Home / Browse projects / Bengaluru Rural, Karnataka / Riqueza Siri

Registration approved No litigation declared Residential/Group Housing project

Riqueza Siri

By Riqueza Estates Private Limited

RG-KA-75624 · RERA PRM/KA/RERA/1250/304/PR/070823/006119 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Nov 2027Possession promisedno revision filed
15 of 15Construction stages doneevery applicable stage filed complete
62 of 128Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 100 documents Report an error

Riqueza Siri is a Residential/Group Housing project by Riqueza Estates Private Limited in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/304/PR/070823/006119 on 7 Aug 2023. Possession is promised by 30 Nov 2027. 66 of the 128 units on this registration are recorded sold or booked, and 15 of 15 construction stages are filed complete.

At a glance

Project

  • NameRiqueza Siri
  • TypeResidential/Group Housing
  • Location
    • Hosakote
    • Bengaluru Rural
    • 562114
  • Pincode562114
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1250/304/PR/070823/006119
  • ReraGenie IDRG-KA-75624

Builder

  • NameRiqueza Estates Private Limited
  • Entity typeCompany
  • CINU45500KA2019PTC121475
  • GSTIN29AAJCR4262P1ZL
  • Authorized SignatoryPrashant Nayak
  • Managing DirectorMahesh K
  • DirectorsMahesh K, Chandur Srinivasachar Vyasaraj, Prashant Nayak, Nataraja Hullikunte
  • Project HeadNaveen Kumar S
  • Other registrations1 more →
  • Declared earlier projects5 →

Key dates

this monthRegisteredAug 2023PromisedNov 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on7 Aug 2023
  • Promised completion30 Nov 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed100 files

Current status

52%66 of 128 units booked
91.7%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block - A---68068
Block - B---60060

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 15 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)Not applicable
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes95%
Sewage and Drainage SystemYes95%
Water conservation/rain water harvesting/recharge of ground waterYes90%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes90%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes95%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes90%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes90%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes60%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityYes0%
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksYes0%
Power BackupYes60%
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes90%
LiftsYes60%
Corridor/LobbiesYes60%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes70%
BasementNoNot applicable
TerraceYes70%
Outer WallYes60%
Open parking areasYes70%
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,348 sq m
Named landowners2
LandownerVillageDistrict
Laburam G--
Pyari Kumari--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 20.45 cr
Cost incurredRs 18.75 cr
Spent of the estimate91.68%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 20.00 crRs 18.34 cr
On-site expenditure-Salaries of workersRs 25.00 lakhRs 25.00 lakh
Payment of cessRs 20.00 lakhRs 16.21 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSathish Babu
EngineerG Gopal
Chartered AccountantVinaykumar Bhat

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed100

As listed on the registration, under the names the promoter filed them with; the newest 80 of 100 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/304/PR/070823/006119 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Q2 Form -4, Chartered Accountant (QU)_Signed.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Engineer SIRI Q2.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer SIRI Q2.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Q1 Form -4, Chartered Accountant (QU)_Signed.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: FORM 5 ARCH-RIQUEZA SIRI-JUNE 2026.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Siri June-20206 Engineer Certificate.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Q4 Form -4, Chartered Accountant (QU)_Signed.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: FORM 5 ARCH RIQUEZA SIRI - QU - MARCH 26.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Riqueza Siri Engineer Certificate.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Q3 Form -1, Chartered Accountant (QU)_Signed.pdf31 Mar 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: FORM 5 ARCH RIQUEZA SIRI DEC 25.pdf31 Mar 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate.pdf31 Mar 2026
Q3 2025-26 Water supply and sewage board31 Mar 2026
Q3 2025-26 KPTCL- BESCOM31 Mar 2026
Source of funds detailsFile: Replay to the Final Notice about funds.pdf3 Aug 2023
Source of Fund NewFile: Source of Fund New.pdf17 Jul 2023
Cash Flow StatementFile: 1 Cash Flow Statement.pdf28 Jun 2023
2_1 and 2_2 Sale DeedFile: 2_1 and 2_2 Sale Deed.pdf28 Jun 2023
Architect Certification for area statementFile: Architect Certification for area statement.pdf28 Jun 2023
BHK wise area details Architect Certification for area statement signedFile: BHK wise area details Architect Certification for area statement signed.pdf28 Jun 2023
Cash Flow Statement signed2File: Cash Flow Statement signed2.pdf28 Jun 2023
Cash Flow StatementFile: Cash Flow Statement.pdf28 Jun 2023
Chartered Certificate Form 1 for RegistrationFile: Chartered Certificate Form 1 for Registration.pdf28 Jun 2023
ECFile: EC.pdf28 Jun 2023
Hissa (1)File: Hissa (1).pdf28 Jun 2023
HissaFile: Hissa.pdf28 Jun 2023
Mutation copyFile: Mutation copy.pdf28 Jun 2023
No litigation affidavit (1)File: No litigation affidavit (1).pdf28 Jun 2023
No litigation affidavitFile: No litigation affidavit.pdf28 Jun 2023
Plan Approval Letter Building LicenseFile: Plan Approval Letter Building License.pdf28 Jun 2023
Riqueza Siri Allotment LetterFile: Riqueza Siri Allotment Letter.pdf28 Jun 2023
Source of FundsFile: Source of Funds.pdf28 Jun 2023
STP flow drawingFile: STP flow drawing.pdf28 Jun 2023
Project name and project address and specificationFile: Specification with Project name and Address.pdf4 May 2023
Proforma of allotement letterFile: Riqueza Siri Allotment Lette.pdf4 May 2023
Proforma of Agreement for saleFile: Agreement of sale.pdf4 May 2023
Affidavit section 3(1)File: Notarized Affidavit for 3(1).pdf4 May 2023
Certified carpet area calculationFile: Architect Certification for area statement signed.pdf4 May 2023
Single plot layout orderFile: Singel site Order.pdf4 May 2023
Commencement certificateFile: Plan Approval Letter- Building License.pdf4 May 2023
Village map sowing the proposed siteFile: Village map showing proposed site.pdf4 May 2023
STP design drawing and STP demarcation drawingFile: STP Demarcation on site plan and Flow chat.pdf4 May 2023
Copy of Fee receipt paid towards BESCOM NOCFile: BESCOM Fee Paid Receipt.pdf4 May 2023
Hight of the building details - 14.55File: Hight of the building.pdf4 May 2023
FAR Sanctioned -1.96File: FAR Sanctioned.pdf4 May 2023
Break up of types of units (BHK wise)File: Break up of types of units (BHK wise).pdf4 May 2023
Registration CertificateFile: Company Registration.pdf-
Organization StructureFile: Organisation Structure.pdf-
Certificate issued by CA Form 1File: Chartered Certificate Form 1 for Registration.pdf-
Certificate issued by Architect Form 2File: Architect Certificate .pdf-
Certificate issued by Engineer Form 3File: Engineer Estimation.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
Certificate from Chartered AccountFile: Chartered Certificate Form 1 for Registration.pdf-
Balance Sheet 2021 - 2022File: Balance Sheet.pdf-
Balance Sheet 2020 - 2021File: Balance Sheet.pdf-
Balance Sheet 2019 - 2020File: Balance sheet.pdf-
Audited Profit and Loss Statement 2021 - 2022File: P & L.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Balance Sheet.pdf-
Audited Profit and Loss Statement 2019 - 2020File: P & L.pdf-
Director's Report 2021 - 2022File: Directors Report.pdf-
Director's Report 2020 - 2021File: Directors Report.pdf-
Director's Report 2019 - 2020File: Directors Report.pdf-
Auditor's Report 2021 - 2022File: Audit Report.pdf-
Auditor's Report 2020 - 2021File: Audit Report.pdf-
Auditor's Report 2019 - 2020File: Audit report.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: Ackl 22-23.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: Ackl.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: Ackl 20-21.pdf-
Plan Approval Letter- Building License-
BESCOM NOC Riqueza Siri-
Water NOC Riqueza Siri-
Approved Site Plan-

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
Riqueza Laghing EarthBhavanahalli Village, Narasapura malur roadOngoingJun 2023Not delivered
Riqueza BarbieSite - 93, 94 Nisarga High tec layout, Kannurahalli Main road, HoskoteOngoingDec 2022Not delivered

How this compares with Bengaluru Rural

52%of this project is bookeddistrict median 45%
20%of Bengaluru Rural projects moved their completion datethis one has not
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep Riqueza Siri on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

2 kmRiqueza SiriOther 22Dot size: filed unitsN

Filed coordinates, straight-line distance. 22 registered projects within 2 km.

Builder: Riqueza Estates Private Limited

Riqueza Estates Private Limited has 2 registrations on RERA Karnataka, including Riqueza Siri and Riqueza Laughing Earth Phase - II. Its filings declare 5 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if Riqueza Siri is delayed beyond 30 Nov 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Riqueza Siri?

The registered promoter entity is Riqueza Estates Private Limited, a company as per the filing. Its CIN U45500KA2019PTC121475 and GSTIN 29AAJCR4262P1ZL can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Riqueza Siri?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Riqueza Siri?

The professionals named in the filing: Architect: Sathish Babu; Engineer: G Gopal; Chartered Accountant: Vinaykumar Bhat. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Riqueza Siri?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Riqueza Siri. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Riqueza Siri to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.