Home / Browse projects / Dakshina Kannada, Karnataka / POONAM SINDOORNIKETHAN

Registration approved No litigation declared Mixed Development project

POONAM SINDOORNIKETHAN

By POONAM BUILDERS

RG-KA-87508 · RERA PRM/KA/RERA/1257/334/PR/070226/008461 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Nov 2028Possession promisedno revision filed
3 of 16Construction stages donefurthest along: Upto Plinth Level, 80%
12 of 19Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 79 documents Report an error

POONAM SINDOORNIKETHAN is a Mixed Development project by POONAM BUILDERS in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/070226/008461 on 7 Feb 2026. Possession is promised by 30 Nov 2028. 7 of the 19 units on this registration are recorded sold or booked, and 3 of 16 construction stages are filed complete.

At a glance

Project

  • NamePOONAM SINDOORNIKETHAN
  • TypeMixed Development
  • Location
    • Mangalore
    • Dakshina Kannada
    • 560003
  • Pincode560003
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/070226/008461
  • ReraGenie IDRG-KA-87508

Builder

  • NamePOONAM BUILDERS
  • Entity typePartnership Firm
  • GSTIN29AANFP2436Q1ZF
  • Authorized SignatoryK. DAMODAR SHENOY
  • Other registrations10 more →
  • Declared earlier projects10 →

Key dates

this monthRegisteredFeb 2026PromisedNov 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on7 Feb 2026
  • Promised completion30 Nov 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed79 files

Current status

37%7 of 19 units booked
15.0%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
POONAM SINDOOR NIKETHAN-----19

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 16 construction stages are filed complete. The stage furthest along is Upto Plinth Level, at 80%.

Building: 36% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level80%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)80%
RCC or MS Framed structure70%
Masonry Construction20%
Plastering inside , outside & Ceiling10%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification10%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes15%
Sewage and Drainage SystemYes15%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingNoNot applicable
Street LightingYes0%
ElectricityYes10%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes15%
LiftsYes15%
Corridor/LobbiesYes15%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes15%
BasementYes15%
TerraceYes0%
Outer WallYes10%
Open parking areasYes10%
Provision for lodging of management staff and security staffYes10%
Water conservation and renewable energyYes10%
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area647 sq m
Named landowners1
LandownerVillageDistrict
POONAM BUILDERS--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 6.02 cr
Cost incurredRs 90.35 lakh
Spent of the estimate15.0%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 6.02 crRs 90.35 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPOOJA SHENOY
EngineerK. DAMODAR SHENOY
Chartered AccountantShravan Kumar

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed79

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/070226/008461 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA CERTIFICATE.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: FORM -5.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM -6.pdf14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA CERTIFICATE.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: ARCHITECT CERTIFICATE.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: ENGINEER CERTIFICATE.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form4_Q4_25_26_Sindoornikethan.pdf11 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form5_Q4_25_26_Sindoornikethan.pdf11 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form6_Q4_25_26_Sindoornikethan.pdf11 Apr 2026
Q4 2025-26 Water supply and sewage board11 Apr 2026
Q4 2025-26 KPTCL- BESCOM11 Apr 2026
water supply NOCFile: WATER NOC.pdf2 Feb 2026
RTC, survey 619-
Mutation, survey 619-
Encumbrance Certificate, survey 619-
Conversion/Alienation Order, survey 619-
Sale/Title/Gift Deed, survey 619-
Khatha, survey 619-
Registration CertificateFile: firm egistration certificate.pdf-
GST CertificateFile: GST.pdf-
Partnership DeedFile: deed of partnership.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form1_Sindoornikethan.pdf-
Certificate issued by Architect Form 2File: Form2_Sindoornikethan.pdf-
Certificate issued by Engineer Form 3File: Form3_Sindoornikethan.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit for non litigation on land.pdf-
Balance Sheet 2024 - 2025File: BS AY 2025-26.pdf-
Balance Sheet 2023 - 2024File: BS AY 2024-25.pdf-
Balance Sheet 2022 - 2023File: BS AY 2023-24.pdf-
Audited Profit and Loss Statement 2024 - 2025File: PL AY 2025-26.pdf-
Audited Profit and Loss Statement 2023 - 2024File: PL AY 2024-25.pdf-
Audited Profit and Loss Statement 2022 - 2023File: PL AY 2023-24.pdf-
Income Tax Return Acknowledgement 2024 - 2025File: ITR AY 2025-26.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: ITR AY 2024-25.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ITR AY 2023-24.pdf-
License-
Approved plan-
Single Site-
Stability certificate with Mtech-
Specification-
Brochure-
proforma AOS-
proforma allottment letter-
form b-
Affidavit 3(1)-
Legal Search Report-
Mescom-
Water NOC applied-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
CDP-
FAR-
Location map-
Demarcation Plan-
TDR Certificate & Utilization Certificate-
Title deed-
mescom fee receipt-
UGD NOC-
Kodialbail village map-
village map site highlighted-
estimation-
carpet area statement-
land cost with guidance value-
STP drawing-

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 under way, not due yet1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
POONAM RATNA NIKETHANPROPOSED PLAN SHOWING THE CONSTRUCTION OF A COMMERCIAL CUM RESIDENTIAL APARTMENT BUILDING IN , S.NO. 249/1, 90 A, BOLOOR VILLAGE, MANGALURUOngoingDec 2028Not due yet
POONAM CHANDRA NIKETHANPLAN SHOWING THE CONTRUCTION OF A COMMERCIAL CUM RESIDENTIAL APARTMENT BUILDING IN , S.N.29/2C(P) AT DEREBAIL VILLAGE MANGALORECompleted-No date filed

How this compares with Dakshina Kannada

37%of this project is bookeddistrict median 38%
30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep POONAM SINDOORNIKETHAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmPOONAM SINDOORNIKETHANOther 110Dot size: filed unitsN

Filed coordinates, straight-line distance. 110 registered projects within 2 km.

Builder: POONAM BUILDERS

POONAM BUILDERS has 11 registrations on RERA Karnataka, including POONAM SURYANIKETHAN and POONAM SINDOORNIKETHAN. Its filings declare 10 earlier projects, 7 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if POONAM SINDOORNIKETHAN is delayed beyond 30 Nov 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of POONAM SINDOORNIKETHAN?

The registered promoter entity is POONAM BUILDERS, a partnership firm as per the filing. Its GSTIN 29AANFP2436Q1ZF can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in POONAM SINDOORNIKETHAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at POONAM SINDOORNIKETHAN?

The professionals named in the filing: Architect: POOJA SHENOY; Engineer: K. DAMODAR SHENOY; Chartered Accountant: Shravan Kumar. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in POONAM SINDOORNIKETHAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About POONAM SINDOORNIKETHAN. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save POONAM SINDOORNIKETHAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.