ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / ORCHID LIFE

Registration approved No litigation declared Residential/Group Housing project

ORCHID LIFE

By GOYAL HARIYANA ASSOCIATES

RG-KA-94105 · RERA PRM/KA/RERA/1251/446/PR/151223/006487 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Feb 2030Possession promisedno revision filed
0 of 18Construction stages donefurthest along: RCC or MS Framed structure, 96%
131 of 772Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 186 documents Report an error

ORCHID LIFE is a Residential/Group Housing project by GOYAL HARIYANA ASSOCIATES in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/151223/006487 on 15 Dec 2023. Possession is promised by 28 Feb 2030. 641 of the 772 units on this registration are recorded sold or booked, and 0 of 18 construction stages are filed complete.

At a glance

Project

  • NameORCHID LIFE
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
    • 560087
  • Pincode560087
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/151223/006487
  • ReraGenie IDRG-KA-94105

Builder

  • NameGOYAL HARIYANA ASSOCIATES
  • Entity typePartnership Firm
  • GSTIN29AAWFG9977E1ZC
  • Authorized SignatorySanjay Kumar Bajaj

Key dates

this monthRegisteredDec 2023PromisedFeb 2030

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on15 Dec 2023
  • Promised completion28 Feb 2030
  • Revised completionNone
  • Buildings5 building records
  • Documents filed186 files

Current status

83%641 of 772 units booked
56.9%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER A---1800180
TOWER B---1480148
TOWER C---1480148
TOWER D---1480148
TOWER E---1480148

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 18 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 96%.

Building: 62% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work95%
Foundation footing work95%
Upto Plinth Level95%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)75%
Retaining wall (All types)88%
RCC or MS Framed structure96%
Masonry Construction0%
Plastering inside , outside & Ceiling75%
Joinery: Doors, Windows, Ventilators etc42%
Basic work of Water supply, Sanitary and Electrification30%
Dadoing, Skirting, Flooring, Tiles work (All types)50%
Railing and Grill fixing85%
Electrification, Water supply and Sanitary Finishing60%
Painting20%
Fire prevention and fire fighting fitting and fixture with network50%
Weather Proof work(tile,concrete)48%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work95%
Internal and External work including landscapes as per sanctioned drawings10%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes30%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes50%
LiftsYes50%
Corridor/LobbiesYes40%
Fire escapesYes50%
Common entrance and exit for the building/common portico/foyer/verandahYes40%
BasementYes85%
TerraceYes20%
Outer WallYes65%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership8

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area29,238 sq m
Named landowners8
LandownerVillageDistrict
Goyal Hariyana Associates--
Goyal Hariyana Associates--
Goyal Hariyana Associates--
Goyal Hariyana Associates--
Goyal Hariyana Associates--
Goyal Hariyana Associates--
Goyal Hariyana Associates--
Goyal Hariyana Associates--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 657.50 cr
Cost incurredRs 373.91 cr
Spent of the estimate56.87%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 340.50 crRs 267.30 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 227.00 crRs 17.14 cr
On-site expenditure-Site OverheadRs 46.00 crRs 76.67 cr
On-site expenditure-Salaries of workersRs 39.00 crRs 7.37 cr
Payment of taxesRs 5.00 crRs 5.44 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSrimathi Adiga
EngineerVishnu Kumar
Chartered AccountantMahaveer Jain

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed186

As listed on the registration, under the names the promoter filed them with; the newest 80 of 186 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/151223/006487 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM-4 ORCHID LIFE Q2 26-27.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: FORM-5 ORCHID LIFE Q2 26-27.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM-6 ORCHID LIFE Q2 26-27.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4 RERA - Orchids Life - Q1 26-27 sd.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5, Q1,2026-27,Orchid Life.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM-6 ORCHID LIFE 30-06-2026.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form -4 RERA - Orchids Life - Q4 25-26 sd.pdf11 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form -5 ORCHID LIFE 31-03-2026.pdf11 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM-6 ORCHID LIFE 31-03-2026.pdf11 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form -4 RERA - Orchids Life - Q3 25-26 signed.pdf14 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5, Q3 2025-26, Orchid Life.pdf14 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM-6 ORCHID LIFE 31-12-2025.pdf14 Jan 2026
Clarification on Quarterly FilingFile: 1 Clarification on Quarterly Filing.pdf14 Dec 2023
Orchid Life Bank Accounts AffidavitFile: 2 Orchid Life Bank Accounts Affidavit.pdf14 Dec 2023
Source of Funds with supporting docsFile: 3 Source of Funds with supporting docs.pdf14 Dec 2023
Amenities and Common AreasFile: 4 Amenities and Common Areas.pdf14 Dec 2023
STP DesignFile: 5 STP Design.pdf14 Dec 2023
SRO guideline notification Self-attestedFile: 6 SRO guideline notification.pdf14 Dec 2023
RERA Bank AccountsFile: 7 RERA Bank Accounts.pdf14 Dec 2023
RIVIERA INFRA VENTURES LLP Financials 2022-23File: RIVIERA INFRA VENTURES LLP Financials 2022-23.pdf14 Dec 2023
GOYAL & CO PVT LTD Financials 2022-23File: GOYAL & CO PVT LTD Financials 2022-23.pdf14 Dec 2023
RCPL Financials -2022-23File: RCPL Financials -2022-23.pdf14 Dec 2023
RTC, survey 20-
Mutation, survey 20-
Encumbrance Certificate, survey 20-
Conversion/Alienation Order, survey 20-
Sale/Title/Gift Deed, survey 20-
Khatha, survey 20-
RTC, survey 21-
Mutation, survey 21-
Encumbrance Certificate, survey 21-
Conversion/Alienation Order, survey 21-
Sale/Title/Gift Deed, survey 21-
Khatha, survey 21-
RTC, survey 125/4-
Mutation, survey 125/4-
Encumbrance Certificate, survey 125/4-
Conversion/Alienation Order, survey 125/4-
Sale/Title/Gift Deed, survey 125/4-
Khatha, survey 125/4-
RTC, survey 125/5-
Mutation, survey 125/5-
Encumbrance Certificate, survey 125/5-
Conversion/Alienation Order, survey 125/5-
Sale/Title/Gift Deed, survey 125/5-
Khatha, survey 125/5-
RTC, survey 126/1-
Mutation, survey 126/1-
Encumbrance Certificate, survey 126/1-
Conversion/Alienation Order, survey 126/1-
Sale/Title/Gift Deed, survey 126/1-
Khatha, survey 126/1-
RTC, survey 126/5-
Mutation, survey 126/5-
Encumbrance Certificate, survey 126/5-
Conversion/Alienation Order, survey 126/5-
Sale/Title/Gift Deed, survey 126/5-
Khatha, survey 126/5-
RTC, survey 126/6-
Mutation, survey 126/6-
Encumbrance Certificate, survey 126/6-
Conversion/Alienation Order, survey 126/6-
Sale/Title/Gift Deed, survey 126/6-
Khatha, survey 126/6-
RTC, survey 127/3-
Mutation, survey 127/3-
Encumbrance Certificate, survey 127/3-
Conversion/Alienation Order, survey 127/3-

How this compares with Bengaluru Urban

83%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep ORCHID LIFE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmORCHID LIFEOther 89Dot size: filed unitsN

Filed coordinates, straight-line distance. 89 registered projects within 2 km.

Builder: GOYAL HARIYANA ASSOCIATES

GOYAL HARIYANA ASSOCIATES has 1 registration on RERA Karnataka, including ORCHID LIFE. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if ORCHID LIFE is delayed beyond 28 Feb 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ORCHID LIFE?

The registered promoter entity is GOYAL HARIYANA ASSOCIATES, a partnership firm as per the filing. Its GSTIN 29AAWFG9977E1ZC can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ORCHID LIFE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ORCHID LIFE?

The professionals named in the filing: Architect: Srimathi Adiga; Engineer: Vishnu Kumar; Chartered Accountant: Mahaveer Jain. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ORCHID LIFE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ORCHID LIFE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ORCHID LIFE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.