Home / Browse projects / Gandhinagar, Gujarat / POSH VILLE BY SAAMARTH

Valid until 30 Apr 2027 Residential/Group Housing project

POSH VILLE BY SAAMARTH

By SPV CORPORATION

RG-GJ-58357 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RN363AA10263/181023 · Last updated on GujRERA portal: 5 May 2026

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Apr 2027Possession promisedno revision filed
16 of 45Construction stages doneacross 5 buildings; furthest along: External plumbing and external plaster, 99%
14 of 24Units unsoldnot recorded sold or booked
Jump to the 34 documents Report an error

POSH VILLE BY SAAMARTH is a Residential/Group Housing project by SPV CORPORATION in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RN363AA10263/181023 on 18 Oct 2023. Possession is promised by 30 Apr 2027. 10 of the 24 units on this registration are recorded sold or booked, and 16 of 45 construction stages are filed complete.

At a glance

Project

  • NamePOSH VILLE BY SAAMARTH
  • TypeResidential/Group Housing
  • Location
    • NEAR SHREEJI 9 BUNGLOWS
    • RAYSAN ROAD RAYSAN
    • RAYSAN
    • Gandhinagar
    • 382007
  • Pincode382007
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RN363AA10263/181023
  • ReraGenie IDRG-GJ-58357

Builder

  • NameSPV CORPORATION
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredOct 2023PromisedApr 2027

Key facts

Registration and timeline

  • StatusValid until 30 Apr 2027
  • Registered on18 Oct 2023
  • Promised completion30 Apr 2027
  • Revised completionNone
  • Buildings5 building records
  • Documents filed34 files

Current status

42%10 of 24 units booked
71.4%Of the estimated cost spent so far

Figures as on 5 May 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Type - A---101
Type - B---11011
Type - C---101
Type - D---101
Type - E---10010

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building5

As on 5 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 45 construction stages are filed complete across 5 buildings. The stage furthest along is External plumbing and external plaster, at 99%.

Type - A62%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats10%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
Type - B67%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats90%
Sanitary fittings within the flats40%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
Type - C65%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats95%
Sanitary fittings within the flats15%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing99%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
Type - D59%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats10%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
Type - E59%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats10%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks55%
External plumbing and external plaster, elevation, completion of terraces with waterproofing95%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%

Progress on shared amenities19

As on 5 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes95%
Water supplyYes95%
Sewerage (chamber, lines, septic tank, STP)Yes90%
Storm water drainsYes94%
Landscaping and tree plantingYes95%
Street lightingYes95%
Community buildingsYes95%
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes90%
Energy managementYes10%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes95%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area14,467 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 44.00 cr
Cost incurredRs 31.44 cr
Spent of the estimate71.44%
BuildingWingEstimatedIncurred
Type - BNARs 20.89 crRs 15.79 cr
Type - ENARs 17.48 crRs 11.69 cr
Type - ANARs 1.96 crRs 1.37 cr
Type - CNARs 1.96 crRs 1.44 cr
Type - DNARs 1.71 crRs 1.13 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNiyatibahen Mahendrakumar Mistry
EngineerUMANG PATEL

Documents filed34

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Gandhinagar Municipal Corporation/RN363AA10263/181023 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)5 May 2026
Engineer's certificate (Form 2)5 May 2026
Engineer's certificate annexure5 May 2026
Accountant's certificate (Form 3)5 May 2026
Site photograph, Type - A24 Apr 2026
Site photograph, Type - B24 Apr 2026
Site photograph, Type - C24 Apr 2026
Site photograph, Type - D24 Apr 2026
Site photograph, Type - E24 Apr 2026
RERA registration certificate18 Oct 2023
Proforma agreement for sale-
Auditor's report (3 of 3)-
Income tax return (3 of 3)-
Project specific document-
Drainage affidavit-
Directors' report (3 of 3)-
Approved sanctioned plan-
Approved layout plan-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Declaration in Form B-
Approved building or plotting plan-
NOCs from authorities-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

42%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep POSH VILLE BY SAAMARTH on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near RAYSAN1,600+ in Gandhinagar

2 kmPOSH VILLE BY SAAMARTHOther 202Dot size: filed unitsN

Filed coordinates, straight-line distance. 202 registered projects within 2 km.

Builder: SPV CORPORATION

SPV CORPORATION has 1 registration on GujRERA, including POSH VILLE BY SAAMARTH. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if POSH VILLE BY SAAMARTH is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of POSH VILLE BY SAAMARTH?

The registered promoter entity is SPV CORPORATION, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in POSH VILLE BY SAAMARTH?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at POSH VILLE BY SAAMARTH?

The professionals named in the filing: Architect: Niyatibahen Mahendrakumar Mistry; Engineer: UMANG PATEL. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in POSH VILLE BY SAAMARTH?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About POSH VILLE BY SAAMARTH. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save POSH VILLE BY SAAMARTH to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.