Home / Browse projects / Bengaluru Urban, Karnataka / Prestige Green Gables

Registration approved No litigation declared Mixed Development project

Prestige Green Gables

By PRESTIGE ESTATES PROJECTS LTD

RG-KA-85289 · RERA PRM/KA/RERA/1251/446/PR/140222/004706 · Last updated on RERA Karnataka portal: 6 Jan 2026

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Dec 2025Possession promisedmoved 6 months from the original
18 of 18Construction stages doneevery applicable stage filed complete
0 of 406Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 124 documents Report an error

Prestige Green Gables is a Mixed Development project by PRESTIGE ESTATES PROJECTS LTD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/140222/004706 on 14 Feb 2022. Possession is promised by 31 Dec 2025. The completion date has moved by 6 months from the original filing. 406 of the 406 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete.

At a glance

Project

  • NamePrestige Green Gables
  • TypeMixed Development
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560087
  • Pincode560087
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/140222/004706
  • ReraGenie IDRG-KA-85289

Builder

  • NamePRESTIGE ESTATES PROJECTS LTD
  • Entity typeCompany
  • CINU07010KA1997PLC022322
  • GSTIN29AABCP8096K1ZP
  • Authorized SignatorySwaroop Anish
  • CmdIrfan Razack
  • DirectorsIrfan Razack, REZWAN RAZACK, NOAMAN RAZACK, Uzma Irfan
  • Project HeadSuresh S
  • Other registrations18 more →
  • Declared earlier projects7 →

Key dates

this monthRegisteredFeb 2022First promiseJun 2025Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on14 Feb 2022
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Jun 2025)
  • Buildings4 building records
  • Documents filed124 files

Current status

100%406 of 406 units booked
110.0%Of the estimated cost spent so far

Figures as on 6 Jan 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 1---1000100
Tower 2---1030103
Tower 3---1030103
Tower 4---1000100

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 6 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 18 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 6 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Solid waste management and disposalYes100%
Emergency Evacuation servicesYes100%
Internal Roads & FootpathsYes100%
Electricity supply transformer and substationYes100%
Storm water drainsYes100%
Use of renewable energyYes100%
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingYes100%
Street LightingYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseYes100%
Community HallYes100%
Outdoor Sports facilityYes100%
Indoor Sports facilityYes100%
Swimming PoolYes100%
GymYes100%
ParksYes100%
Power BackupYes100%
Piped GasNoNot applicable
Water and SanitationYes100%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesYes100%
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallNoNot applicable
Open parking areasYes100%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership8

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area22,334 sq m
Named landowners8
LandownerVillageDistrict
Katta Chandrashekar Reddy--
Jawahar Gopal--
Y Lakshmi Reddy--
Sandeep Reddy--
Y Lakshmi Reddy--
Sandeep Reddy--
Jawahar Gopal--
Katta Chandrashekar Reddy--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 212.33 cr
Cost incurredRs 233.60 cr
Spent of the estimate110.02%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 131.50 crRs 138.99 cr
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 34.57 crRs 32.18 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 18.08 crRs 12.44 cr
Payment of taxesRs 13.66 crRs 25.07 cr
On-site expenditure-Site OverheadRs 12.12 crRs 17.67 cr
On-site expenditure-Consultants FeesRs 2.39 crRs 4.00 cr
On-site expenditure-Salaries of workers-Rs 3.24 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectZachariah Consultants
EngineerDesign Ventures Engineering Consultants (I) Pvt Ltd
Chartered AccountantM Padmanabha Bhat

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/446/PR/250627/004706Jun 2025 → Dec 2025

Reason as filed by the promoterForce Majeure; Shortage of Labour; Transport strike - Delay in Delivery of Material; Shortage of Building Materials, Concrete, Jalli etc; others; others; others; others; Force Majeure; Force Majeure; Force Majeure; Force Majeure; Shortage of Labour; Force Majeure; Force Majeure; Shortage of Building Materials, Concrete, Jalli etc; others; Force Majeure; Shortage of Labour

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed124

As listed on the registration, under the names the promoter filed them with; the newest 80 of 124 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/140222/004706 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Prestige Green Gable.pdf6 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Prestige Green Gable.PDF6 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Prestige Green Gable.pdf6 Jan 2026
Q3 2025-26 Water supply and sewage board6 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)6 Jan 2026
Q3 2025-26 KPTCL- BESCOM6 Jan 2026
Q3 2025-26 Fire and Safety6 Jan 2026
Q3 2025-26 Airport Authority of India6 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department6 Jan 2026
1. BWSSB NOC AttachedFile: BWSSB NOC.pdf8 Feb 2022
1.1) BWSSB affidavit attachedFile: Affidavit - PGG BWSSB.pdf13 Jan 2022
1.2) Drawing AttachedFile: Green gables - Marking in SIte Plan_compressed.pdf13 Jan 2022
1.2) Drawing AttachedFile: RESIDENTIAL BUILDING - COMBINED BASEMENT FLOOR PLAN.PDF13 Jan 2022
1.2) Drawing AttachedFile: RESIDENTIAL BUILDING - GROUND FLOOR PLAN.PDF13 Jan 2022
1.2) Drawing AttachedFile: RESIDENTIAL BUILDING - FIRST FLOOR PLAN.PDF13 Jan 2022
1.2) Drawing AttachedFile: RESIDENTIAL BUILDING - SECOND FLOOR PLAN.PDF13 Jan 2022
1.2) Drawing AttachedFile: RESIDENTIAL BUILDING - THIRD FLOOR PLAN & CLUB HOUSE SECTION.PDF13 Jan 2022
1.2) Drawing AttachedFile: RESIDENTIAL BUILDING - TYPICAL 4th TO 9th & 12th FLOOR PLAN.PDF13 Jan 2022
1.2) Drawing AttachedFile: RESIDENTIAL BUILDING - TENTH FLOOR PLAN.PDF13 Jan 2022
1.2) Drawing AttachedFile: RESIDENTIAL BUILDING - ELEVENTH FLOOR.PDF13 Jan 2022
1.2) Drawing AttachedFile: RESIDENTIAL BUILDING - TERRACE FLOOR PLAN.PDF13 Jan 2022
1.2) Drawing AttachedFile: RESIDENTIAL BUILDING - ELEVATION 01 & SECTION.PDF13 Jan 2022
1.2) Drawing AttachedFile: RESIDENTIAL BUILDING - ELEVATION 02 & SECTION 02.PDF13 Jan 2022
1.2) Drawing AttachedFile: RESIDENTIAL BUILDING - ELEVATION 03 & SECTION 03.PDF13 Jan 2022
1.2) Drawing AttachedFile: RESIDENTIAL BUILDING - ELEVATION 04 & SECTION 02.PDF13 Jan 2022
1.1) Attaching BWSSB demand note and payment receipt also.File: BWSSB - Demand Note & Payment Made.pdf13 Jan 2022
1.1 Demand Note & Fee paid Acknowledgement of BWSSB Attached.File: BWSSB - Demand Note & Payment Made.pdf5 Jan 2022
Affidavit stating BWSSB NOC shall be furnished to RERA during quarterly update is attached.File: Affidavit - PGG BWSSB.pdf5 Jan 2022
1.1. Non litigation affidavit attachedFile: Affidavit - Litigation.pdf23 Dec 2021
1.2. Joint affidavit signed by owner and developer attachedFile: Affidavit cum Declaration - New.pdf23 Dec 2021
2.1 Residential area marked in the site planFile: Green gables - Marking in SIte Plan_compressed.pdf23 Dec 2021
2.2 Clear sections and elevations attachedFile: Green Gables - Sections & elevations merged.pdf23 Dec 2021
3.2. BWSSB demand note and court order attachedFile: BWSSB Demand & Order.pdf23 Dec 2021
3.3 Draft sale deed attached. Specifications will be a part of sale agreement only.File: Draft Sale Deed Green Gables (RERA) - PG 03122021.pdf23 Dec 2021
3.4 STP as shown in the upper basement of sanction plan. Drawing attached.File: For STP- Green Gables.pdf23 Dec 2021
RTC, survey 89/2-
Mutation, survey 89/2-
Encumbrance Certificate, survey 89/2-
Conversion/Alienation Order, survey 89/2-
Sale/Title/Gift Deed, survey 89/2-
JDA, survey 89/2-
Khatha, survey 89/2-
RTC, survey 89/3-
Mutation, survey 89/3-
Encumbrance Certificate, survey 89/3-
Conversion/Alienation Order, survey 89/3-
Sale/Title/Gift Deed, survey 89/3-
JDA, survey 89/3-
Khatha, survey 89/3-
RTC, survey 89/4-
Mutation, survey 89/4-
Encumbrance Certificate, survey 89/4-
Conversion/Alienation Order, survey 89/4-
Sale/Title/Gift Deed, survey 89/4-
JDA, survey 89/4-
Khatha, survey 89/4-
Registration CertificateFile: COI PEPL.pdf-
Organization StructureFile: Org Chart.pdf-
Certificate issued by CA Form 1File: Form 01 - Green Cable CA.pdf-
Certificate issued by Architect Form 2File: Form 02 - Green Cable Architect_compressed.pdf-
Certificate issued by Engineer Form 3File: Form 03 - Green Cable Engineer_compressed.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit Cum Declaration - PGG.pdf-
Certificate from Chartered AccountFile: Form 01 - Green Cable CA.pdf-
Balance Sheet 2020 - 2021File: BS PEPL 2021.pdf-
Balance Sheet 2019 - 2020File: BS PEPL 2020.pdf-
Balance Sheet 2018 - 2019File: BS PEPL 2019.pdf-
Audited Profit and Loss Statement 2020 - 2021File: PL PEPL 2021.pdf-
Audited Profit and Loss Statement 2019 - 2020File: PL FY 19-20 PEPL.pdf-
Audited Profit and Loss Statement 2018 - 2019File: PL PEPL 2019.pdf-
Director's Report 2020 - 2021File: Board Report PEPL 2021.pdf-
Director's Report 2019 - 2020File: Board Report 2020.pdf-
Director's Report 2018 - 2019File: Director's Report 2019.pdf-
Cash Flow Statement 2020 - 2021File: CFS PEPL 2021.pdf-
Cash Flow Statement 2019 - 2020File: CFS PEPL 2020.pdf-
Auditor's Report 2020 - 2021File: Audit Report AR 2021.pdf-
Auditor's Report 2019 - 2020File: Audit Report 2020.pdf-
Auditor's Report 2018 - 2019File: Audit Report PEPL 2019_compressed.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Prestige WestwoodsNO. 19/12, MINERVA MILLS QUARTERS, MYSORE DEVISTION ROAD, , OKALIPURAMCompleted-No date filed

How this compares with Bengaluru Urban

100%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 6 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Prestige Green Gables on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmPrestige Green GablesOther 22Dot size: filed unitsN

Filed coordinates, straight-line distance. 22 registered projects within 2 km.

Builder: PRESTIGE ESTATES PROJECTS LTD

PRESTIGE ESTATES PROJECTS LTD has 19 registrations on RERA Karnataka, including PRESTIGE GARDENIA ESTATE PHASE 2 and Prestige Gardenia Estate. Its filings declare 7 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Prestige Green Gables is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Prestige Green Gables?

The registered promoter entity is PRESTIGE ESTATES PROJECTS LTD, a company as per the filing. Its CIN U07010KA1997PLC022322 and GSTIN 29AABCP8096K1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Prestige Green Gables?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Prestige Green Gables?

The professionals named in the filing: Architect: Zachariah Consultants; Engineer: Design Ventures Engineering Consultants (I) Pvt Ltd; Chartered Accountant: M Padmanabha Bhat. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Prestige Green Gables?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Prestige Green Gables. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Prestige Green Gables to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.