Home / Browse projects / Vadodara, Gujarat / PARAM GREENS

Valid until 31 Oct 2019 Mixed Development project

PARAM GREENS

By AKSHAR CREATION

RG-GJ-87443 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA00368/EX1/071218 · Last updated on GujRERA portal: 7 Sep 2019

Source: official GujRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • Separate project account declared
Oct 2019Possession promisedmoved 12 months from the original
225 of 288Construction stages doneacross 32 buildings; furthest along: Sanitary fittings within the flats, 99%
12 of 190Units unsoldnot recorded sold or booked
Jump to the 70 documents Report an error

PARAM GREENS is a Mixed Development project by AKSHAR CREATION in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA00368/EX1/071218 on 7 Oct 2017. Possession is promised by 31 Oct 2019. The completion date has moved by 12 months from the original filing. 178 of the 190 units on this registration are recorded sold or booked, and 225 of 288 construction stages are filed complete.

At a glance

Project

  • NamePARAM GREENS
  • TypeMixed Development
  • Location
    • 30 MT. BILL CANAL ROAD
    • ALTRADRA PADRA MAIN ROAD
    • Bill
    • Vadodara
    • 391410
  • Pincode391410
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA00368/EX1/071218
  • ReraGenie IDRG-GJ-87443

Builder

  • NameAKSHAR CREATION
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredOct 2017First promiseOct 2018Revised toOct 2019

Key facts

Registration and timeline

  • StatusValid until 31 Oct 2019
  • Registered on7 Oct 2017
  • Promised completion31 Oct 2019
  • Revised completionRevised to 31 Oct 2019 (originally 31 Oct 2018)
  • Buildings32 building records
  • Documents filed70 files

Current status

94%178 of 190 units booked
100.0%Of the estimated cost spent so far

Figures as on 7 Sep 2019, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DUPLEX 12---101
TOWER C---221537
TRIPLEX 06---101
DUPLEX 01---101
DUPLEX 07---101
DUPLEX 13---101
TOWER D---161531
TRIPLEX 07---101
DUPLEX 02---101
DUPLEX 08---101
DUPLEX 14---101
TRIPLEX 01---101
TRIPLEX 08---101
DUPLEX 03---101
DUPLEX 09---101
DUPLEX 15---101
TRIPLEX 02---101
TRIPLEX 09---101
DUPLEX 04---101
DUPLEX 10---101
DUPLEX 16---101
TRIPLEX 03---101
TRIPLEX 10---101
TOWER A---242246
TRIPLEX 04---101
TRIPLEX 11---101
DUPLEX 05---101
DUPLEX 11---101
TOWER B---242448
TRIPLEX 05---101
TRIPLEX 12---101
DUPLEX 06---101

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building20

As on 7 Sep 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 32 buildings; the table lists the first 20.

225 of 288 construction stages are filed complete across 32 buildings. The stage furthest along is Sanitary fittings within the flats, at 99%.

DUPLEX 12100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats99%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing99%
TOWER C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats99%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing99%
TRIPLEX 06100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats99%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing99%
DUPLEX 01100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats99%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing99%
DUPLEX 07100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats99%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing99%
DUPLEX 13100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats99%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing99%
TOWER D100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats99%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing99%
TRIPLEX 07100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats99%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing99%
DUPLEX 02100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats99%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing99%
DUPLEX 08100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats99%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing99%
DUPLEX 14100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats99%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks99%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing99%
TRIPLEX 01100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats99%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing99%
TRIPLEX 08100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats99%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing99%
DUPLEX 03100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats99%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing99%
DUPLEX 09100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats99%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing99%
DUPLEX 15100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats99%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing99%
TRIPLEX 02100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats99%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing99%
TRIPLEX 09100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats99%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing99%
DUPLEX 04100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats99%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing99%
DUPLEX 10100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats99%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing99%

Progress on shared amenities19

As on 7 Sep 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes98%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes98%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes92%
Fire fightingNoNot applicable
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxYes95%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,536 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 7.50 cr
Cost incurredRs 7.50 cr
Spent of the estimate99.96%
BuildingWingEstimatedIncurred
TOWER ANARs 23.44 lakhRs 23.43 lakh
TRIPLEX 04NARs 23.44 lakhRs 23.43 lakh
TRIPLEX 11NARs 23.44 lakhRs 23.43 lakh
DUPLEX 05NARs 23.44 lakhRs 23.43 lakh
DUPLEX 11NARs 23.44 lakhRs 23.43 lakh
TOWER BNARs 23.44 lakhRs 23.43 lakh
TRIPLEX 05NARs 23.44 lakhRs 23.43 lakh
TRIPLEX 12NARs 23.44 lakhRs 23.43 lakh
DUPLEX 06NARs 23.44 lakhRs 23.43 lakh
DUPLEX 12NARs 23.44 lakhRs 23.43 lakh
TOWER CNARs 23.44 lakhRs 23.43 lakh
TRIPLEX 06NARs 23.44 lakhRs 23.43 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRUCHIR SHETH
EngineerZARANA ASSOCIATES

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/MAA00368/EX1/071218Applied Oct 2018; approved Dec 2018

Documents filed70

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA00368/EX1/071218 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)7 Sep 2019
Architect's certificate (Form 1)17 Aug 2019
Engineer's certificate (Form 2)17 Aug 2019
Site photograph, DUPLEX 1217 Aug 2019
Site photograph, DUPLEX 0117 Aug 2019
Site photograph, DUPLEX 0717 Aug 2019
Site photograph, DUPLEX 0217 Aug 2019
Site photograph, DUPLEX 0817 Aug 2019
Site photograph, DUPLEX 0317 Aug 2019
Site photograph, DUPLEX 0917 Aug 2019
Site photograph, DUPLEX 0417 Aug 2019
Site photograph, DUPLEX 1017 Aug 2019
Site photograph, DUPLEX 1117 Aug 2019
Site photograph, DUPLEX 0617 Aug 2019
Site photograph, TOWER C16 Aug 2019
Site photograph, TOWER C16 Aug 2019
Site photograph, TRIPLEX 0616 Aug 2019
Site photograph, DUPLEX 1316 Aug 2019
Site photograph, TOWER D16 Aug 2019
Site photograph, TOWER D16 Aug 2019
Site photograph, TRIPLEX 0716 Aug 2019
Site photograph, DUPLEX 1416 Aug 2019
Site photograph, TRIPLEX 0116 Aug 2019
Site photograph, TRIPLEX 0816 Aug 2019
Site photograph, DUPLEX 1516 Aug 2019
Site photograph, TRIPLEX 0216 Aug 2019
Site photograph, TRIPLEX 0916 Aug 2019
Site photograph, DUPLEX 1616 Aug 2019
Site photograph, TRIPLEX 0316 Aug 2019
Site photograph, TRIPLEX 1016 Aug 2019
Site photograph, TOWER A16 Aug 2019
Site photograph, TRIPLEX 0416 Aug 2019
Site photograph, TRIPLEX 1116 Aug 2019
Site photograph, DUPLEX 0516 Aug 2019
Site photograph, TOWER B16 Aug 2019
Site photograph, TRIPLEX 0516 Aug 2019
Site photograph, TRIPLEX 1216 Aug 2019
RERA registration certificate7 Oct 2017
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

94%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 12 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep PARAM GREENS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bill2,900+ in Vadodara

2 kmPARAM GREENSOther 259Dot size: filed unitsN

Filed coordinates, straight-line distance. 259 registered projects within 2 km.

Builder: AKSHAR CREATION

AKSHAR CREATION has 2 registrations on GujRERA, including PARAM AVENUE and PARAM GREENS. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if PARAM GREENS is delayed beyond 31 Oct 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of PARAM GREENS?

The registered promoter entity is AKSHAR CREATION, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in PARAM GREENS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at PARAM GREENS?

The professionals named in the filing: Architect: RUCHIR SHETH; Engineer: ZARANA ASSOCIATES. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PARAM GREENS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PARAM GREENS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PARAM GREENS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.