pdf | 25 May 2023 |
| Joint Affidavit from Promoter and LandownerFile: Joint Affidavit from Promoter and Landowner.pdf | 25 May 2023 |
| Permission payment receiptFile: Permission payment receipt.jpeg | 25 May 2023 |
| Plan Sca MapFile: Plan Sca Map.pdf | 25 May 2023 |
| RTCFile: RTC.pdf | 25 May 2023 |
| Title ReportFile: Title Report.pdf | 25 May 2023 |
| TownplaningFile: Townplaning.pdf | 25 May 2023 |
| InventoryFile: Inventory.xlsx | 16 Mar 2023 |
| IT BS P&L 2019-20File: IT BS P&L 2019-20.pdf | 16 Mar 2023 |
| IT Return 20-21File: IT Return 20-21.pdf | 16 Mar 2023 |
| IT Return 2021-22File: IT Return 2021-22.pdf | 16 Mar 2023 |
| Permission copyFile: Permission copy.pdf | 16 Mar 2023 |
| PLAN MAPFile: Plan Sca Map.pdf | 16 Mar 2023 |
| TownplaningFile: Townplaning.pdf | 16 Mar 2023 |
| RTCFile: RTC.pdf | 16 Mar 2023 |
| ADVOCATE SEARCH REPORTFile: ADVOCATE SEARCH REPORT.pdf | 14 Feb 2023 |
| Allotment of PlotFile: Allotment of Plot.pdf | 14 Feb 2023 |
| CDP MAPFile: CDP MAP.pdf | 14 Feb 2023 |
| GUIDENCE VALUEFile: GUIDENCE VALUE.pdf | 14 Feb 2023 |
| InventoryFile: Inventory.xlsx | 14 Feb 2023 |
| Joint Affidavit from Promoter and LandownerFile: Joint Affidavit from Promoter and Landowner.pdf | 14 Feb 2023 |
| NON LITIGATION AFFIDAVITEFile: NON LITIGATION AFFIDAVITE.pdf | 14 Feb 2023 |
| Panchayat copyFile: Panchayat copy.pdf | 14 Feb 2023 |
| Provisional Allotment LetterFile: Provisional Allotment Letter Format (1)-converted.pdf | 14 Feb 2023 |
| RTC AND MRFile: RTC AND MR.pdf | 14 Feb 2023 |
| SINGLE PLOT LAYOUT ORDERFile: SINGLE PLOT LAYOUT ORDER.pdf | 14 Feb 2023 |
| SINGLE PLOT LAYOUTFile: SINGLE PLOT LAYOUT.pdf | 14 Feb 2023 |
| TITAL DEED OF BAGAMMA AND OTHERFile: TITAL DEED OF BAGAMMA AND OTHER.pdf | 14 Feb 2023 |
| VILLAGE MAPFile: VILLAGE MAP.pdf | 14 Feb 2023 |
| EXPLANATIONFile: EXPLANATION.pdf | 14 Feb 2023 |
| RTC, survey 74 | - |
| Mutation, survey 74 | - |
| Encumbrance Certificate, survey 74 | - |
| Conversion/Alienation Order, survey 74 | - |
| JDA, survey 74 | - |
| Khatha, survey 74 | - |
| Registration CertificateFile: REGISTRATION CERTIFICATE.pdf | - |
| Partnership DeedFile: PARTNERSHIP DEED.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: CA CERTIFICATE_compressed.pdf | - |
| Certificate issued by Architect Form 2File: ARCHIETECT CERTIFICATE_compressed.pdf | - |
| Certificate issued by Engineer Form 3File: ENGINEER CERTIFICATE.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Kalaburagi
Computed across the 210+ Kalaburagi projects on ReraGenie, from their own filings.
Keep S R APARTMENTS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kalaburagi210+ in Kalaburagi
S R Darshanapur Apartments
MOHAMMAD SHAFEEQ UR RAHMAN
PRIME-ELITE
M/S ISHANYA BUILDERS AND DEVELOPERS
Arya
Arya Builders & Developers
S.R. Galaxy Apartments
MOHAMMAD SHAFEEQ UR RAHMAN
S.R. NAJMA TOWER
S R Constructions
S R Pearl
SR Constructions
See every Kalaburagi project, with the district possession charts
Builder: S R Constructions
S R Constructions has 5 registrations on RERA Karnataka, including S R APARTMENTS and S.R. NAJMA TOWER. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Kalaburagi district page.
Frequently asked questions
What are my rights if S R APARTMENTS is delayed beyond 22 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of S R APARTMENTS?
The registered promoter entity is S R Constructions, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in S R APARTMENTS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at S R APARTMENTS?
The professionals named in the filing: Architect: Siraj Ahmed Shahna; Engineer: Mohammed Irfan; Chartered Accountant: AMOGH DHARWADHAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in S R APARTMENTS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback