Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2028Possession promisedno revision filed
5 of 18Construction stages donefurthest along: RCC or MS Framed structure, 77%
235 of 312Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 266 documents Report an error

POETRY OF EARTH is a Residential/Group Housing project by URBAN EXCELLENCE LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/281024/007183 on 28 Oct 2024. Possession is promised by 31 Dec 2028. 77 of the 312 units on this registration are recorded sold or booked, and 5 of 18 construction stages are filed complete.

At a glance

Project

  • NamePOETRY OF EARTH
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560087
  • Pincode560087
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/281024/007183
  • ReraGenie IDRG-KA-57395

Builder

  • NameURBAN EXCELLENCE LLP
  • Entity typePartnership Firm
  • LLPINAAY-1922
  • GSTIN29AAHFU0117D1ZH
  • Authorized SignatorySyam Sundar Madisetty

Key dates

this monthRegisteredOct 2024PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on28 Oct 2024
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings3 building records
  • Documents filed266 files

Current status

25%77 of 312 units booked
44.2%Of the estimated cost spent so far

Figures as on 23 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block A---1040104
Block B---1040104
Block C---1040104

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 23 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 18 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 77%.

Building: 32% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure77%
Masonry Construction5%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 23 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes48%
LiftsYes10%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes48%
TerraceYes0%
Outer WallYes0%
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesYes0%

Land and ownership9

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,488 sq m
Named landowners9
LandownerVillageDistrict
T Ravindra Kumar--
T Venugopal--
S Muralidhara--
S Madhukiran--
Sarojamma--
Shantha Kelwadi--
R Harish--
Chethan Babu R--
N Padmavathi--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 272.15 cr
Cost incurredRs 120.19 cr
Spent of the estimate44.16%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 230.10 crRs 113.32 cr
Payment of taxesRs 19.60 cr-
Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for constructionRs 16.00 cr-
Administrative CostsRs 3.50 cr-
On-site expenditure-Consultants FeesRs 2.95 crRs 1.20 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAR .SWAPNIL VALVATKAR
EngineerH P YOGESH
Chartered AccountantRakesh K S

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed266

As listed on the registration, under the names the promoter filed them with; the newest 80 of 266 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/281024/007183 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4_Quarterly_CA_Certificate_Q2.pdf23 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-4_Quarterly_CA_Certificate_Q2.pdf23 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6 Engineer's Certificate -September'26.pdf23 Oct 2026
Q2 2026-27 Water supply and sewage board23 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)23 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)23 Oct 2026
Q2 2026-27 KPTCL- BESCOM23 Oct 2026
Q2 2026-27 Fire and Safety23 Oct 2026
Q2 2026-27 Airport Authority of India23 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department23 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4_Quarterly_CA_Certificate_Q1.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: POE Form-5 Architect.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: 9 - Engineer's Certificate -June'26- LH signed - Copy.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA_Certificate_Q4_Signed.pdf27 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect's Certificate -March 26 POE.pdf27 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Eng Certificate -Mar 26.pdf27 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Signed Form 4- Q3.pdf20 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect's Certificate -Dec'25.pdf20 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: 7 - Engineer's Certificate -Dec'25- LH signed.pdf20 Feb 2026
Form 1 certificate_SignedFile: 1 Form 1 certificate_Signed.pdf25 Oct 2024
Bank AffidavitFile: 2 Bank Affidavit.pdf25 Oct 2024
Source of Funds with supporting docsFile: 3 Source of Funds with supporting docs.pdf25 Oct 2024
Proforma Agreement of SaleFile: 4 Proforma Agreement of Sale.pdf25 Oct 2024
Source of Funds with supporting docsFile: 1 Source of Funds with supporting docs.pdf4 Oct 2024
Plan Demarcation DetailsFile: 2 Plan Demarcation Details.pdf4 Oct 2024
Form 1 certificateFile: 3 Form 1 certificate.pdf4 Oct 2024
Partnership deed LLP agreementFile: 5 Partnership deed LLP agreement.pdf4 Oct 2024
RERA Collection AccountFile: 4 RERA Collection Account.pdf4 Oct 2024
REAR Designated accountFile: 4 REAR Designated account.pdf4 Oct 2024
Form-B AffidavitFile: 1 Form-B Affidavit.pdf4 Oct 2024
JD AffidavitFile: 2 JD Affidavit.pdf4 Oct 2024
Non-Litigation AffidavitFile: 3 Non-Litigation Affidavit.pdf4 Oct 2024
DP ApprovedFile: 1 DP Approved.pdf4 Oct 2024
DP Work OrderFile: 1 DP Work Order.pdf4 Oct 2024
Area Statement Certificate by ArchitectFile: 2 Area Statement Certificate by Architect.pdf4 Oct 2024
CDP DemarcationFile: 3 CDP Demarcation.pdf4 Oct 2024
Village Map DemarcationFile: 4 Village Map Demarcation.pdf4 Oct 2024
Clarification on Commencement CertificateFile: 5 Clarification on Commencement Certificate.pdf4 Oct 2024
BBMP BUILDING PLAN, SEC, ELEVATIONFile: 6 BBMP BUILDING PLAN, SEC, ELEVATION.pdf4 Oct 2024
POE - Amenities and Common areasFile: 7 POE - Amenities and Common areas.pdf4 Oct 2024
POE - Estimate BreakupFile: 8 POE - Estimate Breakup.pdf4 Oct 2024
Project Specification PoEFile: 9 Project Specification PoE.pdf4 Oct 2024
Sec 3(1) AffidavitFile: 10 Sec 3(1) Affidavit.pdf4 Oct 2024
Proforma Alottment LetterFile: 11 Proforma Alottment Letter.pdf4 Oct 2024
Proforma AOSFile: 12 Proforma AOS.pdf4 Oct 2024
STP Drawing signedFile: 13 STP Drawing signed.pdf4 Oct 2024
Structural Stability CertificateFile: 14 Structural Stability Certificate.jpeg4 Oct 2024
Land cost calculation SheetFile: 15 Land cost calculation Sheet.pdf4 Oct 2024
UE Master CollectionFile: 1 UE Master Collection.pdf3 Aug 2024
UE Designated AccountFile: 2 UE Designated Account.pdf3 Aug 2024
UE RERA AccountFile: 3 UE RERA Account.pdf3 Aug 2024
Form 1 CA CertificateFile: 5 Form 1 CA Certificate.pdf3 Aug 2024
RTC Sy No 199-1File: 1 RTC Sy No 199-1.pdf3 Aug 2024
RTC Sy No 199-6File: 2 RTC Sy No 199-6.pdf3 Aug 2024
RTC Sy No 199-7File: 3 RTC Sy No 199-7.pdf3 Aug 2024
RTC Sy No 199-8File: 4 RTC Sy No 199-8.pdf3 Aug 2024
RTC Sy No 199-9File: 5 RTC Sy No 199-9.pdf3 Aug 2024
RTC Sy No 199-2AFile: 6 RTC Sy No 199-2A.pdf3 Aug 2024
Phodi MR Sy No 199-8 9File: 7 Phodi MR Sy No 199-8 9 .pdf3 Aug 2024
Phodi MR Sy No 199-2AFile: 8 Phodi MR Sy No 199-2A.pdf3 Aug 2024
Phodi MR Sy No 199-6 7File: 9 Phodi MR Sy No 199-6 7.pdf3 Aug 2024
MR Sy No 199-1File: 10 MR Sy No 199-1.pdf3 Aug 2024
Hissa-Podi-199-8 and 199-9File: 11 Hissa-Podi-199-8 and 199-9.pdf3 Aug 2024
MR 40File: 12 MR 40.pdf3 Aug 2024
MR37File: 13 MR37.pdf3 Aug 2024
IHC 11File: 14 IHC 11.pdf3 Aug 2024
MR 199File: 15 MR 199.pdf3 Aug 2024
Release Deed - 2794 -03-09-2021File: 16 Release Deed - 2794 -03-09-2021.pdf3 Aug 2024
Sale deed 5537 -1995File: 17 Sale deed 5537 -1995.pdf3 Aug 2024
Title deed Sy no 199-3File: 18 Title deed Sy no 199-3.pdf3 Aug 2024
Release Deed 1875 - 07-08-2021File: 19 Release Deed 1875 - 07-08-2021.pdf3 Aug 2024
Sale Deed 5186 - 23-10-1999File: 20 Sale Deed 5186 - 23-10-1999.pdf3 Aug 2024
Sale deed 5533 -1995File: 21 Sale deed 5533 -1995.pdf3 Aug 2024

How this compares with Bengaluru Urban

25%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep POETRY OF EARTH on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmPOETRY OF EARTHOther 48Dot size: filed unitsN

Filed coordinates, straight-line distance. 48 registered projects within 2 km.

Builder: URBAN EXCELLENCE LLP

URBAN EXCELLENCE LLP has 1 registration on RERA Karnataka, including POETRY OF EARTH. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if POETRY OF EARTH is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of POETRY OF EARTH?

The registered promoter entity is URBAN EXCELLENCE LLP, a partnership firm as per the filing. Its LLPIN AAY-1922 and GSTIN 29AAHFU0117D1ZH can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in POETRY OF EARTH?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at POETRY OF EARTH?

The professionals named in the filing: Architect: AR .SWAPNIL VALVATKAR; Engineer: H P YOGESH; Chartered Accountant: Rakesh K S. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in POETRY OF EARTH?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About POETRY OF EARTH. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save POETRY OF EARTH to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.