ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / RADHE PACIFICA

Valid until 31 Jul 2028 Residential/Group Housing project

RADHE PACIFICA

By RADHE CORPORATION

RG-GJ-67757 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RAA15643/060825/310328 · Last updated on GujRERA portal: 6 Aug 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Jul 2028Possession promisedno revision filed
0 of 9Construction stages donefurthest along: Excavation, 15%
27 of 27Units unsoldnot recorded sold or booked
Jump to the 28 documents Report an error

RADHE PACIFICA is a Residential/Group Housing project by RADHE CORPORATION in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RAA15643/060825/310328 on 6 Aug 2025. Possession is promised by 31 Jul 2028. 0 of the 27 units on this registration are recorded sold or booked, and 0 of 9 construction stages are filed complete.

At a glance

Project

  • NameRADHE PACIFICA
  • TypeResidential/Group Housing
  • Location
    • SUR.NO-399/3
    • O.P.NO-91/3
    • F.P.NO-91/3
    • T.P.S.NO-303
    • KHORAJ
    • KHORAJ
    • Gandhinagar
    • 382421
  • Pincode382421
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RAA15643/060825/310328
  • ReraGenie IDRG-GJ-67757

Builder

  • NameRADHE CORPORATION
  • Entity typePARTNERSHIP FIRM
  • Other registrations2 more →
  • Past their filed date2

Key dates

this monthRegisteredAug 2025PromisedJul 2028

Key facts

Registration and timeline

  • StatusValid until 31 Jul 2028
  • Registered on6 Aug 2025
  • Promised completion31 Jul 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed28 files

Current status

0%0 of 27 units booked
3.2%Of the estimated cost spent so far

Figures as on 6 Aug 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Residential Unit (1 TO 27)---27027

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 6 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 9 construction stages are filed complete. The stage furthest along is Excavation, at 15%.

Residential Unit (1 TO 27): 2% average across the applicable activities

ActivityProgress
Excavation15%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, internal plaster, floorings, doors and windows within flats0%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing0%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 6 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyYes0%
SecurityYes0%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,727 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 14.20 cr
Cost incurredRs 45.00 lakh
Spent of the estimate3.17%
BuildingWingEstimatedIncurred
Residential Unit (1 TO 27)NARs 14.20 crRs 45.00 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUrvashi Lalitkumar Tuli
EngineerVIREN DILIPBHAI PAREKH

Documents filed28

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RAA15643/060825/310328 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
RERA registration certificate6 Aug 2025
Accountant's certificate (Form 3)4 Aug 2025
Architect's certificate (Form 1)23 May 2025
Engineer's certificate (Form 2)23 May 2025
Engineer's certificate annexure23 May 2025
Site photograph, Residential Unit (1 TO 27)23 May 2025
Proforma agreement for sale-
Project specific document-
Drainage affidavit-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Declaration in Form B1-
Declaration in Form B2-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Statutory document-
Other document-
Project photograph-
Proforma sale deed-

How this compares with Gandhinagar

0%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep RADHE PACIFICA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near KHORAJ1,600+ in Gandhinagar

2 kmRADHE PACIFICAOther 106Dot size: filed unitsN

Filed coordinates, straight-line distance. 106 registered projects within 2 km.

Builder: RADHE CORPORATION

Radhe Corporation has 3 registrations on GujRERA, including Radhe Helios and VRUNDAVAN VILLA. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if RADHE PACIFICA is delayed beyond 31 Jul 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of RADHE PACIFICA?

The registered promoter entity is RADHE CORPORATION, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in RADHE PACIFICA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at RADHE PACIFICA?

The professionals named in the filing: Architect: Urvashi Lalitkumar Tuli; Engineer: VIREN DILIPBHAI PAREKH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RADHE PACIFICA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RADHE PACIFICA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RADHE PACIFICA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.