ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / PRAMUKH SQUARE

Valid until 30 Sep 2022 Commercial project

PRAMUKH SQUARE

By SHIVAM INFRASTRUCTURE

RG-GJ-56793 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA05274/A2C/140722 · Last updated on GujRERA portal: 28 Mar 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Sep 2022Possession promisedno revision filed
8 of 9Construction stages donefurthest along: Stilt Floor, 0%
25 of 97Units unsoldnot recorded sold or booked
Jump to the 45 documents Report an error

PRAMUKH SQUARE is a Commercial project by SHIVAM INFRASTRUCTURE in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA05274/A2C/140722 on 12 Apr 2019. Possession is promised by 30 Sep 2022. 72 of the 97 units on this registration are recorded sold or booked, and 8 of 9 construction stages are filed complete.

At a glance

Project

  • NamePRAMUKH SQUARE
  • TypeCommercial
  • Location
    • SURVEY NO. 157A
    • OPP. AASHKA HOSPITAL
    • RAKSHASHAKTI SARGASAN MAIN ROAD
    • SARGASAN
    • GANDHINAGAR
    • SARGASAN
    • Gandhinagar
    • 382421
  • Pincode382421
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA05274/A2C/140722
  • ReraGenie IDRG-GJ-56793

Builder

  • NameSHIVAM INFRASTRUCTURE
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredApr 2019PromisedSep 2022

Key facts

Registration and timeline

  • StatusValid until 30 Sep 2022
  • Registered on12 Apr 2019
  • Promised completion30 Sep 2022
  • Revised completionNone
  • Buildings1 building record
  • Documents filed45 files

Current status

74%72 of 97 units booked
100.0%Of the estimated cost spent so far

Figures as on 28 Mar 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---09697

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 28 Mar 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 9 construction stages are filed complete. The stage furthest along is Stilt Floor, at 0%.

A: 89% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 28 Mar 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesYes0%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,903 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 31.25 cr
Cost incurredRs 31.25 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
ANARs 31.25 crRs 31.25 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBhaumikkumar Chandravadanbhai Donga
EngineerBHARAT MAFATLAL OZA

Documents filed45

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/CAA05274/A2C/140722 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)28 Mar 2024
Engineer's certificate (Form 2)27 Mar 2024
Engineer's certificate annexure27 Mar 2024
Architect's certificate (Form 1)5 Mar 2024
Site photograph, A5 Mar 2024
Site photograph, A5 Mar 2024
Site photograph, A5 Mar 2024
Site photograph, A5 Mar 2024
RERA registration certificate12 Apr 2019
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Approved building or plotting plan-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

74%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep PRAMUKH SQUARE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near SARGASAN1,600+ in Gandhinagar

2 kmPRAMUKH SQUAREOther 253Dot size: filed unitsN

Filed coordinates, straight-line distance. 253 registered projects within 2 km.

Builder: SHIVAM INFRASTRUCTURE

SHIVAM INFRASTRUCTURE has 1 registration on GujRERA, including PRAMUKH SQUARE. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if PRAMUKH SQUARE is delayed beyond 30 Sep 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of PRAMUKH SQUARE?

The registered promoter entity is SHIVAM INFRASTRUCTURE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in PRAMUKH SQUARE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at PRAMUKH SQUARE?

The professionals named in the filing: Architect: Bhaumikkumar Chandravadanbhai Donga; Engineer: BHARAT MAFATLAL OZA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PRAMUKH SQUARE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PRAMUKH SQUARE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PRAMUKH SQUARE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.