Home / Browse projects / Gandhinagar, Gujarat / RADHE KUTIR

Valid until 28 Feb 2022 Residential/Group Housing project

RADHE KUTIR

By PALM DEVELOPERS

RG-GJ-33448 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA02605/EX2/081121 · Last updated on GujRERA portal: 23 Dec 2021

Source: official GujRERA filing

Red flags

  • Completion date moved by 26 months
  • 2 extensions taken

Clear

  • Separate project account declared
Feb 2022Possession promisedmoved 26 months from the original
15 of 28Construction stages doneacross 4 buildings; furthest along: Staircases, 98%
7 of 30Units unsoldnot recorded sold or booked
Jump to the 41 documents Report an error

RADHE KUTIR is a Residential/Group Housing project by PALM DEVELOPERS in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA02605/EX2/081121 on 9 May 2018. Possession is promised by 28 Feb 2022. The completion date has moved by 26 months from the original filing. 23 of the 30 units on this registration are recorded sold or booked, and 15 of 28 construction stages are filed complete.

At a glance

Project

  • NameRADHE KUTIR
  • TypeResidential/Group Housing
  • Location
    • SUR NO. 52/4/2
    • 52/5/P
    • BHAT
    • Bhat
    • Gandhinagar
    • 382428
  • Pincode382428
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA02605/EX2/081121
  • ReraGenie IDRG-GJ-33448

Builder

  • NamePALM DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredMay 2018First promiseDec 2019Revised toFeb 2022

Key facts

Registration and timeline

  • StatusValid until 28 Feb 2022
  • Registered on9 May 2018
  • Promised completion28 Feb 2022
  • Revised completionRevised to 28 Feb 2022 (originally 31 Dec 2019)
  • Buildings4 building records
  • Documents filed41 files

Current status

77%23 of 30 units booked
91.3%Of the estimated cost spent so far

Figures as on 23 Dec 2021, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TYPE A---10010
TYPE C---16016
TYPE D---202
TYPE E---202

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 23 Dec 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 28 construction stages are filed complete across 4 buildings. The stage furthest along is Staircases, at 98%.

TYPE A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
TYPE C95%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats76%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing98%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing93%
TYPE D95%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats76%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks97%
External plumbing and external plaster, elevation, completion of terraces with waterproofing97%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing95%
TYPE E90%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats96%
Sanitary fittings within the flats43%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks96%
External plumbing and external plaster, elevation, completion of terraces with waterproofing97%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing96%

Progress on shared amenities19

As on 23 Dec 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes90%
Water supplyYes93%
Sewerage (chamber, lines, septic tank, STP)Yes93%
Storm water drainsYes95%
Landscaping and tree plantingYes94%
Street lightingYes95%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes93%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes96%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,334 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 5.23 cr
Cost incurredRs 4.78 cr
Spent of the estimate91.31%
BuildingWingEstimatedIncurred
TYPE ANARs 1.31 crRs 1.19 cr
TYPE CNARs 1.31 crRs 1.19 cr
TYPE DNARs 1.31 crRs 1.19 cr
TYPE ENARs 1.31 crRs 1.19 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKIRTIKUMAR MAKWANA
EngineerHIMANSHU PATEL

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA02605/EX1/200120Applied Dec 2019; approved Jan 2020
PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA02605/EX2/081121Applied Oct 2021; approved Nov 2021

Documents filed41

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/AUDA/RAA02605/EX2/081121 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)23 Dec 2021
Engineer's certificate (Form 2)23 Dec 2021
Engineer's certificate annexure23 Dec 2021
Accountant's certificate (Form 3)23 Dec 2021
Site photograph, TYPE A23 Dec 2021
Site photograph, TYPE C23 Dec 2021
Site photograph, TYPE D23 Dec 2021
Site photograph, TYPE E23 Dec 2021
RERA registration certificate9 May 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

77%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one moved by 26 months

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep RADHE KUTIR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bhat1,600+ in Gandhinagar

2 kmRADHE KUTIROther 50Dot size: filed unitsN

Filed coordinates, straight-line distance. 50 registered projects within 2 km.

Builder: PALM DEVELOPERS

PALM DEVELOPERS has 1 registration on GujRERA, including RADHE KUTIR. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if RADHE KUTIR is delayed beyond 28 Feb 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of RADHE KUTIR?

The registered promoter entity is PALM DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in RADHE KUTIR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at RADHE KUTIR?

The professionals named in the filing: Architect: KIRTIKUMAR MAKWANA; Engineer: HIMANSHU PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RADHE KUTIR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RADHE KUTIR. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RADHE KUTIR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.