ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / Pramukh Nagar

Valid until 30 Apr 2027 Residential/Group Housing project

Pramukh Nagar

By PRAMUKH DEVELOPERS

RG-GJ-31295 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA02851/EX3/EX5/020226/310326 · Last updated on GujRERA portal: 22 Dec 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 72 months
  • 6 extensions taken

Clear

  • Nothing verified clear yet
Apr 2027Possession promisedmoved 72 months from the original
53 of 54Construction stages doneacross 6 buildings; furthest along: Installation of lifts, 90%
67 of 348Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

Pramukh Nagar is a Residential/Group Housing project by PRAMUKH DEVELOPERS in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA02851/EX3/EX5/020226/310326 on 7 Jun 2018. Possession is promised by 30 Apr 2027. The completion date has moved by 72 months from the original filing. 281 of the 348 units on this registration are recorded sold or booked, and 53 of 54 construction stages are filed complete.

At a glance

Project

  • NamePramukh Nagar
  • TypeResidential/Group Housing
  • Location
    • Survey No 133
    • Gandhinagar Mansa Road
    • Randheja
    • Gandhinagar
    • 382620
  • Pincode382620
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA02851/EX3/EX5/020226/310326
  • ReraGenie IDRG-GJ-31295

Builder

  • NamePRAMUKH DEVELOPERS
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredJun 2018First promiseApr 2021Revised toApr 2027

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2027
  • Registered on7 Jun 2018
  • Promised completion30 Apr 2027
  • Revised completionRevised to 30 Apr 2027 (originally 30 Apr 2021)
  • Buildings6 building records
  • Documents filed43 files

Current status

81%281 of 348 units booked
88.1%Of the estimated cost spent so far

Figures as on 22 Dec 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
D+E---56056
F+G+H---84084
I+J---68068
K+L---56056
A---28028
B+C---56056

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building6

As on 22 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

53 of 54 construction stages are filed complete across 6 buildings. The stage furthest along is Installation of lifts, at 90%.

D+E100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
F+G+H100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
I+J99%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing90%
K+L100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
A100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
B+C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 22 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes20%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,246 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 38.50 cr
Cost incurredRs 33.92 cr
Spent of the estimate88.09%
BuildingWingEstimatedIncurred
F+G+HNARs 9.24 crRs 9.24 cr
I+JNARs 7.64 crRs 3.06 cr
B+CNARs 6.16 crRs 6.16 cr
K+LNARs 6.16 crRs 6.16 cr
D+ENARs 6.12 crRs 6.12 cr
ANARs 3.18 crRs 3.18 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRonak L Joshi
EngineerAmee Associates

Extensions applied for6

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA02851/A1R/EX1/300621Applied Apr 2021; approved Jun 2021
PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA02851/EX2/EX1/011022Applied Sep 2022; approved Oct 2022
PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA02851/EX3/EX1/061023Applied Sep 2023; approved Oct 2023
PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA02851/EX3/EX4/090924/290425Applied Jun 2024; approved Sep 2024
PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA02851/EX3/EX5/020226/310326Applied Aug 2025; approved Feb 2026
ExtensionApplied Apr 2026; no approval date filed

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA02851/EX3/EX5/020226/310326 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)22 Dec 2025
Engineer's certificate (Form 2)17 Dec 2025
Engineer's certificate annexure17 Dec 2025
Architect's certificate (Form 1)15 Dec 2025
Site photograph, D+E9 Dec 2025
Site photograph, F+G+H9 Dec 2025
Site photograph, I+J9 Dec 2025
Site photograph, K+L9 Dec 2025
Site photograph, A9 Dec 2025
Site photograph, B+C9 Dec 2025
RERA registration certificate7 Jun 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

81%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one moved by 72 months

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep Pramukh Nagar on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Randheja1,600+ in Gandhinagar

2 kmPramukh NagarOther 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 25 registered projects within 2 km.

Builder: PRAMUKH DEVELOPERS

PRAMUKH DEVELOPERS has 1 registration on GujRERA, including Pramukh Nagar. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if Pramukh Nagar is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Pramukh Nagar?

The registered promoter entity is PRAMUKH DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Pramukh Nagar?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Pramukh Nagar?

The professionals named in the filing: Architect: Ronak L Joshi; Engineer: Amee Associates. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Pramukh Nagar?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Pramukh Nagar. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Pramukh Nagar to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.