ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / Prestige Elm Park

Registration approved No litigation declared Residential/Group Housing project

Prestige Elm Park

By PRESTIGE ESTATES PROJECTS LTD

RG-KA-38014 · RERA PRM/KA/RERA/1251/446/PR/250123/005667 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Aug 2026Possession promisedno revision filed
8 of 18Construction stages donefurthest along: Railing and Grill fixing, 95%
49 of 192Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 120 documents Report an error

Prestige Elm Park is a Residential/Group Housing project by PRESTIGE ESTATES PROJECTS LTD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/250123/005667 on 25 Jan 2023. Possession is promised by 14 Aug 2026. 143 of the 192 units on this registration are recorded sold or booked, and 8 of 18 construction stages are filed complete.

At a glance

Project

  • NamePrestige Elm Park
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560049
  • Pincode560049
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/250123/005667
  • ReraGenie IDRG-KA-38014

Builder

  • NamePRESTIGE ESTATES PROJECTS LTD
  • Entity typeCompany
  • CINU07010KA1997PLC022322
  • GSTIN29AABCP8096K1ZP
  • Authorized SignatorySwaroop Anish
  • CmdIrfan Razack
  • Directors1, REZWAN RAZACK, NOAMAN RAZACK
  • Project HeadRaghavendra N
  • Other registrations18 more →
  • Declared earlier projects7 →

Key dates

this monthRegisteredJan 2023PromisedAug 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on25 Jan 2023
  • Promised completion14 Aug 2026
  • Revised completionNone
  • Buildings3 building records
  • Documents filed120 files

Current status

74%143 of 192 units booked
105.0%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 1---72072
Tower 2---48048
Tower 3---72072

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 18 construction stages are filed complete. The stage furthest along is Railing and Grill fixing, at 95%.

Building: 89% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc90%
Basic work of Water supply, Sanitary and Electrification80%
Dadoing, Skirting, Flooring, Tiles work (All types)90%
Railing and Grill fixing95%
Electrification, Water supply and Sanitary Finishing80%
Painting70%
Fire prevention and fire fighting fitting and fixture with network75%
Weather Proof work(tile,concrete)80%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work70%
Internal and External work including landscapes as per sanctioned drawings70%

Progress on shared amenities41

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes70%
Sewage and Drainage SystemYes80%
Water conservation/rain water harvesting/recharge of ground waterYes70%
Energy managementYes50%
Fire protection and fire safety requirementsYes70%
Solid waste management and disposalYes70%
Emergency Evacuation servicesYes70%
Internal Roads & FootpathsYes70%
Electricity supply transformer and substationNoNot applicable
Storm water drainsYes85%
Use of renewable energyYes50%
Sewage Treatment Plant (STP)Yes80%
Parks & Tree plantingYes50%
Street LightingYes50%
Electricity supply transformerYes75%
ElectricityYes50%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes70%
Club HouseYes85%
Community HallYes90%
Outdoor Sports facilityYes85%
Indoor Sports facilityYes85%
Swimming PoolYes90%
GymYes90%
ParksYes50%
Power BackupYes50%
Piped GasNoNot applicable
Water and SanitationYes75%
Air ConditioningNoNot applicable
StaircasesYes80%
LiftsYes75%
Corridor/LobbiesYes75%
Fire escapesYes80%
Common entrance and exit for the building/common portico/foyer/verandahYes70%
BasementYes75%
TerraceYes85%
Outer WallYes99%
Open parking areasYes65%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes75%
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area16,120 sq m
Named landowners1
LandownerVillageDistrict
Gaffar Baig--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 161.26 cr
Cost incurredRs 169.38 cr
Spent of the estimate105.03%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 161.26 crRs 127.12 cr
On-site expenditure-Consultants Fees-Rs 1.42 cr
On-site expenditure-Site Overhead-Rs 9.83 cr
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)-Rs 16.88 cr
Payment of taxes-Rs 13.82 cr
Principal sum and interest payable to financial institutions-Scheduled Banks-Rs 30.00 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectZachariah Consultants
EngineerPrasad Consultants
Chartered AccountantM Padmanabha Bhat

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed120

As listed on the registration, under the names the promoter filed them with; the newest 80 of 120 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/250123/005667 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Q2 2026-27.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Q2 2026-27.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Q2 2026-27.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q2 2026-27 Fire and Safety14 Oct 2026
Q2 2026-27 Airport Authority of India14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Q1 2026-27 Elm Park.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Q1 2026-27 Elm Park.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Q1 2026-27 Elm Park.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Q4 Elm Park.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Q4 Elm Park.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Q4 Elm Park.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Q3 Elm Park.pdf15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Q3 Elm Park.pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Q3 Elm Park.pdf15 Jan 2026
Q3 2025-26 Water supply and sewage board15 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)15 Jan 2026
Q3 2025-26 KPTCL- BESCOM15 Jan 2026
Q3 2025-26 Fire and Safety15 Jan 2026
Q3 2025-26 Airport Authority of India15 Jan 2026
Allotment letter with specificationsFile: Allotment letter new 19 01 23.pdf19 Jan 2023
Affidavit along with payment receipts made to BWSSBFile: Affidavit and BWSSB Demand note new 19 1 23.pdf19 Jan 2023
No litigation AffidavitFile: 1 Affidavit No Litigation Prestige Elm Park.pdf11 Jan 2023
OpinionFile: 2 Opinion UProcess.pdf11 Jan 2023
Joint AffidavitFile: 3 Joint Affidavit cum Declaration Prestige Elm Park.pdf11 Jan 2023
Guidelines valueFile: 4 Guidelines value -project near Elm.pdf11 Jan 2023
Sanction level floor planFile: 1A1 Elm Park level Floor Plans compressed.pdf11 Jan 2023
Village mapFile: 1A4 Elm Park Village Map.pdf11 Jan 2023
CDP mapFile: 1A5 Elm Park CDP Landuse.pdf11 Jan 2023
SpecificationsFile: 2A2 Elm project Specifications.pdf11 Jan 2023
Engineer Structural safety certificateFile: 2A3 Elm Park Structural saftey stability certificate.pdf11 Jan 2023
Allotment letterFile: 2A5 Elm Park Allotment letter 09 012023.pdf11 Jan 2023
Sec 3 (1)AffidavitFile: 2A6 Sec 3 1 Afidavit.pdf11 Jan 2023
BESCOM NOC along with fee receiptFile: 2A7 BESCOM NOC with fee receipt.pdf11 Jan 2023
KSFES NOC along with fee receiptFile: 2A7 KSFES NOC with fee receipt.pdf11 Jan 2023
BWSSB Demand note with AffidavitFile: 2A8 BWSSB Demand note.pdf11 Jan 2023
STP drawingFile: 2A9 Elm Park STP.pdf11 Jan 2023
STP demarcationFile: 2A9 Elm Park STP1 demarcation.pdf11 Jan 2023
RTC, survey 142-
Mutation, survey 142-
Encumbrance Certificate, survey 142-
Conversion/Alienation Order, survey 142-
Sale/Title/Gift Deed, survey 142-
JDA, survey 142-
Khatha, survey 142-
Registration CertificateFile: COI PEPL.pdf-
Organization StructureFile: Org Chart.pdf-
Certificate issued by CA Form 1File: Form 1 ELM Park PEPL.pdf-
Certificate issued by Architect Form 2File: Form 2 ELM Park PEPL.pdf-
Certificate issued by Engineer Form 3File: Form 3 ELM Park PEPL.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit No Litigation Prestige Elm Park.pdf-
Certificate from Chartered AccountFile: Form 1 ELM Park PEPL.pdf-
Balance Sheet 2021 - 2022File: BS 2122 PEPL.pdf-
Balance Sheet 2020 - 2021File: BS PEPL 2021.pdf-
Balance Sheet 2019 - 2020File: BS PEPL 2020.pdf-
Audited Profit and Loss Statement 2021 - 2022File: PL 2122 PEPL.pdf-
Audited Profit and Loss Statement 2020 - 2021File: PL PEPL 2021.pdf-
Audited Profit and Loss Statement 2019 - 2020File: PL FY 19-20 PEPL.pdf-
Director's Report 2021 - 2022File: Board Report 2122 PEPL.pdf-
Director's Report 2020 - 2021File: Board Report PEPL 2021.pdf-
Director's Report 2019 - 2020File: Board Report 2020.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
PRESTIGE WATERFORDPATTANDURA AGRAHARA VILLAGE. K. R. PURAM HOBLI, BENGALURU EASTOngoingDec 2023Not delivered

How this compares with Bengaluru Urban

74%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Prestige Elm Park on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmPrestige Elm ParkOther 45Dot size: filed unitsN

Filed coordinates, straight-line distance. 45 registered projects within 2 km.

Builder: PRESTIGE ESTATES PROJECTS LTD

PRESTIGE ESTATES PROJECTS LTD has 19 registrations on RERA Karnataka, including PRESTIGE GARDENIA ESTATE PHASE 2 and Prestige Gardenia Estate. Its filings declare 7 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Prestige Elm Park is delayed beyond 14 Aug 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Prestige Elm Park?

The registered promoter entity is PRESTIGE ESTATES PROJECTS LTD, a company as per the filing. Its CIN U07010KA1997PLC022322 and GSTIN 29AABCP8096K1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Prestige Elm Park?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Prestige Elm Park?

The professionals named in the filing: Architect: Zachariah Consultants; Engineer: Prasad Consultants; Chartered Accountant: M Padmanabha Bhat. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Prestige Elm Park?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Prestige Elm Park. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Prestige Elm Park to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.